Sullivan & Cozart, Inc. v. Main Street Revitalization LLC

CourtCourt of Appeals of Kentucky
DecidedAugust 1, 2025
Docket2024-CA-1188
StatusUnpublished

This text of Sullivan & Cozart, Inc. v. Main Street Revitalization LLC (Sullivan & Cozart, Inc. v. Main Street Revitalization LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sullivan & Cozart, Inc. v. Main Street Revitalization LLC, (Ky. Ct. App. 2025).

Opinion

RENDERED: AUGUST 1, 2025; 10:00 A.M. NOT TO BE PUBLISHED

Commonwealth of Kentucky Court of Appeals NO. 2024-CA-1067-MR

MAIN STREET REVITALIZATION LLC APPELLANT

APPEAL FROM JEFFERSON CIRCUIT COURT v. HONORABLE MELISSA L. BELLOWS, JUDGE ACTION NO. 18-CI-001019

CINCINNATI INSURANCE COMPANY AND SULLIVAN & COZART, INC. APPELLEES

AND

NO. 2024-CA-1188-MR

SULLIVAN & COZART, INC. CROSS-APPELLANT

CROSS-APPEAL FROM JEFFERSON CIRCUIT COURT v. HONORABLE MELISSA L. BELLOWS, JUDGE ACTION NO. 18-CI-001019

MAIN STREET REVITALIZATION LLC AND CINCINNATI INSURANCE COMPANY CROSS-APPELLEES OPINION AFFIRMING

** ** ** ** **

BEFORE: THOMPSON, CHIEF JUDGE; COMBS AND EASTON, JUDGES.

THOMPSON, CHIEF JUDGE: Main Street Revitalization, LLC (“MSR”) appeals

from orders of the Jefferson Circuit Court granting in part the motion of Sullivan &

Cozart, Inc. (“Sullivan”) to dismiss MSR’s claim for breach of contract; an order

granting Cincinnati Insurance Company’s (“CIC”) motion to intervene; an opinion

and order addressing subrogation issues between MSR and CIC; and, an opinion

and order disposing of MSR’s claim for attorney fees and expenses from CIC.

Sullivan cross-appeals, arguing that the circuit court erred in denying it summary

judgment on MSR’s negligence claim. After careful review, we find no error and

affirm the orders on appeal.

FACTS AND PROCEDURAL HISTORY

This case arises out of the “Whiskey Row” fire that occurred on July

6, 2015, in Louisville, Kentucky. MSR is the commercial developer responsible for

renovating three historic buildings located at 111, 113, and 115 West Main Street.

It hired Sullivan as the construction manager for the project pursuant to a contract

dated June 11, 2015.

At the time of the events alleged in MSR’s complaint, the buildings

were insured by CIC under a policy issued to MSR. That policy provided “first-

-2- party” coverage to protect MSR during construction of the Whiskey Row project

for losses resulting from fire and theft. Sullivan also purchased liability insurance

from CIC, providing coverage for “third-party” claims during construction. In the

construction contract, Sullivan agreed to add MSR as an “additional insured” on

that liability policy, resulting in MSR’s having coverage for claims by third parties

for their property damage losses arising from Sullivan’s acts and omissions. Thus,

CIC was the insurer for both MSR and Sullivan.

The July 6, 2015, fire at the MSR project destroyed most of MSR’s

property and significantly damaged other neighboring properties, including adjacent

property owned by the Brown-Forman Corporation. Following the fire, the

Louisville Fire and Rescue Metro Arson Squad investigated the cause and

concluded in a report that the cause of the fire was combustibles ignited during a

cutting operation with an acetylene torch or grinder.

After the MSR and Brown-Forman properties were stabilized, and

reconstruction began on both projects, MSR attempted to collect the full amount of

damages it alleged Sullivan caused. Brown-Forman also sought recovery from

MSR, resulting in MSR’s paying Brown-Forman $650,000 to settle Brown-

Forman’s claims. Thereafter, MSR filed this action on February 19, 2018, against

Sullivan and CIC, seeking declaratory relief and alleging claims of breach of

contract, strict liability, negligence, bad faith, and breach of fiduciary duty.

-3- MSR moved for partial summary judgment on its negligence and strict

liability claims against Sullivan. The motion was denied by way of an order

entered on August 2, 2019.

In August, 2021, Sullivan sought summary judgment seeking

dismissal of MSR’s negligence and contract claims, based on a provision in the

contract which Sullivan argued prevented MSR from pursuing these claims against

Sullivan. MSR responded that the contract provision raised by Sullivan was void

and unenforceable based on the express language of Kentucky Revised Statutes

(“KRS”) 371.180(2) and supportive case law.

Two months later, the circuit court entered an order partially granting

summary judgment. It held that the contract’s subrogation waiver was valid as it

related to all claims other than those for negligence, wanton, or willful conduct.

An extensive procedural history followed. In May, 2022, CIC moved

to intervene and tendered an intervening complaint alleging that Sullivan’s

negligence caused the fire. MSR opposed the motion, arguing that intervention

was untimely and failed to comply with Kentucky Rules of Civil Procedure (“CR”)

24. The trial court granted the motion to intervene.

Trial commenced in September, 2022. When the case was submitted

to the jury, MSR sought $3,609,919 for damage to the real property and

$18,049,595 for punitive damages. The jury decided in favor of Sullivan on the

-4- gross negligence claim and declined to award punitive damages. It ruled in favor

of MSR on the negligence claim, and awarded $2,322,000 of the compensatory

damages claimed. As later noted by CIC, the compensatory damage award was

$1,300,000 below the amount MSR sought to recover at trial, and well below the

$7,028,326 it received from CIC under its Builder’s Risk Policy. MSR’s

additional claims against CIC for breach of contract, bad faith, and breach of

fiduciary duty were bifurcated and reserved for later adjudication.

On October 14, 2022, the Jefferson Circuit Court entered a judgment

reflecting the jury’s award. The following month, CIC asked the circuit court to

assign the judgment to CIC based on subrogation language contained in the

insurance policy. MSR opposed the assignment, arguing that CIC had waived any

subrogation rights by not asserting its negligence claim within the five-year statute

of limitations for real property damage claims in KRS 413.120(4), and because

CIC did not satisfy the standard for intervening in the action per CR 24.

On January 9, 2024, the circuit court held that CIC’s entry into the

case was proper and not barred by the statute of limitations, as Section 12 of the

insurance contract granted to CIC a contractual right to MSR’s recovery which was

subject to a ten-year statute of limitations for contract claims.

Without waiving its rights, MSR then filed a motion asking the circuit

court to order that if CIC’s subrogation claim were allowed, MSR was entitled

-5- under the same Section 12 in the policy to be reimbursed first for MSR’s attorneys’

fees and other legal expenses in obtaining the $2.3 million judgment.

On June 25, 2024, the Jefferson Circuit Court denied the motion for

attorneys’ fees. In support of the order, the court determined that MSR “failed to

cite any case law affirmatively allowing attorney’s fees without a contractual

provision explicitly granting such.” It also found that the American Rule on

attorneys’ fees provides that each party bears its own fees absent an express

contractual or statutory grant of such fees. Sullivan moved to have the circuit court

make its rulings final and appealable pursuant to CR 54.02, which the court

granted. This appeal followed.

STANDARD OF REVIEW

Summary judgment “shall be rendered forthwith if the pleadings,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Government Employees Insurance Co. v. Winsett
153 S.W.3d 862 (Court of Appeals of Kentucky, 2004)
State v. US Fidelity and Guar. Co.
577 So. 2d 1037 (Louisiana Court of Appeal, 1991)
Steelvest, Inc. v. Scansteel Service Center, Inc.
807 S.W.2d 476 (Kentucky Supreme Court, 1991)
Commonwealth v. English
993 S.W.2d 941 (Kentucky Supreme Court, 1999)
Emberton v. GMRI, Inc.
299 S.W.3d 565 (Kentucky Supreme Court, 2009)
Cumberland Valley Contractors, Inc. v. Bell County Coal Corp.
238 S.W.3d 644 (Kentucky Supreme Court, 2007)
Scifres v. Kraft
916 S.W.2d 779 (Court of Appeals of Kentucky, 1996)
Polis v. Unknown Heirs of Jessie C. Blair
487 S.W.3d 901 (Court of Appeals of Kentucky, 2016)
Board of Commissioners v. Teton Corp.
30 N.E.3d 711 (Indiana Supreme Court, 2015)
Chadwick v. CSI, Ltd.
629 A.2d 820 (Supreme Court of New Hampshire, 1993)
Superior Steel, Inc. v. Ascent at Roebling's Bridge, LLC
540 S.W.3d 770 (Missouri Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Sullivan & Cozart, Inc. v. Main Street Revitalization LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sullivan-cozart-inc-v-main-street-revitalization-llc-kyctapp-2025.