Sunset Lumber Co. v. Smith

272 P. 1068, 95 Cal. App. 307, 1928 Cal. App. LEXIS 457
California Court of Appeal·Decided December 6, 1928·No. Docket No. 6386.·Published·Cited by 6 cases

Opinion

CAMPBELL, J., pro tem.

This is an action to recover for materials furnished in the erection and construction of the ‘‘ Soquel Union Grammar School” in the town of Soquel, Santa Cruz County. The action is brought against E. Potter Smith, the contractor to whom the Board of Trustees of the Soquel Union School District let the general contract for the construction of the school building and against James K. Nelson and J. J. Stevenson, the sureties on the contractor’s bond, the members of the school board and the school district itself. The action is primarily one against the contractor to recover for the materials furnished and used in the construction of the school building. The contractor defaulted and the other defendants answered. Defendant James K. Nelson, one of the sureties on the contractor’s bond, is the only defendant who has appealed.

Appellant presents the following points as grounds for a reversal of the judgment: “(1) The demurrer of this defendant should have been sustained because of misjoinder of causes of action and misjoinder of parties defendant; (2) Plaintiff’s action is barred by the provisions of the various lien law statutes of the state of California; (3) The defendant James K. Nelson is not liable by reason of the variance from the provisions of the bond; (4) The defendant James E. Nelson is not liable by reason of the settlement by the principal without the consent of the surety; (5) Plaintiff has failed to comply with the provisions of the Public Works Act; (6) The evidence is insufficient to justify the decision of the trial court; (7) The complaint of plaintiff does not state a cause of action against this defendant; (8) The court erred in striking out the equitable defense of estoppel; (9) The court erred in including in its findings an award of $750.00 counsel fees.”

*312 As to appellant’s first contention it may be said that this action was primarily against the contractor and his bondsmen. The contractor and bondsmen were all parties to the bond in question. The contractor Smith signed it as principal and appellant Nelson and defendant Stevenson signed as sureties. Such joinder of principal and sureties in an action is authorized (Code Civ. Proc., sec. 383; Rice Sureties Co. v. Daggs, 63 Cal. App. 273, 277 [218 Pac. 484]; Rodabaugh v. Kauffman, 53 Cal. App. 676, 682 [200 Pac. 747]). In regard to the joinder of the school dis-

trict and trustees it may be said that while it was not necessary to join them, we fail to see how appellant has been prejudiced or injured thereby. Plaintiff’s cause of action arose out of his contract with the contractor Smith, appellant’s principal, and while the liability of the trustees or the school district, if any, might differ, nevertheless it is based upon plaintiff’s contract with Smith, the contractor, and in order to prevail against any of these defendants, plaintiff would be compelled to prove the performance of his contract with Smith to furnish materials for the construction of this school building. It is well settled that an error overruling a demurrer for misjoinder of parties defendant after a trial on the merits is not ground for the reversal of the judgment unless the party demurring has been misled to his prejudice or the error otherwise appears to have been injurious (2 Cal. Jur. 1012; Asevedo v. Orr, 100 Cal. 200 [34 Pac. 777]; Hirschfield v. Weill, 121 Cal. 14 [53 Pac. 402]). Were we to concede “that the special demurrer for misjoinder might have been properly sustained by the trial court, the concession is of no avail here. This for the reason that under section 4y2 of article VI of the constitution it would not be said that the overruling of the demurrer was such an error as had produced a miscarriage of justice.” (Trask v. Garza, 51 Cal. App. 743 [197 Pac. 807].)

• Appellant contends that because plaintiff’s procedure is a compliance with section 1184 of the Code of Civil Procedure, he cannot enforce the liability of bondsmen given pursuant to the Public Works Act of 1919. A reading of the Public Works Act demonstrates that such act is a remedy in addition to and cumulative with the remedy given by section 1184 of the Code of Civil Procedure and *313 that the two remedies are intended to be co-operative in effect. There is nothing in the Public Works Act which expressly or impliedly says that a materialman must elect between these two remedies or that if he seeks one, he waives the other. On the contrary the act of 1919 expressly makes the right to recover on the bond an additional and cumulative remedy, for in section 1 thereof it is provided that unless the bond is filed, no claim shall be allowed in favor of the contractor. This, obviously, is a penalty placed on the contractor for failure to file the bond, but the act provides that, nevertheless, materialman shall be entitled to be paid in accordance with section 1184 of the Code of Civil Procedure. Hence it is apparent that the act of 1919 is not an exclusive remedy, but is a cumulative one, and one created in view of the rights given under section 1184. The only condition which must be performed by the materialman to establish his right against the surety under the act of 1919 is that “he shall file with the body by whom the contract was awarded a verified statement of his claim, together with a statement that the same has not been paid.” Here plaintiff has filed such verified statement, as shown by the pleadings and the claim admitted in evidence. The fact that this statement is denominated “A Notice to Withhold,” or that it is also sufficient to comply with section 1184 of the Code of Civil Procedure, does not make it any the less sufficient as a compliance with the Public Works Act. It is a verified statement containing an itemized list of the materials furnished, together with a statement that the same has not been paid. Appellant apparently urges that until there is a pro rata p'ayment under section 1184 of the Code of Civil Procedure, no cause of action exists against the bondsmen. The act of 1919 does not require that plaintiff first proceed under section 1184 et seq. The period within which suit may be commenced on the bond as provided in the act of 1919 shows that there need be no steps taken under section 1184 or any waiting for a pro rata payment. The act of 1919 requiring that action on the bond be commenced within ninety days following the period within which claims of lien must be filed for record, it is obvious that if a materialman was first required to bring an action under section 1184a, a period of time would not only possibly but probably expire *314 in excess of ninety days from the time when claims of lien must be filed for record, and, hence, the bondsmen would by insisting upon the plaintiff first exhausting his rights pursuant to section 1184 et seq. avoid liability for any portion of a materialman’s claim. Such construction would defeat the purpose of the act.

If plaintiff has succeeded in reducing his claim against the bondsmen by complying with the provisions of section 1184 et seq., the bondsmen are relieved to that extent and cannot consistently complain.

Free access — add to your briefcase to read the full text and ask questions with AI

Sunset Lumber Co. v. Smith, 272 P. 1068, 95 Cal. App. 307, 1928 Cal. App. LEXIS 457 (Cal. Ct. App. 1928).

272 P. 1068 (Sunset Lumber Co. v. Smith) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Consolidated Electrical Distributors, Inc. v. Kirkham, Chaon & Kirkham, Inc.
18 Cal. App. 3d 54 (California Court of Appeal, 1971)
Wagner v. Shapona
267 P.2d 378 (California Court of Appeal, 1954)
Lewis & Queen v. S. Edmondson & Sons
248 P.2d 973 (California Court of Appeal, 1952)
Cassaretto v. City & County of San Francisco
62 P.2d 777 (California Court of Appeal, 1936)
Pneucrete Corp. v. United States Fidelity & Guaranty Co.
46 P.2d 1000 (California Court of Appeal, 1935)
Hammond Lumber Co. v. Richardson Bldg. & Eng'g Co.
285 P. 851 (California Supreme Court, 1930)