Summerall Electric Co. v. Church of God at Southaven

25 So. 3d 1090, 2010 Miss. App. LEXIS 11, 2010 WL 22551
CourtCourt of Appeals of Mississippi
DecidedJanuary 5, 2010
Docket2008-CA-02120-COA
StatusPublished
Cited by3 cases

This text of 25 So. 3d 1090 (Summerall Electric Co. v. Church of God at Southaven) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Summerall Electric Co. v. Church of God at Southaven, 25 So. 3d 1090, 2010 Miss. App. LEXIS 11, 2010 WL 22551 (Mich. Ct. App. 2010).

Opinion

MYERS, P.J.,

for the Court.

¶ 1. Summerall Electric Company, Inc., Don South Plumbing, Inc., and South and Son Construction Company, Inc., (collectively, the subcontractors) brought suit against the Church of God at Southaven (the Church), alleging that the Church, as the property owner, was liable for costs owed to the subcontractors by the general contractor, National Church Services, Inc. (NCS), which was not a party to the suit. 1 The subcontractors alleged that they had not been paid for their work in the construction of a sanctuary building.

¶ 2. The Church executed a “Construction Agreement” with NCS on September 24, 2005, for the construction of the sanctuary building. The contract price was stated as $1.1 million, plus the cost of the surety bond. NCS engaged the services of Rick Nealy, a member of the Church, as its construction superintendent for the project. 2 At the time, NCS did not hold a Mississippi contractors’ license; it claimed to be seeking one through a reciprocacy agreement with South Carolina. 3 The City of Southaven nonetheless allowed NCS to proceed with the construction.

¶ 3. Construction began in March 2006, several months later than provided for in the construction agreement. For the work, NCS employed various subcontractors; the subcontractors in the instant action contracted with NCS in February and March 2006. Nealy was NCS’s only employee permanently located in Southaven.

*1092 ¶ 4. As the construction progressed, payments from NCS to Nealy and its subcontractors began arriving late, and they had ceased by November 2006, when the subcontractors filed construction liens against the Church’s property. By this point, construction on the sanctuary building had stopped. The Church had paid NCS the balance due under the contract, but approximately $300,000 of work would be required to complete the sanctuary building. The three subcontractors alleged that they were owed about $110,000 among them.

¶ 5. The chancellor found that the subcontractors could not recover from the Church because they had failed to give stop payment notices before the Church made its final payment to NCS, the general contractor. The chancellor also found that the subcontractors could not recover against the Church on an agency theory because no principal-agent relationship existed between the Church and NCS. On appeal, the subcontractors challenge both findings, arguing that the chancellor erred because NCS was not a licensed contractor in the State of Mississippi. Finding no error, we affirm.

STANDARD OF REVIEW

¶ 6. In reviewing the judgment of a chancery court, an appellate court “will not disturb the findings of a chancellor when supported by substantial evidence unless the chancellor abused his discretion, applied an erroneous legal standard, was manifestly wrong, or was clearly erroneous.” Hamilton v. Hopkins, 834 So.2d 695, 699(¶ 12) (Miss.2003) (citations omitted). Additionally, where the chancellor has made no specific findings, we will proceed on the assumption that he resolved all such fact issues in favor of the appellee. Newsom v. Newsom, 557 So.2d 511, 514 (Miss.1990). A chancellor’s interpretation and application of the law, however, is reviewed de novo. Tucker v. Prisock, 791 So.2d 190, 192(¶ 10) (Miss.2001).

DISCUSSION

1. Stop Notices

¶7. The chancellor found that because the subcontractors failed to timely file stop notices, they were simple creditors of the general contractor and were barred from recovery against the owners.

¶ 8. We have previously held:

At common law, subcontractors are common creditors of the contractor for whom they agree to provide materials or services. Jones Supply Co. v. Ishee, 249 Miss. 515, 527, 163 So.2d 470, 475 (1964). No privity exists between a subcontractor and an owner. Corrugated Indus., Inc. v. Chattanooga Glass Co., 317 So.2d 43, 47 (Miss.1975). But Mississippi Code Annotated section 85-7-181 (Rev. 1999) prescribes a remedy against the owner for a subcontractor “who may have furnished materials used in the erection, construction, alteration, or repair of any house” and who is not paid by the contractor. To exercise the remedy, the unpaid subcontractor must serve written notice of the debt upon the property owner, at which point “the amount that may be due upon the date of the service of such notice by such owner to the contractor or master workman, shall be bound in the hands of such owner for the payment in full, or if insufficient then pro rata, of all sums due such person....” Miss.Code Ann. § 85-7-181 (Rev.1999). In other words, when the unpaid subcontractor gives written notice (commonly termed a “stop notice”) to the owner, the subcontractor becomes entitled to payment from the owner up to the amount in which the owner is indebted to the general con *1093 tractor as of the date the notice is served. Id.
The service of the stop notice invokes the subcontractor’s statutory remedy against the owner. Id. Absent such notice, an owner has no obligation to a subcontractor who has provided materials or services pursuant to an agreement with a contractor. Corrugated Indus. Inc., 317 So.2d at 47. And, if a subcontractor serves a stop notice after the owner has paid the contractor the full amount due under the contract, the owner is not liable to the subcontractor. Id.; Miss.Code Ann. § 85-7-181.

Timms v. Pearson, 876 So.2d 1083, 1086 (¶¶ 8-9) (Miss.Ct.App.2004).

¶ 9. It is uncontroverted that none of the subcontractors filed stop notices before the owner, the Church, had paid its obligations to NCS, the general contractor.

¶ 10. On appeal, the subcontractors present several arguments as to why the owners should be liable notwithstanding the subcontractors’ failure to timely file stop notices. The subcontractors present each argument as a separate issue, but because all relate to the single overarching and dispositive issue of whether the chancellor erred in finding that the subcontractors were barred from recovering from the Church, we shall address them together.

¶ 11. First, the subcontractors argue that the chancellor erred in failing to consider Mississippi Code Annotated section 31-3-15 (Rev.2008), which provides:

No contract for public or private projects shall be issued or awarded to any contractor who did not have a current certificate of responsibility issued by said board at the time of the submission of the bid, or a similar certificate issued by a similar board of another state which recognizes certificates issued by said board. Any contract issued or awarded in violation of this section shall be null and void.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bruce Cope v. Thrasher Construction, Inc.
231 So. 3d 1046 (Court of Appeals of Mississippi, 2016)
Goodman v. Physical Resource Engineering, Inc.
270 P.3d 852 (Court of Appeals of Arizona, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
25 So. 3d 1090, 2010 Miss. App. LEXIS 11, 2010 WL 22551, Counsel Stack Legal Research, https://law.counselstack.com/opinion/summerall-electric-co-v-church-of-god-at-southaven-missctapp-2010.