Rapid Transit Subway Construction Co. v. City of New York

182 N.E. 145, 259 N.Y. 472, 1932 N.Y. LEXIS 973
New York Court of Appeals·Decided July 19, 1932·Published·Cited by 69 cases

Opinion

*477 Lehman, J.

On or about August 7, 1914, the city of New York, acting by the Public Service Commission, entered into a contract with the plaintiff, Rapid Transit Subway Construction Company, whereby the plaintiff agreed to furnish at unit prices all the labor and materials necessary for the construction of a part of the Seventh Avenue-Lexington Avenue Rapid Transit Railroad, known as Route 5, Section 7, in accordance with the terms of the contract and the plans and specifications incorporated in it.

The contract required the plaintiff to begin actual work within sixty days after the date of delivery of the contract and to complete the work within thirty-one months after such delivery and, in the event of delay in completion of the work, beyond the period prescribed or beyond the period to which such time may be extended by resolution of the Commission for good cause shown,” the plaintiff agreed to pay the sum of three hundred dollars as stipulated damages for each day’s delay. According to the certificate of the engineer of the Public Service Commission the work was completed on November 1st, 1918, more than eighteen months after the expiration of the period prescribed in the contract, but the Commission duly extended that period by resolution.

The contract provides that “ whenever in the opinion of the Engineer the Contractor shall have completely performed the contract the Engineer shall so certify in writing and in duplicate to the Commission, and in his certificate shall state from actual measurement the whole amount of work done by the Contractor * * *. Upon the receipt of such certificate the Commission shall forthwith prepare and certify two final vouchers * * *. One of such final vouchers shall be payable by the City. * * * The City shall pay the amount due on such voucher payable by it on or before the expiration of ninety (90) days after the acceptance of the work herein agreed to be done by the Contractor and the filing of a *478 certificate of the completion and acceptance of the work in the office of the Comptroller signed by the Engineer and the Commission.”

Promptly after the work was completed the plaintiff requested that a certificate of the completion and acceptance of the work should be prepared and signed. The final certificates and vouchers for payment were not prepared and signed till December 7th, 1920, more than two years after the date of completion.

During the interval the engineer made five partial estimates of the work, theretofore performed by the contractor, for which the contractor had not been paid. The plaintiff received payments aggregating $66,045.44 upon such partial estimates. The final estimate and certificates showed that a balance of $61,119.65 remained due and payable to the plaintiff from the city of New York. The plaintiff claimed that a much larger amount was due for work under the contract and as damages for various alleged breaches by the city of its own obligations under the contract. The contract provides that “ The acceptance by the Contractor of the final payment by the City aforesaid * * * shall be and shall operate as a release to the City from all claim and liability to the Contractor for anything done or furnished for, or relating to the work. * * * ” The plaintiff refused final payment for its work and presented its claim to the Comptroller. Then it began this action. Thereafter, under a special agreement with the city, it received from the city the sum of $61,000, leaving only the sum of $119.65 due to it under the final certificate.

The complaint herein sets forth six causes of action involving numerous items of work for which, the plaintiff urges, it has not been paid in accordance with the terms of the contract and, in addition, several claims for damages for alleged defaults by the city under the contract. It demands judgment for sums which, with interest as claimed by the plaintiff, would amount to approximately *479 one million dollars. After a protracted trial, a verdict in favor of the plaintiff was directed for the sum of $84,949.17. From the judgment entered on that verdict the plaintiff appealed to the Appellate Division which modified the judgment by addition of the sum of $119.65, concededly due to the plaintiff under the final certificate, which through inadvertence had not been included in the original judgment.

Since the defendant did not appeal, we are concerned now only with those claims and items set forth in the complaint which were not allowed in the final certificate and for which recovery was denied by the courts below. The appellant urges that the trial judge erred in denying recovery for a considerable number of unrelated items. Each of these items must be examined separately, but in most instances the questions presented are narrow. The most serious questions, both in the amount involved and in the importance of the governing legal principles, relate to the denial of recovery for alleged neglect of the city in failing to furnish, within a reasonable time, drawings and directions which were required for the prompt and orderly performance of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Rapid Transit Subway Construction Co. v. City of New York, 182 N.E. 145, 259 N.Y. 472, 1932 N.Y. LEXIS 973 (N.Y. 1932).

182 N.E. 145 (Rapid Transit Subway Construction Co. v. City of New York) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Village of Ilion v. County of Herkimer
18 N.E.3d 359 (New York Court of Appeals, 2014)
Optigen, LLC v. Int'l Genetics, Inc.
877 F. Supp. 2d 33 (N.D. New York, 2012)
Worthy v. New York City Housing Authority
21 A.D.3d 284 (Appellate Division of the Supreme Court of New York, 2005)
Morris v. New York State Department of Taxation & Finance
623 N.E.2d 1157 (New York Court of Appeals, 1993)
Stephens v. American Home Assurance Co.
811 F. Supp. 937 (S.D. New York, 1993)
Boyle v. Jacor Communications, Inc.
799 F. Supp. 811 (S.D. Ohio, 1992)
William Wrigley Jr. Co. v. Waters
890 F.2d 594 (Second Circuit, 1989)
William Wrigley Jr. Company v. Eric Waters
890 F.2d 594 (Second Circuit, 1989)
Key International Manufacturing, Inc. v. Morse/Diesel, Inc.
142 A.D.2d 448 (Appellate Division of the Supreme Court of New York, 1988)
A/S DOMINO MOBLER v. Braverman
669 F. Supp. 592 (S.D. New York, 1987)
Fehr Bros. v. Scheinman
121 A.D.2d 13 (Appellate Division of the Supreme Court of New York, 1986)
AFP Imaging Corp. v. Ross
780 F.2d 202 (Second Circuit, 1985)
Afp Imaging Corporation v. Ross
780 F.2d 202 (Second Circuit, 1985)
We're Associates Co. v. Cohen, Stracher & Bloom, P. C.
65 N.Y. 148 (New York Court of Appeals, 1985)
We're Associates Co. v. Cohen, Stracher & Bloom, P. C.
103 A.D.2d 130 (Appellate Division of the Supreme Court of New York, 1984)
Zanoni v. 855 Holding Co.
96 A.D.2d 860 (Appellate Division of the Supreme Court of New York, 1983)
Soanes v. Baltimore & Ohio Railroad
89 F.R.D. 430 (E.D. New York, 1981)