Sullivan Electric, Inc. v. Robins & Morton Corporation

CourtCourt of Appeals of Tennessee
DecidedFebruary 27, 2013
DocketM2012-00821-COA-R3-CV
StatusPublished

This text of Sullivan Electric, Inc. v. Robins & Morton Corporation (Sullivan Electric, Inc. v. Robins & Morton Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sullivan Electric, Inc. v. Robins & Morton Corporation, (Tenn. Ct. App. 2013).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE November 27, 2012 Session

SULLIVAN ELECTRIC, INC. v. ROBINS & MORTON CORPORATION

Appeal from the Chancery Court for Davidson County No. 022639IV Russell T. Perkins, Chancellor

No. M2012-00821-COA-R3-CV - Filed February 27, 2013

A subcontractor on a large project in Texas sued the general contractor claiming the general contractor breached an agreement the parties made regarding claims both had against the owner of the Texas project. The parties agreed the subcontractor would be entitled to a pro rata share of the settlement or judgment amount if the subcontractor’s claims were not itemized. The settlement agreement between the general contractor and the owner did not include an itemization of the subcontractor’s claims. The subcontractor had been given a prepayment of its claim against the owner in the amount of $300,000, and applying this to the subcontractor’s pro rata share, the general contractor determined the subcontractor was not entitled to anything more. The trial court deducted the $300,000 from the subcontractor’s claim and awarded the subcontractor its pro rata share of the difference. Both the subcontractor and general contractor appealed, the subcontractor claiming it was not awarded enough and the general contractor claiming the subcontractor was awarded too much. We reverse the trial court’s award and hold the $300,000 the subcontractor received as a prepayment was more than it was entitled to pursuant to the terms of the parties’ agreement. Accordingly, the contractor did not breach its agreement, and the subcontractor was not entitled to any damages.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Reversed.

P ATRICIA J. C OTTRELL, P.J., M.S., delivered the opinion of the Court, in which F RANK G. C LEMENT, J R. and R ICHARD H. D INKINS, JJ., joined.

Richard McCallister Smith, Nashville, Tennessee, for the appellant, Sullivan Electric, Inc.

L. Wearen Hughes and Cecil Woods VanDevender for the appellee, Robins & Morton Corporation. OPINION

I. B ACKGROUND

Robins & Morton Corporation (“R&M”) was the general contractor on a project involving the construction of a medical center in Texas for Mercy Hospital of Laredo, Inc. (the “Owner”). Sullivan Electric, Inc. (“Sullivan”) was the subcontractor responsible for performing the electrical work. During the course of the project a dispute arose between R&M and the Owner. In November 1998 the Owner refused to pay R&M’s application for a $2.8 million progress payment, which meant R&M could not pay its subcontractors, including Sullivan. R&M directed its subcontractors to stop work until the Owner made its progress payment.

With the project stalled, R&M negotiated with the Owner to find a way for the project to get back on track. R&M and the Owner reached an agreement whereby the Owner would pay the outstanding progress payments in addition to the re-mobilization and delay costs incurred by R&M and its subcontractors, including Sullivan. R&M contacted its subcontractors to determine the amount of their re-mobilization and delay costs, and Sullivan informed R&M that its costs were $300,000.1 In reliance on this figure and the figures submitted by its other subcontractors, R&M informed the Owner that the total re- mobilization and delay costs were $3.25 million.

In February 1999 R&M and the Owner entered into an agreement whereby the Owner paid R&M the outstanding progress payments in addition to the $3.25 million to cover the subcontractors’ re-mobilization and delay costs. R&M paid Sullivan its portion of the outstanding progress payments as well as $300,000 out of the $3.25 million it received from the Owner as compensation for its delay costs. R&M accepted the $3.25 million from the Owner as a loan with the understanding that R&M would later have to justify its and its subcontractors’ entitlement to the money. To the extent the Owner could show R&M and its subcontractors were not entitled to the full $3.25 as delay and re-mobilization costs, R&M understood it may have to repay some or all of the $3.25 to the Owner at a later date. Sullivan was aware of the circumstances surrounding its receipt of the $300,000.

After distributing the $300,000 to Sullivan, R&M asked Sullivan for an itemized claim that R&M could present to the Owner to support and justify the $300,000 Sullivan received. In response, Sullivan submitted a claim in the amount of $529,185.68. The claim included $390,305.68 in extended overhead as well as $138,880 in claimed expenses for

1 Sullivan did not demobilize from the project, so the $300,000 represented its delay costs.

-2- circuits, a dimmer, and a fire alarm relay. A Sullivan employee explained while giving his deposition that the $529,185.68 claim was intended to justify the $300,000 Sullivan received from the $3.25 million loan.

After the hospital project was completed, R&M pursued its claim against the Owner through mediation and litigation in Texas. Sullivan submitted a claim to the mediator for $529,185.68. In its cover letter to the mediator Sullivan stated:

We are participating in this mediation for the purpose of assisting Robins & Morton in recovering certain extended overhead costs which it has partially paid to Sullivan Electric, Inc. in the amount of $300,000.00.

R&M’s claim against the Owner, on behalf of itself and its subcontractors, was in the amount of $18,632,519. R&M’s claim included the $3.25 million loan that R&M asserted it should not have to pay back, and an additional $15,382,519 that included Sullivan’s claim for $529,185.68. R&M made clear that when calculating the net payment due from the Owner, the total claim should be offset by the $3.25 million the Owner already paid R&M.

In the summer of 2001, during the pendency of R&M’s claim against the Owner, R&M and Sullivan entered into a Settlement and Joint Prosecution Agreement (the “Agreement”). The Agreement included the following relevant provisions:

WHEREAS, on or about September 17, 1996, Robins & Morton entered into a contract with the Mercy Regions Medical Center (“Mercy”) to build the Mercy Regional Medical Center, at Laredo, Texas (“the Project”);

WHEREAS, Robins & Morton and Sullivan entered into a subcontract, whereby Sullivan agreed to perform certain work (“Work”) on the Project as more particularly described therein (the “Subcontractor”);

.....

WHEREAS, during the performance of the Work, Sullivan also incurred extended overhead costs as a result of delays caused by various acts and omissions of the Mercy, its agents, assigns or privies;

WHEREAS, Robins & Morton filed an action in Texas state court against Mercy, HKS, Inc. and Federal Insurance Company (the “Litigation”);

WHEREAS, Robins & Morton and Sullivan believe that their best

-3- interests will be served and substantial litigation expenses will be saved by a settlement of the disputes or claims which exist or which might exist between them and by the joint prosecution of a combined claim;

NOW, THEREFORE, in consideration of the mutual promises, agreements, and understandings herein contained, and for good and valuable consideration, the receipt of which is hereby acknowledged, the Parties covenant and agree as follows:

3. Robins & Morton will jointly prosecute Sullivan’s claim for extended overhead and other damages caused by the acts and omission of Mercy and its agents during the Project (collectively the “Sullivan Pass Through Claim”) against Mercy. Robins & Morton and Sullivan also will jointly defend against any backcharges, counterclaims or cross-claims initiated by Mercy (collectively “Counterclaims”).

4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seagull Energy E & P, Inc. v. Eland Energy, Inc.
207 S.W.3d 342 (Texas Supreme Court, 2006)
Whaley v. Perkins
197 S.W.3d 665 (Tennessee Supreme Court, 2006)
Taylor v. Fezell
158 S.W.3d 352 (Tennessee Supreme Court, 2005)
Bogan v. Bogan
60 S.W.3d 721 (Tennessee Supreme Court, 2001)
Cross v. City of Memphis
20 S.W.3d 642 (Tennessee Supreme Court, 2000)
Abraxas Petroleum Corp. v. Hornburg
20 S.W.3d 741 (Court of Appeals of Texas, 2000)
Blair v. Brownson
197 S.W.3d 681 (Tennessee Supreme Court, 2006)
Stewart v. Basey
245 S.W.2d 484 (Texas Supreme Court, 1952)
Mays v. Pierce
203 S.W.3d 564 (Court of Appeals of Texas, 2006)
Union Carbide Corp. v. Huddleston
854 S.W.2d 87 (Tennessee Supreme Court, 1993)
B & W SUPPLY, INC. v. Beckman
305 S.W.3d 10 (Court of Appeals of Texas, 2009)
Maggart v. Almany Realtors, Inc.
259 S.W.3d 700 (Tennessee Supreme Court, 2008)
Guiliano v. Cleo, Inc.
995 S.W.2d 88 (Tennessee Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Sullivan Electric, Inc. v. Robins & Morton Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sullivan-electric-inc-v-robins-morton-corporation-tennctapp-2013.