Sufi Network Services, Inc. v. United States

817 F.3d 773, 2016 WL 1211812, 2016 U.S. App. LEXIS 5742
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 29, 2016
Docket2015-5151
StatusPublished
Cited by10 cases

This text of 817 F.3d 773 (Sufi Network Services, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sufi Network Services, Inc. v. United States, 817 F.3d 773, 2016 WL 1211812, 2016 U.S. App. LEXIS 5742 (Fed. Cir. 2016).

Opinion

TARANTO, Circuit Judge.

‘ This government contract case returns to us after the completion by a contract appeals board of the remand proceedings that we ordered in 2014. The board reached its final decision in early 2015, and the private contractor promptly accepted the decision. When the United States challenged its own board’s decision, the Court of Federal Claims dismissed the challenge. We affirm.

Background

As the parties agree, this case is governed by the Wunderlich Act, codified at 41 U.S.C. §§ 321-322 before its repeal in 2011.- Under a contract, with the Air Force, SUFI Network Services, Inc. invested money to build and to operate telephone systems at certain Air Force bases and was to earn returns on that investment for fifteen years (for each installation) from per-call charges, the revenue to be shared with the Air Force. The Air Force breached the contract in various ways by allowing contractually prohibited diversions of calls from the SUFI phones, depriving SUFI of revenue. See SUFI Network Servs., Inc. v. United States, 755 F.3d 1305, 1309-10 (Fed.Cir.2014) (2014 CAFC Decision).

Following the contractually prescribed process for dispute resolution, SUFI brought claims against the Air Force, and the Armed Services Board of Contract Appeals (Board or ASBCA) rendered a decision on those claims. The Board found breach and awarded roughly $2.8 million (plus interest) on one group of claims and roughly $4.6 million (plus interest) on another. See J.A. 3899-3900. The award on the first group of claims became final and has not been at issue since then. SUFI was dissatisfied with the Board’s damages determinations on the second group of claims, so it sued the United States in the Court of Federal Claims to challenge those determinations on numerous grounds, invoking the standards of review set by the Wunderlich Act. See S & E Contractors, Inc. v. United States, 406 U.S. 1, 3 n. 1, 92 S.Ct. 1411, 31 L.Ed.2d 658 (1972); United States v. Anthony Grace & Sons, Inc., 384 U.S. 424, 427 n. 3, 86 S.Ct. 1539, 16 L.Ed.2d 662 (1966); United States v. Carlo Bianchi & Co., 373 U.S. 709, 709 n. 1, 83 S.Ct. 1409, 10 L.Ed.2d 652 (1963). The United States filed' nó counterclaims to challenge any aspect of the Board’s decision, including the rulings on breach and damages.

After the Court of Federal Claims granted SUFI relief, SUFI Network Servs., Inc. v. United States, 108 Fed.Cl. 287, 321 (2012) (2012 CFC Decision), the United States appealed several of that court’s rulings'to this court. SUFI cross-appealed to obtain more relief on a few points. The United States sought to reinstate a variety of Board determinations on damages, but it asked in the alternative that this court order a remand for the Board to. exercise its “wide discretion” in fact-finding if this court agreed with SUFI that the Board had committed errors that prejudiced SUFI. See Brief for Defendant-Appellant, The United States at 26, 33-34, 38, SUFI Network Servs., Inc. v. United States, 755 F.3d 1305 (Fed.Cir.2014) (Nos.2013-5039, 5040) (2014 U.S. Br.); Reply and Response for Defendant-Appellant at 30, SUFI Network Servs., Inc. v. United States, 755 F.3d 1305 (Fed.Cir.2014) (Nos.20135039, -5040) (2014 U.S. Reply Br.).

Our 201k CAFC Decision was governed by. the same standard of review of the Board’s rulings as governed in the Court of Federal Claims. We held that the *776 Court of Federal Claims had not properly-applied that standard in several respects. And, when we applied the proper standard of review to the Board’s rulings, we agreed with a number, though not all, of SUFI’s assertions of prejudicial error by the Board. We ordered the Court of Federal Claims to remand the case to- the Board for further proceedings on certain issues bearing on SUFI’s challenges.

The Board conducted the remand proceedings and reached a decision in early 2015. SUFI Network Servs., Inc., ASBCA No. 55306, 15-1 BCA ¶ 35,878, J.A. 3899-3924, modified on reconsideration, SUFI Network Servs., Inc., No. ASBCA 55306, 15-1 BCA ¶ 35,992, J.A. 3925-3933. The new Board decision, though not giving SUFI all it sought on the claims at issue, was much more favorable to SUFI than the'earlier Board decision on those claims: it awarded roughly $113 million (plus interest) rather than the original amount of roughly $4.6 million (plus interest). Indeed, the new decision was favorable enough that SUFI filed in the Court of Federal Claims, in the docket of the Wun-derlich Act case that had produced the remand to the Board, a notice stating that it accepted the 2015 Board decision.

The United States, however, was dissatisfied with its own Board’s decision. It fiied with the Court of Federal Claims, in the same docket, a request for review of the new award. The Court of Federal Claims denied the request. SUFI Network Servs., Inc. v. United States, 122 Fed.Cl. 257, 263 (2015) (2015 CFC Decision ).

The Court of Federal Claims explained that, as relevant here, “[ujnder the Wun-derlich Act, only the contractor has the right to appeal from a Board decision.” 2015 CFC Decision, 122 Fed.Cl. at 259. The basis for that rule is the exchange embodied in the contract between SUFI and the' Air Force, which includes a “standard ‘Disputes’ clause” under which SUFI gave up its rights to cease work if a dispute arose and both SUFI and the government agreed that “‘the decision of the Board shall be final and conclusive.’ ” See id. at 261. 1 The “trade-off’ is the contractor’s promise to stay on the job and the United States’ -commitment “to be bound *777 by board decisions favorable to the contractor.” Id. at 262.

The Court of: Federal Claims stated that, under clear precedents now more than 35 years old, “the United States d[oes] not have the right to seek review of an adverse board of contract appeals’ decision” where, as here, there is no claim of fraud or bad faith on the part of the Board and the contractor fully accepts the (decision. Id. at 261-62; see S & E, 406 U.S. at 8, 92 S.Ct. 1411; id. at 20, 92 S.Ct. 1411 (Blackmün, J., with whom Burger, C.J., and Stewart and Powell, JJ., join, concurring); Roscoe-Ajax Constr. Co. v. United States, 204 Ct.Cl. 726, 499 F.2d 639, 644-47 (1974); Fischbach & Moore Int’l Corp. v. United States, 223 Ct.Cl.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
817 F.3d 773, 2016 WL 1211812, 2016 U.S. App. LEXIS 5742, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sufi-network-services-inc-v-united-states-cafc-2016.