Stuart Inv. Co. v. Westinghouse Electric Corp.

11 F.R.D. 277, 1951 U.S. Dist. LEXIS 3605
CourtDistrict Court, D. Nebraska
DecidedMarch 2, 1951
DocketCiv. No. 69
StatusPublished
Cited by18 cases

This text of 11 F.R.D. 277 (Stuart Inv. Co. v. Westinghouse Electric Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stuart Inv. Co. v. Westinghouse Electric Corp., 11 F.R.D. 277, 1951 U.S. Dist. LEXIS 3605 (D. Neb. 1951).

Opinion

DELEHANT, District Judge.

Exhaustive analysis of the voluminous file in this action need not be made on this occasion. Counsel are intimately aware of the underlying factual history of the principal controversy between their clients and of the plaintiff’s ultimate objective in the present suit. They also understand the issues immediately before the court for ruling. Except as to subsequent developments, an effort was made by the writer of this- memorandum on October 27, 1950 in the oral announcement of the final disposition of an earlier action arising from the same transaction and then pending here, to identify and summarily to recount the facts upon which that case rested entirely, and this one largely depends. So, only a very brief and admittedly incomplete outline will now be offered in respect of the issues in the present case and its facts. It will shortly be apparent that the litigation has to be carried forward to final submission and determination in the ordinary course. And it is appropriate that the finding and announcement of facts be reserved until that determination. It is equally in order that the major legal issues in the case be discussed then, and only the procedural and administrative considerations involved in the motions now decided be presently mentioned. This is true, notwithstanding the comprehensive briefs covering the entire field of the litigation with which the court has already been favored by counsel. Inevitably, they have been oriented in large measure to the eventual merits of the matter in suit, for those merits lie at the roots of the two motions, if it be granted that the case is in such posture that either of them ought to be sustained.

The plainiff is a Nebraska corporation, the defendant a Pennsylvania corporation authorized to do business in Nebraska. A controversy largely exceeding $3,000 in its amount is unquestionably involved.

The defendant now is and for some eleven months has been prosecuting in the district court of Lancaster County, Nebraska, an action against the plaintiff to recover a large sum of money allegedly due on a contract for the construction or reconstruction and installation by the defendant of certain elevators in an office building belonging to the plaintiff and located in Lincoln, Nebraska. The plaintiff denies that it is indebted to the defendant and claims on the- contrary that, by reason of the latter’s defaults in their contract the plaintiff is entitled to recover from the defendant damages in a sum substantially exceeding any amount which may be unpaid to the defendant under the contract. That suit, except possibly for further pleadings in the way of reply to the answer and answer to the counterclaim, is at issue but untried and undetermined.

Omitting many relevant historical features, it is recalled that in the contract between the parties provisions were included, (a) for the submission to the architect for decision of the defendant’s applications or claims for payments, and also of disputes between the parties under the contract, and for the making of deci-' sion thereon by the architect, subject to appeal and to arbitration, and (b) for arbitration (with adequate procedural -machinery) in sundry specific situations, including, by way of appeal, decisions of the architect except in matters relating to artistic effect, if within the terms of the contract. The dispute between the parties having arisen, reference of it to the architect was maeje and at least some showing upon it was made at an appointed time to the architect who shortly made a finding in writing to the [279]*279general effect that the plaintiff was not indebted to the defendant in the premises. No appeal was prosecuted from that finding, either by resort to arbitration, or otherwise, by the plaintiff or at the instance of the defendant. On the contrary, the defendant, almost immediately after the architect’s finding, instituted the action in the state court to which reference has already been made.

Some months thereafter the plaintiff, in the earlier case in this court, sought an order, within Title 9 U.S.C.A. § 4, compelling the defendant to proceed to arbitration. In the oral announcement of ruling mentioned above, and by appropriate findings of fact, conclusions of law and judgment, prepared thereafter and entered on December 18, 1950, this -court denied the relief sought and dismissed the case. No appeal was prosecuted from that judgment.

This action for a declaratory judgment under Title 28 U.S.C.A. § 2201 was instituted on December 20, 1950. In its complaint (with amendments), the plaintiff set out the history of the relations and earlier, and then and still pending litigation between the parties and, among other things, prayed “that the court adjudge:

jjt

“2. That Section 2, Title 9, U.S.C.A. declares substantive law and is applicable to said contract in both State and Federal courts, and that it is the law of the State of Nebraska.

“3. That the clause of said contract providing that arbitration is the only method of appeal from the architects’ decision is valid and- enforceable under Section 2, Title 9, U.S.C.A.

“4. That neither plaintiff nor defendant appealed from the architects’ decision to arbitration, pursuant to the provisions of the contract.

“5. That the architects’ decision that the plaintiff is not indebted to the defendant has become final and conclusive of the rights of both parties and is binding upon them because neither party appealed to arbitration as provided in said contract, and therefore there is no- amount owing the defendant by the plaintiff under said contract.”

Against that complaint, the defendant on January 12, 1951 served and filed a motion to dismiss for failure, to state a claim upon which relief can be granted, under Fed.Rules Civ.Proc. Rule 12(b)(6), 28 U.S. C.A. On the same day the court entered an order setting that motion for hearing on January 20, 1951. But on January 18, 1951 the plaintiff served and filed a motion for summary judgment in its behalf under Rule 56. Thereupon, and immediately, the court vacated its earlier order for hearing on the motion to dismiss and directed that the two motions then pending be heard together. By agreement of the parties the motions were presented on February 13, 1951, after which briefs were submitted by counsel. The action is now pending upon those motions and the complaint as amended and the showings in writing made by the parties. It must be recalled that the defendant has not yet answered.

The court considers that, in the light of the posture of the pleadings, it should deny and overrule both motions. An order to-that effect, and also requiring the defendant to answer within twenty days from this date is being entered. The reasons which induce that ruling will be set down very briefly.

While the motion for summary judgment was the more recently filed of the two pleadings, it may properly have the earlier attention in this ruling.

No doubt- is entertained respecting the adaptability of the procedure for summary judgment under Rule 56 to a proceeding for a declaratory judgment under Title 28 U.S.C.A. § 2201. If conditions appropriate for the entry of a summary judgment otherwise exist, its allowance may not be intercepted by the circumstance that the judgment sought will be declaratory in its nature. California Apparel Creators v. Wieder, D.C.N.Y., 68 F.Supp. 499; Northland Greyhound Lines v. Amalgamated Association, D.C.Minn., 66 F.Supp. 431.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Kjk Const. Co., Inc.
414 B.R. 416 (N.D. Illinois, 2009)
Beach Higher Power Corp. v. Granados
717 So. 2d 563 (District Court of Appeal of Florida, 1998)
Rodriguez v. Tri-Square Const., Inc.
635 So. 2d 125 (District Court of Appeal of Florida, 1994)
Tapper v. Herbst (In Re Herbst)
76 B.R. 882 (D. Massachusetts, 1987)
First American Bank, N. A. v. United Equity Corp.
89 F.R.D. 81 (District of Columbia, 1981)
H. Daroff & Sons, Inc. v. Strickland Transportation Co.
284 F. Supp. 510 (E.D. Pennsylvania, 1968)
Jackson v. Stelco Employees' Credit Union
178 So. 2d 58 (District Court of Appeal of Florida, 1965)
Coast Cities Coaches, Inc. v. Dade County
178 So. 2d 703 (Supreme Court of Florida, 1965)
Wallens v. Lichtenstein
159 So. 2d 912 (District Court of Appeal of Florida, 1964)
United States v. McFaddin Express, Inc.
197 F. Supp. 289 (D. Connecticut, 1961)
Coast Cities Coaches, Inc. v. Whyte
130 So. 2d 121 (District Court of Appeal of Florida, 1961)
Lehew v. Larsen
124 So. 2d 872 (District Court of Appeal of Florida, 1960)
Olin's, Inc. v. Avis Rental Car System of Florida, Inc.
105 So. 2d 497 (District Court of Appeal of Florida, 1958)
Stuart Investment Co. v. Westinghouse Electric Corp.
192 F.2d 935 (Eighth Circuit, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
11 F.R.D. 277, 1951 U.S. Dist. LEXIS 3605, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stuart-inv-co-v-westinghouse-electric-corp-ned-1951.