Summers Group, Inc. v. Tempe Mechanical, LLC

299 P.3d 743, 231 Ariz. 571, 656 Ariz. Adv. Rep. 15, 2013 WL 1136417, 2013 Ariz. App. LEXIS 39
CourtCourt of Appeals of Arizona
DecidedMarch 19, 2013
DocketNo. 1 CA-CV 12-0086
StatusPublished
Cited by5 cases

This text of 299 P.3d 743 (Summers Group, Inc. v. Tempe Mechanical, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Summers Group, Inc. v. Tempe Mechanical, LLC, 299 P.3d 743, 231 Ariz. 571, 656 Ariz. Adv. Rep. 15, 2013 WL 1136417, 2013 Ariz. App. LEXIS 39 (Ark. Ct. App. 2013).

Opinion

OPINION

OROZCO, Judge.

¶ 1 Summers Group, Inc., doing business as Rexel Phoenix Electric (Rexel), appeals the trial court’s order holding Rexel as the only liable party for ML Manager’s attorney fees.1 For the following reasons, we reverse and remand to the trial court to apportion the attorney fees consistent with this opinion.

FACTUAL AND PROCEDURAL HISTORY

¶ 2 Rexel sold electrical materials to J.C. York Electrical Contracting, Inc. to be used in the construction of lofts on property owned by The Metropolitan Lofts, L.L.C. (Metro Lofts). Rexel was not compensated for the materials it provided and on June 26, 2008, recorded a mechanics’ lien on the property owned by Metro Lofts. Subsequently, other companies filed mechanics’ liens against the property for non-payment: Tempe Mechanical, LLC (Tempe); Pama Drywall, Inc. (Parra); Paramount Iron, Inc. (Paramount); Wilson Electric Services Corporation (Wilson); Azteca Glass, Inc. (Azteca); Cannon Door and Trim (Cannon); and Lickety Split Construction, Inc. (Lickety).

¶ 3 On December 24, 2008, Rexel filed a complaint against numerous defendants, alleging multiple causes of action: breach of contract, breach of personal guaranty, breach of prompt payment act, unjust enrichment, and foreclosure of its mechanics’ lien for materials that it had provided and not been paid.2 Rexel named all other mechanics’ lienholders as defendants in the complaint pursuant to Arizona Revised Statutes (A.R.S.) section 33-996 (2007). An order of default was entered against Lickety, Cannon and Wilson for their failure to file an answer to the complaint and Azteca was dismissed as a party.

¶ 4 On July 2, 2008, Tempe recorded a mechanics’ lien on the property and filed an answer to Rexel’s complaint on February 11, 2009.3 Parra recorded a mechanics’ lien on July 30, 2008 and filed an answer to Rexel’s complaint on January 26, 2009. Paramount recorded a mechanics’ lien on August 26, [573]*5732008 and filed an answer to Rexel’s complaint on February 17, 2009. We refer to Rexel, Tempe, Parra and Paramount collectively as the Remaining Lien Claimants.

¶ 5 Mortgages, Ltd., a defendant in this ease, filed bankruptcy and the case was removed to bankruptcy court. The parties agreed that the bankruptcy court would only determine the priority of all of the liens. The bankruptcy court determined that ML Manager4 had priority over all the other mechanics’ liens. The ease was then remanded to superior court for determination of the validity of the mechanics’ liens, interest owed and attorney fees.

¶ 6 ML Manager filed an application for attorney fees pursuant to A.R.S. §§ 33-998.B (2007) and 12-341.01 (Supp.2012).5 After oral argument, the court granted ML Manager its attorney fees under § 33-998.B, but only against Rexel. The court stated that “the record does not indicate that any party other than [Rexel] caused ML [Manager] to challenge its lien priority. Apportioning fees to other [Remaining Lien Claimants] would not be appropriate.”

¶ 7 Rexel timely appealed.6 We have jurisdiction under A.R.S. §§ 12-120.21.A1 (2003) and -2101.A1 (Supp.2012).

DISCUSSION

¶ 8 The sole issue on appeal is whether under A.R.S. § 33-998.B, all Remaining Lien Claimants should be responsible for paying ML Manager’s attorney fees award in proportion to their respective lien claims.

¶ 9 The grant or denial of a request for attorney fees is within the discretion of the trial court and will not be overturned if it is reasonably supported by the record. West v. Salt River Agric. Improvement & Power Dist., 179 Ariz. 619, 626, 880 P.2d 1165, 1172 (App.1994). When the application of an attorney fees statute involves' statutory interpretation, we review the trial court’s ruling de novo. Keystone Floor & More, LLC v. Ariz. Registrar of Contractors, 223 Ariz. 27, 29, ¶ 7, 219 P.3d 237, 239 (App.2009) (stating that the standard of review is de novo when reviewing statutory attorney fees awards arising out of a contract dispute).-

Lien Priority Challenge

¶ 10 Mechanics’ lien statutes and Arizona case law establish procedures to be followed when a mechanics’ lien claimant initiates a foreclosure action on a lien. First, a mechanic lienor must sue each party against whom it seeks to assert its lien within six months after recording its lien. Scottsdale Mem’l Health Sys., Inc. v. Clark, 157 Ariz. 461, 469-70, 759 P.2d 607, 615-16 (1988). After an action is commenced by one mechanic lienor, “[p]ersons claiming liens who fail or refuse to become parties plaintiff shall be made parties defendant, and those not made a party, may, at any time before final hearing, intervene.” A.R.S. § 33-996. After all the lien claimants are served, in order to assert their lien priority, each must file an answer or cross-claim. A.R.S. § 33-998.A Finally, pursuant to A.R.S. § 33-998.A, if a lien claimant is made a party defendant to an action brought by another lien claimant, the timely filing of an answer or cross-claim asserting the lien, within six months of recording the lien, shall be deemed the commencement of an action.

¶ 11 In order to enforce its lien priority, Rexel named all of the other mechanics’ lien claimants as parties in the complaint. See Lilley v. J.D. Halstead Lumber Co., 42 Ariz. 546, 557, 28 P.2d 616, 620 (1934) (stating that the Legislature intended “that all claims for [574]*574liens against a certain piece of property should be litigated in one action, and that all lien claimants should be parties thereto and their rights determined therein”); see also Scottsdale Mem’l, 157 Ariz. at 469-70, 759 P.2d at 615-16 (recognizing that a mechanic lienor must sue each party against whom he seeks to assert his lien; however, enforcement is barred as to any party not sued within six months).

¶ 12 In this case, by filing answers to the allegations set forth in Rexel’s complaint, the Remaining Lien Claimants each commenced an action asserting their lien priority. Because the Remaining Lien Claimants were involved in the litigation, the bankruptcy court’s decision on the lien priority issue also affected their claims. Therefore, we hold that the Remaining Lien Claimants caused ML Manager to defend its lien priority. See id.

Attorney Fees Award Under A.R.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Perez v. Corral
Court of Appeals of Arizona, 2024
Heritage v. Weinberg
Court of Appeals of Arizona, 2021
Foreclosure v. Farmington
Court of Appeals of Arizona, 2020
Marsh v. Mayer
Court of Appeals of Arizona, 2015
Marsh v. Coles
361 P.3d 383 (Court of Appeals of Arizona, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
299 P.3d 743, 231 Ariz. 571, 656 Ariz. Adv. Rep. 15, 2013 WL 1136417, 2013 Ariz. App. LEXIS 39, Counsel Stack Legal Research, https://law.counselstack.com/opinion/summers-group-inc-v-tempe-mechanical-llc-arizctapp-2013.