Stronghold Engineering, Inc. v. City of Monterey

CourtCalifornia Court of Appeal
DecidedNovember 6, 2023
DocketH050157
StatusPublished

This text of Stronghold Engineering, Inc. v. City of Monterey (Stronghold Engineering, Inc. v. City of Monterey) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stronghold Engineering, Inc. v. City of Monterey, (Cal. Ct. App. 2023).

Opinion

Filed 11/3/23 CERTIFIED FOR PUBLICATION

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SIXTH APPELLATE DISTRICT

STRONGHOLD ENGINEERING H050157 INCORPORATED, (Santa Clara County Super. Ct. No. 18-CV-329015) Plaintiff and Appellant,

v.

CITY OF MONTEREY,

Defendant and Respondent.

Before filing a lawsuit asserting a claim for money or damages against a public entity, the Government Claims Act (Gov. Code, § 810 et seq.) requires that a claim be presented to the entity. That requirement does not apply to an action seeking purely declaratory relief. As applied here, a declaratory relief action seeking interpretation of a contract is not a claim for money or damages, even if the judicial interpretation sought may later be the basis for a separate claim for money or damages which would itself trigger the claim presentation requirement. Defendant City of Monterey contracted with Stronghold Engineering Incorporated to renovate the city’s conference center and adjacent plaza. A dispute arose about which party was financially responsible under the contract and a change order for unforeseen delays in the renovation. Without first presenting a claim to the city, Stronghold filed suit seeking a declaration of its rights and duties under the contract and the change order. Stronghold’s single cause of action for declaratory relief sought a determination that the “City must compensate Stronghold for due compensable or excusable delays in time and money for any changes made by or caused by the City to the Project that negatively impact the critical path.” The trial court sustained a demurrer with leave to amend based on the failure to present a claim before suing. Stronghold then presented multiple claims to the city alleging the city rejected proposed change orders related to delays which were caused by specific undisclosed site conditions. After the claims were denied, Stronghold amended its complaint to allege breach of contract causes of action based on the claims it had presented. The trial court ultimately granted summary judgment for the city, finding Stronghold’s failure to present a claim before initially filing suit doomed the entire action. As we will explain, we conclude that because the initial action sought purely declaratory relief, the trial court was incorrect to sustain the demurrer and later grant summary judgment. We will therefore reverse the judgment. I. TRIAL COURT PROCEEDINGS Stronghold and the city entered into a contract in December 2015 to renovate the Monterey Conference Center and Portola Plaza. The contract required Stronghold to give written notice before seeking additional compensation for any aspect of the renovation. Any change to the project had to be approved by the city by written change order. The contract specified a dispute resolution procedure for claims of $375,000 or less for “[p]ayment of money or damages arising from work done by or on behalf of the Contractor pursuant to this Contract and payment of which is not otherwise expressly provided for as the Contractor is not otherwise entitled.” The parties signed a change order in early 2016 to extend the completion date for the renovation. Stronghold agreed in the change order to “waive[] its rights to any due compensable or excusable delays in time and money for all known and unknown knowledge of the project conditions, including unforeseen site conditions and errors and omissions in the drawings and specifications, with the exception of any major owner 2 changes affecting the critical path of the schedule or Acts of God or of the public enemy, fire, floods, epidemics, quarantine restrictions, strikes and freight embargoes.” A dispute arose about how to interpret the waiver language. Without first presenting a claim to the city, Stronghold filed suit in December 2016 alleging a single cause of action for declaratory relief. The initial complaint alleged that “[b]ecause this is an action solely for declaratory relief regarding the meaning, interpretation and legality of a contract, the Tort Claims Act provisions are inapplicable.” The initial complaint did not request compensatory damages. The city demurred based on Stronghold not presenting a claim to the city before commencing the litigation, which the trial court sustained with leave to amend in February 2017. (The case then took multiple procedural turns not relevant to the issues raised on appeal, including multiple amended complaints, a cross-complaint by the city, and the transfer of the case from Monterey County to Santa Clara County on Stronghold’s motion (Code Civ. Proc., §§ 394, 397).) While the case was pending, Stronghold presented three claims to the city between September 2017 and July 2019. In those claims, Stronghold asserted that the city had refused to approve proposed change orders necessitated by what Stronghold contended were excusable delays. The claims referenced specific site conditions including unforeseen soil conditions, gas line conflicts, and design revisions. Stronghold filed the operative fourth amended complaint in October 2019 containing four causes of action. The first cause of action alleged that the city breached the project contract by, among other things, not providing a complete and accurate design and refusing to issue change orders for modifications to the scope of work. The second cause of action sought declaratory relief based on the same set of facts as the declaratory relief cause of action alleged in the initial complaint. The third cause of action also alleged breach of the renovation contract, focusing on the city’s refusal to issue change orders and pay Stronghold for extra, changed, and modified work. The fourth cause of 3 action alleged the city had violated the Public Contract Code by not promptly paying Stronghold for work. The city moved for summary judgment, arguing that the entire suit was barred by the failure to present a claim before filing the initial complaint. The court granted summary judgment by written order. The trial court reasoned that the declaratory relief cause of action in the initial complaint was, in essence, a claim for money or damages. The court further concluded that all causes of action in the operative complaint “lack merit as [Stronghold] failed to timely present a claim to public entity City prior to filing the instant action, thereby barring [Stronghold] from filing a lawsuit against that public entity.” The city dismissed its cross-complaint, and Stronghold appealed from the judgment. (The trial court later granted attorney fees and costs to the city as the prevailing party; Stronghold has challenged that postjudgment order in a separate appeal, with briefing stayed by stipulation pending resolution of this appeal.) II. DISCUSSION A. THE INITIAL COMPLAINT WAS NOT A CLAIM FOR MONEY OR DAMAGES “Government Code section 905 requires that ‘all claims for money or damages against local public entities’ be presented to the responsible public entity before a lawsuit is filed.” (City of Stockton v. Superior Court (2007) 42 Cal.4th 730, 734.) “[N]o suit for money or damages may be brought against a public entity on a cause of action for which a claim is required to be presented ... until a written claim therefor has been presented to the public entity.” (Gov. Code, § 945.4.) The claim presentation requirement does not apply to “ ‘non-pecuniary actions, such as those seeking injunctive, specific, or declaratory relief.’ ” (Minsky v. City of Los Angeles (1974) 11 Cal.3d 113, 121, fns. omitted.) Whether the initial complaint included a claim for money or damages is a question of statutory interpretation we review de novo. (Segal v. ASICS America Corp. (2022) 12 Cal.5th 651, 658.)

4 “A declaratory judgment action provides litigants with a quick, efficient means of resolving a disputed issue.” (Mycogen Corp. v. Monsanto Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Bock
549 U.S. 199 (Supreme Court, 2007)
Southern California Edison Co. v. City of Victorville
217 Cal. App. 4th 218 (California Court of Appeal, 2013)
Minsky v. City of Los Angeles
520 P.2d 726 (California Supreme Court, 1974)
State of California v. Superior Court
143 Cal. App. 3d 754 (California Court of Appeal, 1983)
Ameron Internat. Corp. v. Insurance Co. of State of Pennsylvania
242 P.3d 1020 (California Supreme Court, 2010)
City of Stockton v. Superior Court
171 P.3d 20 (California Supreme Court, 2007)
Mycogen Corp. v. Monsanto Co.
51 P.3d 297 (California Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Stronghold Engineering, Inc. v. City of Monterey, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stronghold-engineering-inc-v-city-of-monterey-calctapp-2023.