Sullivan Mechanical Contractors, Inc. v. Barlows, Inc.

24 Va. Cir. 392, 1991 Va. Cir. LEXIS 196
CourtCharlottesville County Circuit Court
DecidedSeptember 5, 1991
DocketCase No. (Law) 4860
StatusPublished

This text of 24 Va. Cir. 392 (Sullivan Mechanical Contractors, Inc. v. Barlows, Inc.) is published on Counsel Stack Legal Research, covering Charlottesville County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sullivan Mechanical Contractors, Inc. v. Barlows, Inc., 24 Va. Cir. 392, 1991 Va. Cir. LEXIS 196 (Va. Super. Ct. 1991).

Opinion

By JUDGE JAY T. SWETT

This case concerns the applicability of Virginia’s arbitration statutes, §§ 8.01-577 and 8.01-581.01 to 8.01-581.016. Procedurally, the matter is before the court on plaintiff’s motion for summary judgment in which it contends that there are no arbitrable disputes between the parties and that the plaintiff is entitled to judgment as a matter of law. The defendant’s position is that this litigation must be stayed pending a determination by an arbitrator of all contractual disputes between the parties.

In February of 1990, the Commonwealth of Virginia contracted with the defendant, Barlows, Inc., to construct and/or renovate an "MR! Interiors Package" in conjunction with the University of Virginia Hospital. On April 24, 1990, Barlows subcontracted a portion of this work to the plaintiff, Sullivan Mechanical Contractors, Inc. The contract price was $264,787.00. Sullivan started work in May of 1990 and completed the work in December of 1990.

Under the parties’ agreement, Barlows was to make periodic progress payments to Sullivan. Apparently, Barlows made its last payment on November 8, 1990. Sullivan continued to work until its work was completed. Sullivan demanded payment for the balance due under the contract, $81,486.34. After several demands went unheeded, Sullivan filed suit [393]*393on April 26, 1991. Barlows demurred citing the arbitration clause in the agreement, requested a stay of its suit and an order compelling the parties to submit to arbitration. Barlows then filed an answer after its demurrer was overruled but still requests an order to stay this litigation and to compel arbitration. In response to Barlows’ answer and motion to compel arbitration, Sullivan has filed a motion for summary judgment arguing that, as a matter of law, there are no issues to submit to arbitration.

There are two separate but related issues to resolve. The first is whether the parties have agreed to arbitrate and, if so, is the dispute one in which the parties agreed to submit to arbitration. The parties agree that this court is the appropriate forum for a presubmission judicial determination of arbitrability issues. John Wiley & Sons v. Livingston, 376 U.S. 543, 546-47 (1964); Doyle & Russell v. Roanoke Hospital, 213 Va. 489, 494 (1973). The second is whether there are "procedural arbitration issues to be decided that would cause this court not to compel arbitration.

The contract between Sullivan and Barlows contains a broad arbitration clause. Article VI, paragraph 6.1, states that "[a]ny controversy or claim between the Contractor and the Subcontractor arising out of or related to this Subcontract, or the breach thereof, shall be settled by arbitration . . . ." Here, Sullivan contends that Barlows has breached the April 24, 1990, agreement because Barlows has failed to make the payments due under the contract. Although the contract provided a specific remedy to Sullivan to cease work in the event of nonpayment, Sullivan chose to continue working until the job was completed. Sullivan has offered no explanation why it did not elect to invoke the stop-work clause under paragraph 4.7.1, but that is not of importance here.

After the work was completed and Barlows refused to pay Sullivan the balance due, Sullivan made additional written demands on Barlows and on the University, but took no other action until it filed suit in this court in April, 1991. The motion for judgment was supported by an affidavit that complied with Va. Code § 8.01-28, thereby requiring a response under oath by the defendant. That response was filed by Barlows on June 14, 1991. [394]*394Barlows denied, under oath, that Sullivan was due the $81,486.34 on two grounds. The first was that Sullivan had not complied with conditions relating to Sullivan’s payments to subcontractors. The second was based on unspecified claims for liquidated damages against Barlows by the owner, a portion of which Barlows contends may be attributable to Sullivan.

The first issue, the question of whether the parties agreed to arbitrate these claims, must be answered in the affirmative. Paragraph 6.1 of the agreement is a comprehensive arbitration clause and provides that "any controversy or claim" between the parties arising out of the contract "or the breach thereof" shall be settled by arbitration. Sullivan claims that Barlows is in breach of the agreement by refusing to pay the balance due.

One cannot seriously argue that this claim is not a controversy arising out of the contract. Sullivan’s reliance on Doyle & Russell, supra, and Alascom, Inc. v. ITT North Electric Co., 727 F.2d 1419 (9th Cir. 1984), is misplaced. In Doyle & Russell, the arbitration clause provided that disputes would be submitted to arbitration and that factual findings by the arbitrator would be binding. In discussing that clause and how it applied to the facts in Doyle & Russell, the Court found there were no factual disputes between the parties that would require arbitration. Indeed, the contractor in Doyle & Russell, the party seeking the order to compel arbitration, conceded that its claim for additional compensation was not based on factual matters and what was at issue was a question of law. Based on the language of the arbitration clause in Doyle & Russell, and given the contractor’s position that only a question of law was at issue, the Court affirmed the trial court’s decision to deny the contractor’s request to submit the legal issue to arbitration. In Alascom, Inc., supra, the arbitration clause was a very limited one and completely different from the broad arbitration clause contained in this contract.

Sullivan’s second contention is more troublesome. Sullivan argues that even if the dispute is subject to the arbitration clause, Sullivan is nevertheless entitled to summary judgment because Barlows has failed to follow certain notice or procedural requirements called for under the contract and has in effect waived its right for an [395]*395order to compel the parties to arbitrate. The principal contractual clause at issue is paragraph 10.1.4.

Subcontractor shall insure that all Sub-contractors, employees and suppliers, at all times, are paid all amounts due in connection with the performance of this Subcontract. After the first partial payment hereunder, Barlows, Inc., shall have the right to withhold any subsequent partial payments until Subcontractor submits evidence satisfactory to Barlows, Inc., that all previous amounts owed in connection with performance of this Subcontract have been paid. Barlows, Inc., may withhold specific amounts otherwise due under this agreement provided that Barlows notifies Sullivan Mechanical in writing of this [sic] valid reason[s] as to why amounts are being withheld and further agrees to render payment upon completion or correction of this problem.

Sullivan contends, and Barlows does not deny, that when Barlows withheld progress payments, it did not notify Sullivan in writing regarding the reasons payments were withheld. In fact, Sullivan contends, and Barlows does not deny, that the first time Barlows gave a reason why payments were withheld was when it filed its answer to Sullivan’s motion for judgment in this suit some six months after it stopped making payments.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Wiley & Sons, Inc. v. Livingston
376 U.S. 543 (Supreme Court, 1964)
BOARD OF SUP'RS, ETC. v. Fralin & Waldron, Inc.
278 S.E.2d 859 (Supreme Court of Virginia, 1981)
Doyle and Russell, Inc. v. Roanoke Hospital Ass'n
193 S.E.2d 662 (Supreme Court of Virginia, 1973)
Alascom, Inc. v. ITT North Electric Co.
727 F.2d 1419 (Ninth Circuit, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
24 Va. Cir. 392, 1991 Va. Cir. LEXIS 196, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sullivan-mechanical-contractors-inc-v-barlows-inc-vacccharlottesv-1991.