Stronghold Engineering v. City of Monterey CA4/1

CourtCalifornia Court of Appeal
DecidedJune 21, 2024
DocketD082763
StatusUnpublished

This text of Stronghold Engineering v. City of Monterey CA4/1 (Stronghold Engineering v. City of Monterey CA4/1) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stronghold Engineering v. City of Monterey CA4/1, (Cal. Ct. App. 2024).

Opinion

Filed 6/21/24 Stronghold Engineering v. City of Monterey CA4/1 NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

COURT OF APPEAL, FOURTH APPELLATE DISTRICT

DIVISION ONE

STATE OF CALIFORNIA

STRONGHOLD ENGINEERING, D082763 INCORPORATED,

Plaintiff and Appellant, (Super. Ct. No. CVRI2103427) v.

CITY OF MONTEREY,

Defendant and Respondent.

APPEAL from a judgment of the Superior Court of Riverside County, Chad W. Firetag, Judge. Affirmed in part, reversed in part and remanded.

Varela, Lee, Metz & Guarino and Andrew Van Ornum, for Plaintiff and Appellant. Colantuono, Highsmith & Whatley; Michael G. Colantuono, Megan A. Wharton and Merete E. Rietveld; Christine Davi, City Attorney, for Defendant and Respondent. Appellant Stronghold Engineering Incorporated (Stronghold) successfully bid to renovate the City of Monterey’s (the City) conference center and Portola Plaza (the Project). The City later issued a notice of violation against Stronghold under the Subletting and Subcontracting Fair Practices Act (Pub. Contract Code,1 § 4100 et seq., the Act) for allegedly substituting its concrete and waterproofing subcontractors without notice or the City’s consent. Stronghold appealed to the City’s Appeals Hearing Board (the Board) who sided with the City and assessed penalties against Stronghold for both substitutions. Stronghold filed this action challenging the Board’s decision and the role of a city attorney at the hearing. The trial court found in the City’s favor. Stronghold appeals from the court’s ruling, contending: (1) the Board did not conduct a fair hearing consistent with due process; (2) the laches doctrine barred the City’s claims; and (3) substantial evidence does not support the Board’s decision. We conclude the City’s claim as to the waterproofing subcontractor is barred by laches and remand the matter to the trial court to reverse this penalty assessment. We otherwise reject Stronghold’s arguments. FACTUAL AND PROCEDURAL BACKGROUND2 In October 2015, Stronghold submitted a bid to the City for the Project. The bid listed West Coast Concrete as the concrete subcontractor and Gino Rinaldi, Inc. (Rinaldi) as the waterproofing subcontractor. In November 2015, the City awarded the Project contract to Stronghold and the parties

1 Undesignated statutory references are to the Public Contract Code.

2 This section provides a brief background regarding the parties’ disputes. We provide additional background facts in the sections of this opinion addressing Stronghold’s arguments on appeal.

2 entered into a written contract. Stronghold sub-contracted with Perry Coast Construction (Perry) for the concrete work in December 2015 and with F.D. Thomas, Inc. (F.D. Thomas) for waterproofing in April 2016. In 2016, Stronghold sued the City regarding interpretation of the contract and later amended its complaint to seek damages due to the City’s alleged deficient design and resulting delays (the civil litigation). The City filed its initial cross-complaint in January 2018. In March 2020, the City claimed it learned of the subcontractor substitutions during discovery. In January 2021, it amended its cross-complaint to allege that Stronghold violated the Act based on its substitution of Perry for West Coast Concrete and F.D. Thomas for Rinaldi. The civil litigation is still pending. Separately, in September 2020, the City’s public works director sent Stronghold a letter notifying it of the Act violations and that the matter had been set for a hearing before the Board to consider the City’s request for $437,230 in statutory penalties. As relevant here, the letter claimed: (1) Perry and West Coast Concrete were not the same company, and West Coast Concrete did not exist; and (2) Stronghold contracted with F.D. Thomas for the waterproofing, not Rinaldi as listed in the bid. After a hearing, on December 7, 2020, the Board issued a decision penalizing Stronghold for two violations of the Act. It imposed a $291,000 penalty for the concrete subcontractor substitution and $50,000 for the waterproofing subcontractor substitution, totaling $341,000. Stronghold initiated this action by filing a combined petition for traditional mandamus (Code Civ. Proc., § 1085) and administrative mandamus (id., § 1094.5) challenging the Board’s decision. Among other things, Stronghold claimed the hearing process was unfair, the City’s allegations should have been time-barred, and the evidence did not support

3 the Board’s decision. The trial court denied the writ, finding Stronghold received a fair hearing and substantial evidence supported the Board’s conclusion that Stronghold violated the Act. DISCUSSION I. THE BOARD’S HEARING WAS FAIR Stronghold argues on appeal that the Board was unconstitutionally biased against it because the Board’s legal advisor at the hearing, Salameh, was an attorney in the office that was suing it in the civil litigation, i.e. the

City Attorney’s Office.3 A. Additional Background At the Board’s contested hearing to consider penalties against Stronghold based on alleged violations of the Act, the City was represented by outside counsel, the same outside counsel who represented the City in the civil litigation. Salameh was present at the hearing to advise the Board. Specifically, review of the hearing transcript shows Salameh acted as an advisor and moderator regarding proper hearing procedures. Because of Salameh’s involvement in the hearing, Stronghold objected to the hearing process as unfair. In response, Salameh made an unsworn statement claiming she has been segregated from other members of the City Attorney’s Office and has not communicated with the public works director or any other colleagues in her office regarding the Board hearing or their preparations for it. Davi made a similar unsworn statement for the record.

3 In the civil litigation, the caption of the amended cross-complaint lists as representing the City both the City Attorney’s Office and City Attorney Christine Davi, and outside counsel. Salameh is not listed on the caption in the civil litigation.

4 After the hearing, Salameh drafted the Board’s proposed decision. At a subsequent hearing to adopt the proposed decision, she stated: “I tried to distill the Board’s deliberations from the November 18th, 2020 hearing and the findings they made and then the ultimate vote imposing penalties for two violations. So I tried to capture all of that in the written decision but, of course, you are welcome to edit and provide further direction as you see fit.” The Board adopted the proposed decision as its own. Stronghold filed a verified petition for traditional mandamus and administrative mandamus in the superior court, seeking to set aside the Board’s decision. The court granted Stronghold’s motion to augment the administrative record to include a privilege log from the City showing Salameh’s communications relating to the civil litigation. The privilege log shows that from November 10, 2014, to July 31, 2018, Salameh was copied on 14 privileged communications. On March 9, 2018, after being copied on two privileged communications, Salameh prepared two privileged emails and directly received two privileged emails. After the privilege log was mentioned at the hearing, Salameh stated, “And, again, I’ll just say for the record, you know, those likely were e-mails with Staff from years ago.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ward v. Village of Monroeville
409 U.S. 57 (Supreme Court, 1972)
Samuels v. Mix
989 P.2d 701 (California Supreme Court, 1999)
Brown v. State Personnel Board
166 Cal. App. 3d 1151 (California Court of Appeal, 1985)
Midstate Theatres, Inc. v. County of Stanislaus
55 Cal. App. 3d 864 (California Court of Appeal, 1976)
Breakzone Billiards v. City of Torrance
97 Cal. Rptr. 2d 467 (California Court of Appeal, 2000)
Nasha L.L.C. v. City of Los Angeles
22 Cal. Rptr. 3d 772 (California Court of Appeal, 2004)
Nightlife Partners, Ltd. v. City of Beverly Hills
133 Cal. Rptr. 2d 234 (California Court of Appeal, 2003)
Magic Kitchen LLC v. Good Things International, Ltd.
63 Cal. Rptr. 3d 713 (California Court of Appeal, 2007)
Donley v. Davi
180 Cal. App. 4th 447 (California Court of Appeal, 2009)
Jensen v. BMW of North America, Inc.
35 Cal. App. 4th 112 (California Court of Appeal, 1995)
TJX Companies, Inc. v. Superior Court of Orange County
163 Cal. App. 4th 80 (California Court of Appeal, 2008)
Craig v. City of Poway
28 Cal. App. 4th 319 (California Court of Appeal, 1994)
Howitt v. Superior Court
3 Cal. App. 4th 1575 (California Court of Appeal, 1992)
Cal-Air Conditioning, Inc. v. Auburn Union School District
21 Cal. App. 4th 655 (California Court of Appeal, 1993)
Titan Elec. v. La Unified School Dist.
72 Cal. Rptr. 3d 570 (California Court of Appeal, 2008)
Morey v. Vannucci
64 Cal. App. 4th 904 (California Court of Appeal, 1998)
Quintero v. City of Santa Ana
7 Cal. Rptr. 3d 896 (California Court of Appeal, 2003)
Fountain Valley Regional Hospital & Medical Center v. Bonta'
89 Cal. Rptr. 2d 139 (California Court of Appeal, 1999)
NILES FREEMAN EQUIPMENT v. Joseph
74 Cal. Rptr. 3d 690 (California Court of Appeal, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Stronghold Engineering v. City of Monterey CA4/1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stronghold-engineering-v-city-of-monterey-ca41-calctapp-2024.