Sullivan v. Mosner

295 A.2d 482, 266 Md. 479, 1972 Md. LEXIS 755
CourtCourt of Appeals of Maryland
DecidedOctober 12, 1972
Docket[No. 17, September Term, 1972.]
StatusPublished
Cited by19 cases

This text of 295 A.2d 482 (Sullivan v. Mosner) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sullivan v. Mosner, 295 A.2d 482, 266 Md. 479, 1972 Md. LEXIS 755 (Md. 1972).

Opinion

Smith, J.,

delivered the opinion of the Court.

Appellants, Timothy F. Sullivan (Sullivan) and Mary Jane Sullivan (Mrs. Sullivan), his wife, (the Sullivans) bought a partially completed home in Anne Arundel County from Municipal Savings and Loan Association, Incorporated (the Association), one of the appellees. They entered into a contract with a builder to complete the home. The Sullivans deposited with appellees, William F. Mosner (Mosner) and C. Arthur Eby (Eby), as trustees (the trustees), a sum of money equal to the amount of the contract with the builder, part of which they borrowed from the Association.

The Sullivans sued Mosner, Eby, and the Association in equity. They alleged that the trustees “carried out their duties with reckless indifference to the interest of *481 the beneficiary”; that they “failed to carry out the terms and conditions of the Trust agreement with ordinary skill and diligence required of Trustees”; that they “were delinquent in carrying out their duties”; that “the trust fund did not accomplish its purpose due to mismanagement and misapplication of the trust funds by the respondent Trustees”; and that $11,918.98 had “been wrongfully disbursed from the trust fund by the defendant Trustees, said disbursements not being in accord with the terms and conditions of the said Trust Agreement,” among other things. They prayed that Mosner, Eby, and the Association might be directed “to recompense [the Sullivans] out of their private funds for all of [the Sullivans’] losses and damages”; that they also “be ordered to replace, pay back, all those funds, sums of money, improperly or wrongfully disbursed from the trust fund so that [it might be] restored to its original sum of Twelve Thousand Two Hundred Fifty Dollars ($12,250.00)”; that the trustees be removed and a disinterested party appointed to act as trustee, and that they “be awarded a reasonable attorney’s fee from respondent’s [sic] private funds for services performed in enforcing Petitioners [sic] rights under the Trust Agreement.” The president of the Association was named in the trust agreement to act in place of any trustee who might be unable to perform his duties under the agreement.

The Association had made a construction loan to a contractor on subject property. Default took place prior to the completion of the home and the Association was obliged to buy it in at the foreclosure sale.

The Sullivans had been living in Pittsburgh. He went house hunting after his transfer to Maryland. After he spied this partially completed home, his inquiries led him to Frank Vavra (Vavra) who was associated with the original builder. Vavra in turn referred the Sullivans to Mosner, the attorney for the Association. Sullivan and Mosner met relative to purchase. Sullivan was advised to have a contractor look at the house and give a *482 price for its completion. Mosner specifically advised Sullivan to obtain a contractor other than Vavra.

Sullivan approached several contractors. Time was important insofar as the Sullivans were concerned. They ultimately selected Vavra to complete the home because he quoted the lowest price and because they believed, on the basis of Vavra’s having been involved in the original construction, having the original plans and having’ derived knowledge and familiarity from his earlier work, that he could complete the house in less time.

The Sullivans ultimately purchased the home from the Association and entered into the trust agreement to which we have previously alluded. The first paragraph of that agreement recited the deposit of $12,250.00 with the trustees; that the sum so deposited was to be placed by the trustees in such financial institution as they might deem proper; that it was not to be assignable by the Sullivans; and that the home was to be completed “on or before six months from the date [thereof].” Then follow subparagraphs (d) and (e) which are in controversy and which we reproduce in their entirety:

“(d) Following inspection and approval by such person or persons as may be designated by the Trustee from time to time, the Trustee shall pay to the Owner, except as herein-above otherwise provided, the installments due in accordance with the following schedule of payments:
“(e) And in addition to the Six Thousand Dollar Mortgage money that the Owners have deposited with the Trustees the said Owners also agree to deposit an additional Six Thousand Two Hundred Fifty Dollars of their own monies to be used in completion of the construction of said house and to be disbursed along with the other Six Thousand Dollars as follows:
1. Contractor shall submit a list of his *483 subcontractors and supplies [sic] to William F. Mosner, agent for Owner, and they shall, upon completion of their work or supplying of materials, submit bills to the agent who shall thereupon make payment of the amounts due less a retainage of ten percent.
2. The retainage shall be paid to the subcontractors and suppliers thirty days after completion of the house.
3. The difference between the amount paid to subcontractors and suppliers and the contract price shall be paid to the contractor upon completion, less ten percent which shall be paid as specified in ‘2’ above.”

The agreement contained an exculpatory clause releasing the trustees from any “personal responsibility” and providing that no claim should be made against them “in excess of a sum of money paid into their hands or such balance therefore [sic] as may be remaining and undisposed of in accordance with the terms and agreements [therein] set forth.”

Simultaneously with the conveyance and trust agreement a construction contract was entered into between the Sullivans and Vavra for completion of the home, which reads in part as follows:

“3. The Owner shall pay the Contractor for the performance of the contract the sum of twelve thousand two hundred fifty ($12,250.00) dollars as follows:
A. Contractor shall submit a list of his subcontractors and supplies [sic] to William F. Mosner, agent for Owner, and they shall, upon completion of their work or supplying of materials, submit bills to the agent who shall thereupon make payment of the amounts due less a retainage of ten percent.
B. The retainage shall be paid to the sub *484 contractors and suppliers thirty days after completion of the house.
C. The difference between the amount paid to subcontractors and suppliers and the contract price shall be paid to the contractor upon completion, less ten percent which shall be paid as specified in ‘B’ above.”

The contract was dated November 8. Work was to “be completed within forty-five days,” which would have permitted the Sullivans to move in by the first of the year, if not by Christmas.

The first payment to Vavra was made on November 22, 1968. Mosner said on that date Vavra came to his office with bills for certain materials he had purchased for the house and for work that Vavra and his employees had done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eaglehead Corp. v. Cambridge Capital Group, Inc.
170 F. Supp. 2d 552 (D. Maryland, 2001)
Universal Underwriters Insurance v. Lowe
761 A.2d 997 (Court of Special Appeals of Maryland, 2000)
Berringer v. Steele
758 A.2d 574 (Court of Special Appeals of Maryland, 2000)
Seigneur v. National Fitness Institute, Inc.
752 A.2d 631 (Court of Special Appeals of Maryland, 2000)
Adloo v. H.T. Brown Real Estate, Inc.
686 A.2d 298 (Court of Appeals of Maryland, 1996)
Pyles v. Goller
674 A.2d 35 (Court of Special Appeals of Maryland, 1996)
Wolf v. Ford
644 A.2d 522 (Court of Appeals of Maryland, 1994)
ATTORNEY GRIEV. COMM'N OF MARYLAND OF MARYLAND v. Owrutsky
587 A.2d 511 (Court of Appeals of Maryland, 1991)
Edwards Family Ltd. Partnership v. Barlow
915 F.2d 1564 (Fourth Circuit, 1990)
Axelrod v. NA" JIM" GIAMBALVO
472 N.E.2d 840 (Appellate Court of Illinois, 1984)
Webber v. Smith
632 P.2d 998 (Court of Appeals of Arizona, 1981)
Mercantile-Safe Deposit & Trust Co. v. Delp & Chapel Concrete & Construction Co.
408 A.2d 1043 (Court of Special Appeals of Maryland, 1979)
Safer v. Perper
569 F.2d 87 (D.C. Circuit, 1977)
Ross v. Hoffman
372 A.2d 582 (Court of Appeals of Maryland, 1977)
Shipley v. Crouse
370 A.2d 97 (Court of Appeals of Maryland, 1977)
Loyola Federal Savings & Loan Ass'n v. Galanes
365 A.2d 580 (Court of Special Appeals of Maryland, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
295 A.2d 482, 266 Md. 479, 1972 Md. LEXIS 755, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sullivan-v-mosner-md-1972.