Summers Drilling & Blasting, Inc. v. Goodwin & Goodwin, Inc.

2020 Ark. App. 194, 598 S.W.3d 853
CourtCourt of Appeals of Arkansas
DecidedMarch 18, 2020
StatusPublished
Cited by1 cases

This text of 2020 Ark. App. 194 (Summers Drilling & Blasting, Inc. v. Goodwin & Goodwin, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Summers Drilling & Blasting, Inc. v. Goodwin & Goodwin, Inc., 2020 Ark. App. 194, 598 S.W.3d 853 (Ark. Ct. App. 2020).

Opinion

Cite as 2020 Ark. App. 194 ARKANSAS COURT OF APPEALS DIVISION IV No. CV-19-489

Opinion Delivered: March 18, 2020

SUMMERS DRILLING & BLASTING, APPEAL FROM THE SEBASTIAN INC., A/K/A SUMMERS DRILLING, COUNTY CIRCUIT COURT, FORT INC. SMITH DISTRICT APPELLANT [NO. 66FCV-17-696]

V. HONORABLE J. MICHAEL FITZHUGH, GOODWIN & GOODWIN, INC. JUDGE APPELLEE AFFIRMED IN PART; REVERSED AND REMANDED IN PART

PHILLIP T. WHITEAKER, Judge

The appellant Summers Drilling & Blasting, Inc. (SD&B), a subcontractor, was

sued by the appellee Goodwin & Goodwin Inc. (Goodwin), a general contractor, under the

theory of breach of contract. The Sebastian County Circuit Court found that SD&B had

breached the parties’ subcontract by failing to perform its work in accordance with the

contract’s plans and specifications and ultimately by refusing to complete the contract. The

court awarded Goodwin $132,792.26 in damages, plus costs and attorney’s fees. On

appeal, SD&B argues (1) that Goodwin’s claims sound in tort, not in contract; (2) that

even if Goodwin’s claims were properly pled as a contract action, Goodwin failed to prove

a breach of that contract; and (3) that the court’s award of damages was not supported by the evidence presented. We disagree with SD&B’s first two arguments on appeal but agree

that a remand is necessary for a recalculation of damages.

2 I. Facts and Procedural History

Goodwin is a general contractor employed by the Arkansas Highway and

Transportation Department (AHTD) and the City of Fayetteville to assist in the Porter

Road–Highway 112/71B Widening and Interchange Project (“the Project”) in Fayetteville,

Arkansas. In December 2016, Goodwin obtained and accepted a bid from SD&B in

which SD&B agreed to drill and blast rock along a designated route of the Project for the

relocation of an existing sewer line, and Goodwin agreed to pay SD&B $181 per blasted

foot with a 1,350-foot minimum.

SD&B began work on the project. After having completed 1,204 linear feet of work,

it sent Goodwin an invoice requesting $217,924 for services rendered. Goodwin paid

$185,235.40, or 85 percent of the invoice less a 15 percent retainage. Approximately

halfway through the project, Goodwin discovered that certain areas blasted by SD&B were

not as deep as required. As a result, Goodwin rented equipment and employed crews to

hammer to the required depth, resulting in a delay of the project. SD&B subsequently

removed its equipment from the job site.1 At the time of withdrawal, SD&B had submitted

two other invoices in the amounts of $28,598 for 158 linear feet, and $32,761 for 181

linear feet. Goodwin did not pay these two invoices. In total, SD&B invoiced Goodwin

1 When SD&B withdrew from the project, it had blasted 1,540 feet, but the project plans specified relocation of approximately 1,650 linear feet of sewer line.

3 $279,283 for the work completed, but Goodwin paid only $185,235.40, or 85 percent of

the original invoice.

In July 2017, Goodwin filed suit against SD&B for breach of contract. Goodwin

alleged that SD&B had breached its contract by failing to blast to the depths specified by

the Project plans and in failing to complete the work. SD&B denied any breach,

contending that the written contract specified only a minimum distance to be blasted—

1,350 feet—and made no mention of a required depth. Because it had blasted the

minimum distance specified in the bid and because drilling to a required depth was not an

express term of the contract, SD&B claimed that there could be no breach.

The parties presented their dispute to the court at a bench trial. The circuit court

was presented conflicting positions and evidence concerning the terms of the agreement

between the parties and the performance of the parties pursuant to the terms of the

agreement. Goodwin took the position and presented evidence that its contract with

SD&B required performance under the terms and specifications of the Project plans that

Goodwin had with AHTD and the City of Fayetteville; that those Project plans detailed the

depth at which the sewer pipes were to be positioned; and that SD&B failed to meet the

depth specifications of the Project plans. SD&B took the position and presented evidence

that its bid constituted the written contract between the parties and that this written

contract was silent as to required depths. SD&B also contended that Goodwin never

provided the depth specifications of the Project plans and had not provided a suitable

4 blasting site in that there was an unacceptable amount of overburden 2 hindering its ability

to effectively blast. Goodwin disagreed and presented evidence that it had provided the

Project plans to SD&B and contended that SD&B had specified in the agreement that the

naturally occurring overburden should remain in place in order to prevent flooding of the

ditches.

After hearing all the evidence and reviewing the documents provided, the court

made specific findings concerning the parties’ agreement: (1) the parties had entered into a

contract; (2) the contract obligated SD&B to blast rock to grade; and (3) SD&B breached

the contract by not blasting to the required depths under the contract and had left the job

prior to completion. Concerning overburden, the court found that while there was some

dispute as to the removal of overburden, Goodwin had performed as required under the

contract. Concerning damages, the court found Goodwin was damaged as a result of

SD&B’s breach. The court calculated damages equal to the amount Goodwin incurred to

complete the project less the amount it would have paid SD&B if the contract had been

performed without breach, awarding Goodwin $132,792.26 in damages. SD&B appeals.

II. Standard of Review

SD&B appeals the judgment of damages from a breach-of-contract cause of action

entered after a bench trial. In appeals from civil bench trials, our standard of review on

appeal is not whether there is substantial evidence to support the findings of the court but

2 The term “overburden” is used to describe soil and ancillary material above the bedrock in a given area.

5 whether the court’s findings were clearly erroneous or clearly against the preponderance of

the evidence. Barnes v. Wagoner, 2019 Ark. App. 174, at 3, 573 S.W.3d 594, 595–96. A

finding is clearly erroneous when, although there is evidence to support it, the

reviewing court on the entire evidence is left with a firm conviction that a mistake has been

made. Id. Where the issue is one of law, our review is de novo. Id.

6 III. Analysis

A. Negligence v. Breach of Contract

In its first point on appeal, SD&B argues that Goodwin’s cause of action actually

sounds in negligence rather than in contract and that Goodwin failed to plead or prove a

negligence claim. Essentially, SD&B argues that Goodwin’s challenge is to the sufficiency

of its performance under the contract and not to the breach of any specific provision of the

contract. SD&B then concludes that because it did not breach a specific provision of the

contract, the judgment against SD&B should be reversed, along with the court’s award of

attorney’s fees, which are available only in breach-of-contract actions.

We begin analyzing SD&B’s argument by noting that the question of whether a

cause of action sounds in tort or in contract usually arises in the context of either

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Summers Drilling & Blasting, Inc. v. Goodwin & Goodwin, Inc.
2021 Ark. App. 267 (Court of Appeals of Arkansas, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2020 Ark. App. 194, 598 S.W.3d 853, Counsel Stack Legal Research, https://law.counselstack.com/opinion/summers-drilling-blasting-inc-v-goodwin-goodwin-inc-arkctapp-2020.