Structural Metals, Inc. v. S&C Electric Company

CourtCourt of Appeals for the Fifth Circuit
DecidedOctober 6, 2014
Docket13-50666
StatusUnpublished

This text of Structural Metals, Inc. v. S&C Electric Company (Structural Metals, Inc. v. S&C Electric Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Structural Metals, Inc. v. S&C Electric Company, (5th Cir. 2014).

Opinion

Case: 13-50332 Document: 00512794420 Page: 1 Date Filed: 10/06/2014

IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT

No. 13-50332 United States Court of Appeals Fifth Circuit

FILED Con. w/ 13-50666 October 6, 2014 Lyle W. Cayce STRUCTURAL METALS, INCORPORATED, Clerk

Plaintiff - Appellee

v.

S&C ELECTRIC COMPANY,

Defendant - Appellant

Appeals from the United States District Court for the Western District of Texas USDC No. 5:09-CV-984

Before KING, GRAVES, and HIGGINSON, Circuit Judges. PER CURIAM:* Appellant S&C Electric Company appeals the district court’s denial of its motion for remittitur as well as the district court’s award of attorney’s fees to Appellee Structural Metals, Inc. For the following reasons, we AFFIRM the judgment of the district court.

* Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4. Case: 13-50332 Document: 00512794420 Page: 2 Date Filed: 10/06/2014

No. 13-50332 c/w No. 13-50666 I. Factual and Procedural Background Plaintiff-Appellee Structural Metals, Inc. operates a steel recycling plant in Seguin, Texas. Steel recycling is, as one might imagine, a process that demands a significant amount of power. Yet the amount of power required is not constant. Smaller pieces of scrap require less power, while larger pieces require more. That fluctuation in the demand for power can cause dips in the overall flow of electricity throughout the plant. When Structural Metals acquired a new caster, 1 which was unable to tolerate variances in voltage of more than 5 per cent, it began looking for a solution that would make the flow of electricity throughout the plant more reliable. To that end, Structural Metals began negotiating with Defendant- Appellant S&C Electric Company. Between 2003 and 2005, Structural Metals and S&C Electric negotiated various proposals for the purchase of Adaptive VAR Compensators (“AVC”), which were meant to ensure that the amount of power flowing throughout the steel recycling plant remained consistent. Some of the proposals involved the purchase of the AVCs and all of the additional facilities, products, and installation required to make them work. Other proposals were simply for the purchase of the AVCs themselves. Structural Metals ended up accepting the proposal for the AVC units only, electing to purchase the additional products elsewhere and to have another company install the AVCs and build the necessary facility. The purchase price for the AVCs was $306,500. Nevertheless, Structural Metals has maintained throughout this action that its contract was for an “AVC System,” by which it presumably meant that S&C Electric had sold it an overall design to regulate its power flow, not just the AVC units that were the centerpiece of that design. Structural Metals’s

1 A caster transforms the molten steel into solid steel bars for storage and transport. 2 Case: 13-50332 Document: 00512794420 Page: 3 Date Filed: 10/06/2014

No. 13-50332 c/w No. 13-50666 argument was that even though Structural Metals did not purchase all of the components of that design from S&C Electric, S&C Electric was responsible for making sure the overall design worked. S&C Electric hotly contested that interpretation of the contract, alleging that it only promised to sell the two individual AVC units, and that Structural Metals was responsible for implementing them after rejecting an offer to have S&C Electric build and install the entire system. In January of 2006, S&C Electric commissioned the two AVC units. From that point forward, Structural Metals began experiencing problems. Structural Metals contends that the AVC units never regulated the power level in the plant to the degree that S&C Electric had warranted. It also claims that the AVC units constantly overheated, causing damage to the capacitors and other components of the AVC system. S&C Electric responded to these concerns by promising to stand by its equipment. In November, 2006, it extended the warranty and promised to bring its equipment “to an acceptable condition.” Before it could follow through, however, a fire broke out in the AVC system on December 2, 2006 and caused extensive damage. Structural Metals blamed S&C Electric’s AVC units for causing the fire, and demanded its money back. When S&C Electric refused, Structural Metals sued for breach of contract and breach of warranty under Texas law. Under both theories of recovery, Structural Metals sought not just the value of the AVC units, but the value of the entire “AVC System,” including components purchased from other companies. After the litigation began, the cause of the fire continued to be a major issue. Structural Metals contended that the AVC units caused the fire, whereas S&C Electric claimed that the electrical cables running from one of 3 Case: 13-50332 Document: 00512794420 Page: 4 Date Filed: 10/06/2014

No. 13-50332 c/w No. 13-50666 the AVC units to one of the transformers—which had not been installed by S&C Electric—were the cause. S&C Electric claimed that the cables used were rated for too low a current and were overtaxed by the AVC system, causing them to overheat and arc, causing the fire. The electric cables ran through an underground culvert from the building housing the AVC units to the transformers. After the fire, Structural Metals retrieved the electric cables from the burned out, melted culvert and stored them in a locked building on the plant’s premises. Yet, before S&C Electric was able to investigate the cables in connection with this litigation, the cables disappeared. 2 As a spoliation remedy, the district court approved Structural Metals’s proposal that it not be allowed to contest that the fire started in the cables at trial. After the fire, Structural Metals filed a claim with its insurance company, Liberty Mutual. Liberty Mutual investigated the fire damage and prepared a list of items that needed to be repaired or replaced and proposed a settlement of the insurance claim. After some negotiation, Liberty Mutual agreed to settle the claim for $475,650, which, after Structural Metals’s $200,000 deductible, resulted in a net insurance payment of $275,650. The case went to trial in November 2009, with Structural Metals asserting a breach of contract claim that also included theories of breach of an express warranty, breach of the implied warranty of merchantability, and breach of the implied warranty of fitness for a particular purpose. On the breach of warranty claims, the jury was instructed that the measure of damages is “[t]he difference, if any, at the time and place of acceptance,

2 Structural Metals had suffered a series of copper thefts from its plant. The lock on the building in which the cables were being stored was found damaged around the time that Structural Metals discovered the cables were missing. The cables contained copper. 4 Case: 13-50332 Document: 00512794420 Page: 5 Date Filed: 10/06/2014

No. 13-50332 c/w No. 13-50666 between the value of the AVC system accepted and the value that the AVC system would have had if it had been as warranted.” The jury found S&C Electric liable for breach of an express warranty, breach of the implied warranty of merchantability, and breach of the implied warranty of fitness for a particular purpose. 3 The jury awarded Structural Metals $306,500 in damages. After the verdict, S&C Electric moved the court to remit the damages award under Federal Rule of Civil Procedure 59(e). 4 S&C Electric argued that its damages should be remitted by the amount of the insurance payment that Structural Metals received from Liberty Mutual.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mathis v. Exxon Corporation
302 F.3d 448 (Fifth Circuit, 2002)
DP Solutions, Inc. v. Rollins, Inc.
353 F.3d 421 (Fifth Circuit, 2003)
Foradori v. Harris
523 F.3d 477 (Fifth Circuit, 2008)
Richardson v. Marsh
481 U.S. 200 (Supreme Court, 1987)
Consolidated Companies, Inc. v. Lexington Insurance
616 F.3d 422 (Fifth Circuit, 2010)
RANDALL D. WOLCOTT, MD, PA v. Sebelius
635 F.3d 757 (Fifth Circuit, 2011)
Medical City Dallas, Ltd. v. Carlisle Corp.
251 S.W.3d 55 (Texas Supreme Court, 2008)
United States v. Reagan
596 F.3d 251 (Fifth Circuit, 2010)
Toshiba MacHine Co. v. SPM Flow Control, Inc.
180 S.W.3d 761 (Court of Appeals of Texas, 2005)
Brown v. American Transfer & Storage Co.
601 S.W.2d 931 (Texas Supreme Court, 1980)
Stewart Title Guaranty Co. v. Sterling
822 S.W.2d 1 (Texas Supreme Court, 1992)
Jones v. Kelley
614 S.W.2d 95 (Texas Supreme Court, 1981)
Green International, Inc. v. Solis
951 S.W.2d 384 (Texas Supreme Court, 1997)
Arthur Andersen & Co. v. Perry Equipment Corp.
945 S.W.2d 812 (Texas Supreme Court, 1997)
City of Dallas v. Arnett
762 S.W.2d 942 (Court of Appeals of Texas, 1988)
Aaron Glenn Haygood v. Margarita Garza De Escabedo
356 S.W.3d 390 (Texas Supreme Court, 2011)
Tony Gullo Motors I, L.P. and Brien Garcia v. Nury Chapa
212 S.W.3d 299 (Texas Supreme Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Structural Metals, Inc. v. S&C Electric Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/structural-metals-inc-v-sc-electric-company-ca5-2014.