Sunpower v. Arizona State Registrar of Contractors

803 P.2d 430, 166 Ariz. 437, 59 Ariz. Adv. Rep. 41, 1990 Ariz. App. LEXIS 153
CourtCourt of Appeals of Arizona
DecidedApril 26, 1990
Docket2 CA-CV 89-0232
StatusPublished
Cited by8 cases

This text of 803 P.2d 430 (Sunpower v. Arizona State Registrar of Contractors) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sunpower v. Arizona State Registrar of Contractors, 803 P.2d 430, 166 Ariz. 437, 59 Ariz. Adv. Rep. 41, 1990 Ariz. App. LEXIS 153 (Ark. Ct. App. 1990).

Opinion

OPINION

HATHAWAY, Judge.

This appeal arises from the superior court’s decision affirming the Arizona State Registrar of Contractor’s (Registrar) order following a hearing requiring the appellant, Sunpower of Arizona, Inc. (Sun-power), to remove solar equipment it had installed and to return to appellees Stumph and Kessler the amounts they paid for the equipment and installation. Sunpower argues that the Registrar’s order (1) exceeded its regulatory authority under A.R.S. § 32-1154; (2) was a violation of the separation of powers contained in article 3 of the Arizona Constitution; (3) appellee Kessler’s complaint does not fall within the applicable statute of limitations as mandated by A.R.S. § 32-1155(A); and, (4) the transcript was incomplete, thus preventing proper review by the superior court.

FACTS

In December 1985, appellees Stumph and Kessler contracted with Sunpower for the purchase of solar equipment and installation of it at their residences. The equipment was to provide additional hot water and all the heat for their residences. The installations were completed in June 1986. Appellees both filed written complaints with the Registrar on January 6, 1988, regarding the installation and operation of the solar heating equipment. On February 17, 1988, the Registrar sent a corrective work order notice to Sunpower for each complaint with directions to “[pjroperly repair/replace necessary components of solar hot water & heating system to ensure systems operate as designed.” Sunpower did *439 attempt to repair the systems, but the promised result that the systems would independently provide a habitable degree of home heating was never achieved.

Subsequently, on July 28, 1988, the Registrar served Sunpower with a formal citation and complaint. An administrative hearing was held on September 29, 1988. The hearing officer made the following findings of fact which were adopted and approved by the Registrar:

******
3. The agreed purchase price for each contract was ultimately paid in full. It is found by the weight of credible evidence that neither installation was completed or substantially completed more than two years before the filing of the respective separate complaints hereon [sic] on January 6, 1988. Consequently, any asserted defense based upon the expiration of the applicable statute of limitations must be rejected with respect to the specific contents of each complaint which, essentially, alleged that the systems, and in particular the last additions thereto, were not fit for the intended purposes for which they were represented and sold. ******
5. It is determined that Complainants demonstrated by a preponderance of competent, probative and credible testimony that Respondent’s sales representative, who is found to have possessed at least apparent authority, communicated express assurances to both Complainants which were intended to and which did, in fact, induce favorable action culminating in the contractural [sic] arrangements for the 1986 installation. These assurances generated the belief on the part of both the homeowners that the extra panel and storage tank to be added would improve upon their then-existing systems to such an extent that no back-up household system would be needed on a regular basis to heat the interior space within the residences. The evidence revealed that neither contract contemplated the furnishing or installing of added registers or the enlargement of those installed in 1984.
6. Although the systems’ capabilities for heating the household water supplies continued to be adequate, very little, if any, improvement was experienced with respect to heating the interior space. In any event, the system, as augmented, was shown not to independently enable a habitable degree of heating in either home____

Further, the Registrar adopted the hearing officer’s conclusions of law establishing that Sunpower had violated the provisions of A.R.S. §§ 32-1154(A)(7) and (3), namely, A.C.R.R. R4-9-108, which details workmanship standards for contractors. The statute sets forth the grounds for suspension of a contractor’s license:

A. The holder of a license pursuant to this chapter shall not commit any of the following acts or omissions:
******
(3) Violation of any rule adopted by the registrar.
******
(7) The doing of a wrongful or fraudulent act by the licensee as a contractor resulting in another person being substantially injured.

A.R.S. § 32-1154(A).

The hearing officer also concluded as a matter of law that the Registrar could impose conditions against Sunpower’s contractor’s license for the violations under A.R.S. § 32-1154(A). Therefore, on the facts of the case, the Registrar determined the appropriate and equitable remedy was the removal of the equipment and return of the full amount paid as a condition for Sunpower’s continued operation under its contractor’s license.

STANDARD OF REVIEW

When reviewing a superior court judgment affirming administrative action, we will determine whether there is substantial evidence to support the decision. Sundown Imports, Inc. v. Arizona Dep’t of Transp., 115 Ariz. 428, 565 P.2d 1289 (App.1977). However, we will independently determine issues of law. Havasu Heights Ranch and Dev. Corp. v. State *440 Land Dep’t of State of Arizona, 158 Ariz. 552, 764 P.2d 37 (App.1988); Eshelman v. Blubaum, 114 Ariz. 376, 560 P.2d 1283 (App.1977).

REGULATORY AUTHORITY UNDER § 32-1154

Sunpower argues that the Registrar’s order to remove the solar equipment it sold and installed and to return the monies paid for the sales and installations was outside the power granted by the legislature. The superior court found that the Registrar’s action was contemplated by and within the scope of A.R.S. § 32-1154(B), which provides as follows:

B. The registrar may ... temporarily suspend, with or without imposition of specific conditions ... any or all licenses issued under this chapter if the holder of the license ... is guilty of or commits any of the acts or omissions set forth in subsection A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pinnamaneni v. Arizona Registrar of Contractors
347 P.3d 593 (Court of Appeals of Arizona, 2015)
Twin Peaks Construction Inc. v. Weatherguard Metal Construction, Inc.
154 P.3d 378 (Court of Appeals of Arizona, 2007)
Bentivegna v. Powers Steel & Wire Products, Inc.
81 P.3d 1040 (Court of Appeals of Arizona, 2004)
Lake Havasu City v. Arizona Department of Health Services
48 P.3d 499 (Court of Appeals of Arizona, 2002)
Arizona Health Care Cost Containment System v. Bentley
928 P.2d 653 (Court of Appeals of Arizona, 1996)
Cactus Wren Partners v. Arizona Department of Building & Fire Safety
869 P.2d 1212 (Court of Appeals of Arizona, 1993)
Berenter v. Gallinger
839 P.2d 1120 (Court of Appeals of Arizona, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
803 P.2d 430, 166 Ariz. 437, 59 Ariz. Adv. Rep. 41, 1990 Ariz. App. LEXIS 153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sunpower-v-arizona-state-registrar-of-contractors-arizctapp-1990.