Subterrane Corp. v. City of New York

11 Misc. 2d 566, 178 N.Y.S.2d 1, 1957 N.Y. Misc. LEXIS 2808
CourtNew York Supreme Court
DecidedJune 25, 1957
StatusPublished

This text of 11 Misc. 2d 566 (Subterrane Corp. v. City of New York) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Subterrane Corp. v. City of New York, 11 Misc. 2d 566, 178 N.Y.S.2d 1, 1957 N.Y. Misc. LEXIS 2808 (N.Y. Super. Ct. 1957).

Opinion

Isidob Wassebvogel, Spec. Ref.

Plaintiff seeks to recover upwards of $88,000 for work, labor and services performed by it for the defendant in accordance with a supplemental agreement which provided for the completion of the construction of certain sewers in the borough of Brooklyn.

On October 14, 1949, plaintiff entered into a contract with defendant for the construction of intercepting sewers for the so-called Owls Head Sewage Treatment Works. During the course of its work, plaintiff encountered subsoil conditions which were unforeseen by either contracting party. Accordingly, on July 14, 1950, plaintiff and defendant entered into the supplemental agreement here involved which enabled plaintiff to proceed with the completion of its construction work. The [568]*568physical work in the field was completed on June 25, 1952, but plaintiff’s books and records were not audited by the defendant until more than a year thereafter.

Plaintiff’s claim, in substance, is based upon its contention that pursuant to the supplemental agreement it is entitled to payments based upon the following items:

1 —10% for overhead in the computation of the final amount due it for the completion of the sewer work, said overhead running until October, 1953, when defendant completed its audit of plaintiff’s books and records.

2 — $6,728.04 for the rental of equipment, which amount, in effect, was disallowed by defendant.

3 — Interest on the above sums allegedly improperly withheld and unpaid by the defendant.

Defendant contends that plaintiff is not entitled to claim any overhead expense incurred after the date of the actual field work. Defendant further contends that the express language of the supplemental agreement, particularly the provisions of paragraph 6 thereof, bars the allowance of any 10% overhead payment to plaintiff in the final computation of moneys due it. In effect, therefore, the following items of plaintiff’s claims and demand for payment are disputed by defendant:

1 — $153,513.65 claimed as overhead by plaintiff (10% of the' final direct cost of $1,535,136.54).

2 — $84,432.51 claimed as 5% profit due plaintiff under the terms of the supplemental agreement. Defendant does not dispute plaintiff’s right to take a 5% profit but contends that the amount claimed by it is computed upon an improper basis, particularly with respect to the claimed 10% overhead.

3 — $10,504.07 in interest. Defendant contends that plaintiff is not entitled to any interest.

4 — $412,525.47 for rental value of equipment. Defendant alleges that the true value thereof is $405,797.43.

Plaintiff has concededly received from defendant for the work performed by it under the entire contract the sum of $2,276,742.81. The sum of $584,058.77 thereof represents the total amount that was due to plaintiff for all of its work under the original contract prior to the execution of the supplemental agreement. Both parties are in accord as to the following amounts claimed by plaintiff as expenses incurred by it in connection with the work performed under the supplemental agreement:

1 —$650,488.34 for labor.

2 — $132,222.58 for insurance.

3 — $347,157.44 for materials..

[569]*569Of the $412,528.47 claimed by plaintiff as its expense for the rental of equipment, defendant has conceded only $405,797.43 thereof, leaving the sum of $6,728.04 in dispute. Plaintiff thus arrives at the sum of $1,542,393.83 as compared with defendant’s figure of $1,528,726.49 as the total direct cost of its work under the supplemental agreement. Giving the defendant credit for $7,257.27 for dividends and insurance premiums, plaintiff then claims as the final net cost of its supplemental contract work, the sum of $1,535,136.56. It is plaintiff’s contention that 10% thereof, or the sum of $153',513.65, constitutes its allowable overhead expense in determining moneys due it pursuant to the supplemental agreement with defendant.

Compensation for the work to be performed by plaintiff under this agreement is set forth in paragraph 6 thereof, which provides as follows: “ the cost of performing the work * * * shall be determined in accordance with Items 1 to 9 of Article 26 of the Contract Agreement, it being expressly understood that this method of determining the cost is to be used solely for the purpose of preparing and paying partial estimates and that the final and actual cost of all the worlc shall be determined as hereinafter set forth.” (Italics added.)

It is apparent from the language of this provision that the 10% overhead method of determining plaintiff’s costs was intended only as a method of convenience adopted by the parties solely for the purpose of facilitating and expediting partial and interim payments during the progress of the work. Contrary to plaintiff’s contention, the use of this method was not intended, nor is it a proper one, for computing the final actual cost of the work to the defendant, inclusive of the direct cost and the overhead. The words of paragraph 6 “ as hereinafter set forth ’ ’ clearly refer to subdivisions (a) and (b) of paragraph 15 of the supplemental agreement, which subdivisions define the direct cost and the specific items of actual overhead expense that may be charged to defendant. In determining the final actual cost of the work, therefore, the computation must be made in accordance with the terms of paragraph 15, rather than the provisional method set forth in paragraph 6 for the payment of partial estimates only. It necessarily follows that in the computation of such final cost, for the purpose of fixing the final payment due plaintiff therefor, plaintiff is obligated under the unambiguous provisions of paragraphs 6 and 15 of the supplemental agreement to treat as overhead only the actual and allowable items of overhead as specified and restricted in the provisions of said paragraph 15 (b). ■ In the opinion of the [570]*570court, to sustain plaintiff’s contention that it had a right to utilize the 10% method of computing its overhead in connection with its demand for final payment from defendant for its work under the supplemental agreement would he an unjustifiable attempt to construe the language of paragraph 6 beyond its plain, clear, and ordinary meaning (Brainard v. New York Cent. R. R. Co., 242 N. Y. 125, 131-32; Hartigan v. Casualty Co. of America, 227 N. Y. 175, 179-180). The mere fact that the parties could have worded paragraph 6 more aptly and suitably is irrelevant. The inexactitude, inadequacy or ineptitude of the draftsmanship of the provisions of the supplemental agreement do not justify or warrant a total disregard or rejection by the court of the clear intent of the parties to employ the 10% method “ solely for the purpose of preparing and paying partial estimates.” (Standard Oil. Co. of N. Y. v. Central Dredging Co., 225 App. Div. 407, 410, affd. 252 N. Y. 545; Cameron-Hawn Realty Co. v. City of Albany, 207 N. Y. 377, 381-382.)

Defendant, however, improperly limited plaintiff’s items of overhead to the date of the completion of the field work. The cost to a contractor of performing work does not begin with the actual physical labor in the field, nor does it stop when this work is completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hartigan v. . Casualty Co. of America
124 N.E. 789 (New York Court of Appeals, 1919)
Rapid Transit Subway Construction Co. v. City of New York
182 N.E. 145 (New York Court of Appeals, 1932)
Prager v. New Jersey Fidelity & Plate Glass Insurance Co. of Newark
156 N.E. 76 (New York Court of Appeals, 1927)
Standard Oil Co. v. Central Dredging Co.
170 N.E. 137 (New York Court of Appeals, 1929)
Cameron-Hawn Realty Co. v. . City of Albany
101 N.E. 162 (New York Court of Appeals, 1913)
Standard Oil Co. v. Central Dredging Co.
225 A.D. 407 (Appellate Division of the Supreme Court of New York, 1929)
Rusciano & Son Corp. v. State
281 A.D. 733 (Appellate Division of the Supreme Court of New York, 1952)
Rusciano & Son Corp. v. State
201 Misc. 690 (New York State Court of Claims, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
11 Misc. 2d 566, 178 N.Y.S.2d 1, 1957 N.Y. Misc. LEXIS 2808, Counsel Stack Legal Research, https://law.counselstack.com/opinion/subterrane-corp-v-city-of-new-york-nysupct-1957.