Sue Klau Enterprises, Inc. v. American Fidelity Fire Insurance Company

551 F.2d 882, 1977 U.S. App. LEXIS 13958
CourtCourt of Appeals for the First Circuit
DecidedApril 6, 1977
Docket76-1143
StatusPublished
Cited by3 cases

This text of 551 F.2d 882 (Sue Klau Enterprises, Inc. v. American Fidelity Fire Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sue Klau Enterprises, Inc. v. American Fidelity Fire Insurance Company, 551 F.2d 882, 1977 U.S. App. LEXIS 13958 (1st Cir. 1977).

Opinion

VAN OOSTERHOUT, Senior Circuit Judge.

This is an appeal by plaintiff Sue Klau Enterprises, Inc., from a judgment dismissing its complaint for enforcement of an award made by architect Carlos de la Uz Arenal pursuant to the provisions of a building construction contract against defendant American Fidelity Fire Insurance Company. Jurisdiction in the trial court, based on diversity of citizenship and the jurisdictional amount under 28 U.S.C. § 1332, is established.

A rather extensive statement of the factual and legal background appears to be desirable. Edil Construction, Inc., (Edil) entered into a contract to construct an apartment building for plaintiff in Santurce, Puerto Rico. The contract is based on American Institute of Architects Standard Form A-201.

Defendant in its brief admits that it issued to plaintiff material, labor and performance bonds which are in full force and effect and which incorporate the construction contract by reference, and that such bonds obligate it for the faithful performance by Edil of its obligations under the building contract.

Defendant also admits that Edil defaulted in the performance of the contract, that plaintiff elected to complete the project pursuant to paragraph 7.6.1 of the contract, and that plaintiff by letters of April 4,1973, so notified both Edil and defendant bonding company.

Plaintiff completed the building project and on July 25, 1973, sent a letter to the bonding company containing an itemized claim of damages due it by reason of Edil’s default and demanding payment under the contract and bonds for its completion expenditures and for delay in construction caused by Edil’s default. Defendant admits that it has refused to make payment.

By letter dated December 11, 1973, to architect de la Uz, plaintiff requested determination by the architect that the amounts expended by plaintiff as itemized in its July 25 letter for the completion of the building were due under the contract and defendant’s bonds. Said letter requested the architect’s decision on the amount due by reason of the contractor’s default, pursuant to paragraphs 2.2.6 et seq. of the contract which provide in substance that claims and disputes arising under the contract shall be initially referred to the architect for decision which shall be made in writing.

The architect sent to defendant a copy of plaintiff’s letter requesting the architect’s determination of the amount due under the contract and a letter advising that a meeting would be held at 9:00 a. m. on February 22, 1974, at a place specified, for the purpose of making the determination requested. Such letter concluded by saying: “It is my intention to give an impartial opinion on this matter, for which reason you will appreciate how important this meeting will be.” Defendant admits the receipt of such letters on February 15, 1974.

The architect, by deposition, testified that a number of meetings were held with the interested parties and that the defendant was represented at several such meetings. On cross examination he testified:

Q Did you call the parties and then give them a chance to refute the evidence that was there?
*884 A Yes, I would say so, I called a meeting, and after several postponements, I remember now, we finally got together, and this letter was reviewed in this meeting, as I see it I gave a chance to everybody to talk about the letter and refute it or do whatever had to be done on this letter. That’s my opinion.
Q Do you know what an arbiter is? What is your opinion of what an arbiter is?
A I think it is a person who would act as a judge would in a matter in dispute between two parties.
Q Do you think it’s important that the parties know that they are actually in arbitration proceedings?
A Of course I would say that.

The letter referred to is plaintiff’s demand letter heretofore referred to.

The architect by letter dated April 10, 1974, supplemented by letter dated August 13, 1974, allowed many of plaintiff’s claims but rejected some of them and awarded plaintiff $67,516.06. The August 13 letter stated: “This decision is rendered pursuant to the construction agreement and is final but subject to appeal.”

Part 7.10 of the contract contains provisions for additional arbitration. Paragraph 7.10.1 provides: “All claims [with certain exceptions not here relevant] shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining.”

Paragraph 7.10.2 in pertinent part reads:

Notice of the demand for arbitration shall be filed in writing with the other party to the Contract and with the American Arbitration Association, and a copy shall be filed with the Architect. The demand for arbitration shall be made within the time limits specified in Sub-paragraphs 2.2.10 and 2.2.11 where applicable, . . . ”

Paragraph 2.2.11 provides in turn:

If a decision of the Architect is made in writing and states that it is final but subject to appeal, no demand for arbitration of a claim . . . covered by such decision may be made later than thirty days after the date on which the party making the demand received the decision. The failure to demand arbitration within said thirty days’ period will result in the Architect’s decision becoming final and binding upon the Owner and the Contractor.

No notice of demand for arbitration was given by the defendant within thirty days from the architect’s final decision as required by paragraph 2.2.11. By letter dated September 17, 1974, plaintiff demanded payment of $67,516.06 determined due by the architect. No payment was made. Plaintiff then commenced this action to enforce the architect’s award.

Defendant by answer made admissions, as set out in the statement of facts, supra, and generally denied the allegations asserting its liability. By way of affirmative defense, defendant pleaded that it had never appeared in a meeting for the purpose of issuing an arbitration award and specifically refused to do so, that the architect was not accepted by the defendant, that this information was communicated to the architect, and that, although a meeting was held for the purpose of obtaining information from the plaintiff, the defendant does not accept the letters of April 10 and August 13,1974, as an award. Defendant also pleaded that the plaintiff failed to produce any evidence during the hearings before the architect, although the architect through his recollections tried to help plaintiff clarify its position.

Both parties filed motions for summary judgment pursuant to Rule 56, Fed.R. Civ.P., both claiming that there is no dispute as to any material fact and that they are entitled to judgment as a matter of law. The motions were based upon the pleadings, plaintiff’s request for admissions and defendant’s response thereto, and the deposition taken of the architect. An affidavit was also filed by Juan N.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Neighbors Construction Co. v. Woodland Park at Soldier Creek, LLC
284 P.3d 1057 (Court of Appeals of Kansas, 2012)
D'Amario v. Connor Construction, Inc.
1980 Mass. App. Div. 1 (Mass. Dist. Ct., App. Div., 1980)

Cite This Page — Counsel Stack

Bluebook (online)
551 F.2d 882, 1977 U.S. App. LEXIS 13958, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sue-klau-enterprises-inc-v-american-fidelity-fire-insurance-company-ca1-1977.