Bruce Cope v. Thrasher Construction, Inc.

231 So. 3d 1046
CourtCourt of Appeals of Mississippi
DecidedJune 28, 2016
Docket2014-CA-01474-COA
StatusPublished

This text of 231 So. 3d 1046 (Bruce Cope v. Thrasher Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bruce Cope v. Thrasher Construction, Inc., 231 So. 3d 1046 (Mich. Ct. App. 2016).

Opinions

GRIFFIS, P.J.,

for the Court:

¶1.. Bruce Cope, Mary Cope, and. Ike Thrash (Cope and Thrash) appeal a judgment against them requiring that they pay Thrasher Construction $69,290 for goods and services provided in waterproofing Inn by the Sea, a condominium in Pass Christian, Mississippi. Cope and Thrash argue that the facts of this case do not support a recovery under the theory of quantum me-ruit. Thrasher Construction cross-appeals claiming that the county court erred in dismissing its third-party-beneficiary claim against Cope and Thrash.

FACTS

¶ 2. Inn by the’ Sea was destroyed by Hurricane Katrina in 2005. The owners of the individual units engaged Sealnn LLC (Sealnn) to develop a new complex and rebuild. Sealnn consisted of two members, Greg Stewart and Kenny Labelle. The unit owners conveyed their interest in the property to Sealnn in order to begin the project. Sealnn then hired Madison Homes as its general contractor. Greg Stewart is the only known representative of Madison Homes.

¶ 3. In February 2009, Madison Homes contracted with Thrasher Construction in order to waterproof Inn by ■" the Sea. Thrasher Construction was to -be paid $106,600 for this project. Thrasher Construction worked on the Inn by the - Sea project from April to July of 2009. Each month, it sent an invoice to Madison Homes, but none of the invoices were paid. Eventually, upon completion of sixty-five percent of the work on the Inn by the Sea project, Thrasher Construction stopped work due to nonpayment. Thrasher Construction then filed a Notice of Construction Lien against the Inn by the Sea property in September 2009. The amount due at the time that Thrasher. Construction stopped work was $69,290, calculated based on the percentage of the project completed.

¶4. Ike Thrash later purchased La-belle’s fifty pércent interest in Sealnn. He then signed over part of his interest to Bruce Cope and Mary Cope. After realizing that neither Stewart nor Madison Homes was paying' the subcontractors, Cope and Thrash entered into a settlement agreement with Stewart to remove him. Cope and Thrash agreed to take over and complete certain projects. Cope and Thrash agreed to pay the subcontractors on the Inn by the Sea project to the extent that the invoices provided by Stewart were “true, validC,] and correct.” Attached to the agreement was a list of unpaid invoices for each project; Thrasher Construction’s multiple invoices were listed.

¶5. Cope and Thrash then began to contact the subcontractors. . They requested that the subcontractors come to Inn by the Sea during a specific two-day period to verify the work performed. Upon verification, Cope and Thrásh would pay each subcontractor what was owed. ■ Thrash contacted Thrasher Construction approximately four times during this two-day period, but Thrasher Construction did not come to the project to verify its work because of the existing lien, Cope and Thrash paid every other subcontractor on the Inn by the Sea project. In November 2009, Thrasher Construction withdrew its lien.

¶ 6. Thrasher Construction then filed a lawsuit against Madison Homes as well as [1050]*1050Cope and Thrash claiming breach of contract. Specifically, Thrasher Construction alleged breach of contract as a third-party beneficiary against Cope and Thrash based on the settlement agreement.

¶ 7. During trial, after Thrasher Construction’s case-in-chief, the county court dismissed the third-party beneficiary breach-of-contract claim after Cope and Thrash moved for a directed verdict. The court allowed Thrasher Construction to proceed on the theory of quantum meruit. The jury returned a verdict in favor of Thrasher Construction in tfye amount of $69,290. Cope and Thrash then filed a motion for a judgment notwithstanding the verdict (JNOV), which was denied by the county court. They appealed tó the circuit court, which affirmed. Cope and Thrash now appeal; Thrasher Construction cross-appeals.

ANALYSIS

I. Whether the court erred in allowing Thrasher Construction to proceed on the theory of quantum meruit.

¶ 8. First, Cope and Thrash contend that the express contract between Madison Homes and Thrasher Construction should have precluded Thrasher Construction from moving forward on the theory of quantum meruit. Second, Cope and Thrash argue that Thrasher failed to meet the burden of proof as to the elements of quantum meruit, and therefore, the court erred in allowing quantum meruit to be before the jury for consideration.

¶ 9. When reviewing the denial of a motion for a JNOY,

we will review all of the evidence in the light most favorable to the party opposed to the motion. If the facts and inferences from this evidence point so overwhelmingly in favor of the movant that reasonable jurors could not have arrived at a contrary verdict, the motion would be properly granted. On the other hand, if there is evidence of such quality and weight that reasonable and fair[-]minded jurors in the exercise of impartial judgment might reach different conclusions, the jury verdict should be allowed to stand, and the motion would be properly denied.

Ferguson v. Snell, 905 So.2d 516, 520 (¶ 16) (Miss.2004).

¶ 10. “Quantum meruit means literally ‘as much as he deserves[.]’ ” Redd v. L & A Contracting Co., 246 Miss. 548, 151 So.2d 205, 207 (1963). “Quantum meruit is a contract remedy which may be premised either on express or implied contract, and a prerequisite to establishing grounds for quantum meruit recovery is the claimant’s reasonable expectation of compensation.” Ace Pipe Cleaning Inc. v. Hemphill Constr. Co., 134 So.3d 799, 805 (¶ 29) (Miss.Ct.App.2014). The essential elements for recovery under quantum me-ruit are:

(1) valuable services were rendered or materials furnished; (2) for the person sought to be charged; (3) which services and materials were accepted by the person sought to be charged, used[,] and enjoyed by him; and (4) under such circumstances as reasonably notified [the] person sought to be charged that [the] plaintiff, in performing such services, ... expected to be paid by [the] person sought to be charged.

In re Estate of Fitzner, 881 So.2d 164, 173-73 (¶ 25) (Miss.2003). Quantum meru-it

applies to situations where there is no legal contract but where the person sought to be charged is in possession of money which in good conscience and justice he should not retain but should deliver to another, the courts imposing a [1051]*1051duty to refund the money or the use value of the property to the person to whom in good conscience it ought to belong.

Ace Pipe Cleaning, 134 So.3d at 806 (¶ 29).

¶ 11. To collect under the theory of quantum meruit, “the claimant must show there is no legal contract!.]” Johnston v. Palmer, 963 So.2d 586, 596 (¶ 22) (Miss.Ct.App.2007). It is true that quantum meruit “may be premised either on express or implied contract.” Ace Pipe Cleaning, 134 So.3d at 805 (¶29). But “where there is a contract, and the contract has not failed, the parties may not abandon the contract and resort to quantum meruit.” 3 Jeffrey Jackson & Mary Miller, Encyclopedia of Mississippi Law § 21:73 (2001); Sentinel Indus. Contracting Corp. v. Kimmis Indus. Serv. Corp., 743 So.2d 954, 970 (¶ 48) (Miss.1999).

¶ 12.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SIMMONS HOUSING, INC. v. Shelton
36 So. 3d 1283 (Mississippi Supreme Court, 2010)
Tupelo Redevelopment Agency v. Gray Corp.
972 So. 2d 495 (Mississippi Supreme Court, 2007)
Summerall Electric Co. v. Church of God at Southaven
25 So. 3d 1090 (Court of Appeals of Mississippi, 2010)
Redd and Hill v. L & a Contracting Co.
151 So. 2d 205 (Mississippi Supreme Court, 1963)
Bailey v. Worton
752 So. 2d 470 (Court of Appeals of Mississippi, 1999)
White v. Stewman
932 So. 2d 27 (Mississippi Supreme Court, 2006)
Johnston v. Palmer
963 So. 2d 586 (Court of Appeals of Mississippi, 2007)
Ferguson v. Snell
905 So. 2d 516 (Mississippi Supreme Court, 2004)
Turnbough v. Steere Broadcasting Corp.
681 So. 2d 1325 (Mississippi Supreme Court, 1996)
Associated Dealers v. Mississippi Roofing
589 So. 2d 1245 (Mississippi Supreme Court, 1991)
In Re Estate of Fitzner
881 So. 2d 164 (Mississippi Supreme Court, 2003)
Aladdin Const. Co. v. John Hancock Life Ins. Co.
914 So. 2d 169 (Mississippi Supreme Court, 2005)
Brogno v. W & J ASSOCIATES, LTD.
698 A.2d 191 (Supreme Court of Rhode Island, 1997)
R. Don Williams v. Ellis Realty, Inc.
176 So. 3d 133 (Court of Appeals of Mississippi, 2015)
Woolbright v. Wilhite
121 So. 3d 301 (Court of Appeals of Mississippi, 2013)
Ace Pipe Cleaning, Inc. v. Hemphill Construction Co.
134 So. 3d 799 (Court of Appeals of Mississippi, 2014)
Ground Control, LLC v. Capsco Industries, Inc.
120 So. 3d 365 (Mississippi Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
231 So. 3d 1046, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bruce-cope-v-thrasher-construction-inc-missctapp-2016.