Keith Capps Landscaping & Excavation, Inc. v. Van Horn Construction, Inc.

2014 Ark. App. 638, 448 S.W.3d 207
CourtCourt of Appeals of Arkansas
DecidedNovember 12, 2014
DocketCV-14-309
StatusPublished
Cited by5 cases

This text of 2014 Ark. App. 638 (Keith Capps Landscaping & Excavation, Inc. v. Van Horn Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keith Capps Landscaping & Excavation, Inc. v. Van Horn Construction, Inc., 2014 Ark. App. 638, 448 S.W.3d 207 (Ark. Ct. App. 2014).

Opinion

RITA W. GRUBER, Judge.

| iThis is a breach-of-contract case filed by appellee, Van Horn Construction, Inc., a general contractor, against appellant, Keith Capps Landscaping & Excavation, Inc., a subcontractor. After a bench trial, the • circuit court found that Capps had breached the parties’ subcontract by failing to perform the work in accordance with the contract’s plans and specifications and ultimately by refusing to complete the contract. The court awarded Van Horn $245,682 in damages, plus costs and attorneys’ fees. On appeal, Capps argues that the trial court erred in finding that it breached the subcontract and in awarding an amount in damages that is in excess of the actual “reasonable damages.” We find no error and affirm the judgment of the circuit court.

In September 2010, Van Horn was awarded the bid as general contractor for the expansion of the Searcy water-treatment plant. In connection with that project, Van Horn |2sought subcontractor bids for the demolition and earthwork from various firms, including Capps. Capps submitted two bids, which Van Horn rejected because it determined that the amount of fill was overestimated in one bid and underestimated in the other. Van Horn accepted Capps’s third proposal, and the parties executed a subcontract on January 3, 2011, in which Capps agreed to “[f]ur-nish all required labor, equipment, and materials to complete the dirtwork for the Searcy Water Treatment Plant Expansion per plans, specifications, and addenda by Garver Engineers.” The contract included, among other tasks, excavation and fill for the sedimentation basin. In exchange for this work, Van Horn agreed to' pay Capps $131,700.

There was some confusion in the beginning of the project about the type of fill material Capps could use for the sedimentation basin. 1 In this project, the basin was to be set on fill material that was placed in layers, or lifts. Each lift was designed to be six to eight inches high and had to be compacted and tested for proper compaction and moisture content before another lift was placed on top of it. The specifications required that “class 7” material be used, but Keith Capps, the owner of Capps, testified that he understood from Van Horn when he submitted bid proposals that he could use shale, which is not a class 7 material and which is a considerably cheaper material. Van Horn eventually convinced Wendell Williams, who was the project-construction observer for the project engineer, and the geotechnical engineering firm, Grubbs Engineering, to allow Capps to use material that it submitted for ¡^testing from its “borrow pit,” which was originally brought to the site for this purpose. The borrow pit included shale.

However, when Capps began work on the sedimentation basin, numerous tests' of its lifts failed—generally due either to the moisture content being too high or the shale not being sufficiently broken up, or processed—and Capps was required to constantly rework the lifts and reprocess the material, causing considerably more work and expense than it had anticipated. The project manager for Van Horn, Mark Hurley, testified that when shale is “dug out,” it comes out in large chunks. The specifications called for the material to be processed to a certain gradation to be properly compacted. Thus, Capps was required to process the material before placing it to meet the moisture and compaction requirements. In addition, Mr. Hurley testified that Capps was attempting to place the fill in layers that were too thick rather than placing it in six-to-nine-inch layers as the specifications required.

Although Mr. Hurley testified that the plans and specifications were always available for Capps’s review on the company website and indeed had been brought to a meeting with Capps before Capps submitted his third proposal, Keith Capps testified that he did not see the plans and specifications for the project until the day Van Horn picked up Keith’s copy of the signed subcontract. Keith signed the contract, which included specifications regarding the lifts and fill material, without reviewing the specifications. He testified that he was instructed by Van Horn before the contract was signed to use shale for the fill material because it was cheaper than other fill material. Keith also testified that it was his understanding that he would be allowed to stockpile material next to the fill site but that after the project began, he was |4required to stockpile material 250 yards away and use a loader and dump truck to move it. He said that he had not anticipated this extra work and expense. He said that he told Van Horn that it was impossible to accomplish the lifts with the material he was using, but he was unable to get the matter resolved. He attempted to get Van Horn to agree to a change order to help with the processing or use a different material, but according to Keith, Van Horn refused. Mr. Hurley testified that Van Horn did offer to split the cost of “B stone” that did not require as much processing to use as fill, but Capps declined the offer and quit the project.

Van Horn notified Capps pursuant to Article 10 of the subcontract that Capps had forty-eight hours to return to the job or Van Horn would terminate the contract. Article 10 states in pertinent part as follows:

If Subcontractor persistently or repeatedly fails or neglects to carry out the work or otherwise to perform in accordance with the Subcontract, Contractor may, at its option and after forty-eight (48) hours notice to Subcontractor ... (ii) declare this Subcontract terminated, take possession of all materials, tools and appliances belonging to Subcontractor whether on the job site or stored elsewhere pursuant to agreement, and either complete the work itself or contract with other parties for the completion thereof.

When Capps did not return to finish the project, Van Horn completed the job by hiring other subcontractors, obtaining fill material and rental equipment, and performing some of the work itself. Van Horn submitted an itemized list of the costs to complete the project and the liquidated damages Van Horn was required to pay to the owner for the delay in completing the contract.

Van Horn then brought a breaeh-of-con-tract claim against Capps. Capps counterclaimed for breach of contract, essentially alleging that Van Horn breached the 1 .^contract by refusing to issue a change order for the change in fill material. After a hearing, the circuit court found that Capps breached the contract by “failing to perform the work in accordance with the plans and specifications and ultimately refused to complete its contract.” It also determined that all prior negotiations and proposals of Capps merged into the subcontract. The court noted that the cost to Van Horn to complete the work was $222,852, giving Capps credit for the remaining contract balance for work not performed by Capps. Finally, the circuit court found that Capps’s failure to perform the work delayed the project, causing Van Horn to incur damages pursuant to Van Horn’s contract with the city of Searcy. Van Horn-negotiated the liquidated-damages amount it would have owed the city for the delay from $141,000 ($1,000 per day of delay) to $96,541.94 (the cost of the excess onsite engineering services paid by the city due to the delay). The court allocated $28,280 of the $96,541.94 to Capps for a -total award of damages of $245,632.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Montie Hobson v. George W. Hobson
2025 Ark. App. 311 (Court of Appeals of Arkansas, 2025)
Summers Drilling & Blasting, Inc. v. Goodwin & Goodwin, Inc.
2020 Ark. App. 194 (Court of Appeals of Arkansas, 2020)
Barnes v. Wagoner
2019 Ark. App. 174 (Court of Appeals of Arkansas, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2014 Ark. App. 638, 448 S.W.3d 207, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keith-capps-landscaping-excavation-inc-v-van-horn-construction-inc-arkctapp-2014.