Stringer Construction Co. v. Chicago Housing Authority

563 N.E.2d 819, 206 Ill. App. 3d 250, 150 Ill. Dec. 692, 1990 Ill. App. LEXIS 1474, 1990 WL 139468
CourtAppellate Court of Illinois
DecidedSeptember 26, 1990
Docket1—89—0332
StatusPublished
Cited by17 cases

This text of 563 N.E.2d 819 (Stringer Construction Co. v. Chicago Housing Authority) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stringer Construction Co. v. Chicago Housing Authority, 563 N.E.2d 819, 206 Ill. App. 3d 250, 150 Ill. Dec. 692, 1990 Ill. App. LEXIS 1474, 1990 WL 139468 (Ill. Ct. App. 1990).

Opinion

PRESIDING JUSTICE CERDA

delivered the opinion of the court:

The plaintiff, Stringer Construction Company, Inc. (Stringer), 1 brought an action against the Chicago Housing Authority (CHA) seeking reimbursement for the costs of extra materials and labor expended in the construction of a housing project for senior citizens. Following a jury trial, the jury returned a verdict in favor of the plaintiff and awarded $334,813.25 in damages. The CHA appeals, contending that: (1) the trial court abused its discretion in granting plaintiff leave to amend its fourth amended complaint at the close of the evidence to plead a new cause of action; (2) the trial court abused its discretion for refusing to grant the CHA sufficient time to respond; (3) the trial court erred in denying its motions for directed verdict and judgment notwithstanding the verdict; (4) the trial court erred in refusing to give certain jury instructions; and (5) the plaintiff’s exclusive remedy lies with the Mechanics’ Liens Act (Ill. Rev. Stat. 1989, ch. 82, par. 1 et seq.) (the Act).

The evidence produced at trial reveals the following. In 1970, the CHA began a project to erect an 86-unit senior citizens home at the intersection of Larrabee and Wisconsin in Chicago. The CHA obtained Federal funding for the project from the Department of Housing and Urban Development (HUD) and entered into a consolidated annual contributions contract with HUD on June 13, 1972. On November 27, 1972, the CHA contracted with a developer to construct the building known as Project 111. 2-71. The developer could not fulfill its obligations and assigned its rights and obligations to a second developer, Industrial Mechanical, Inc. (Industrial). The CHA and HUD approved the assignment. American Insurance Company (American), a New Jersey corporation, issued a performance bond for the services to be rendered by Industrial. The contract required Industrial to complete the project by March 1, 1976. On September 1, 1976, the CHA declared Industrial in default of its contract.

In September of 1976, while the project was idle after Industrial was terminated, Philip Stringer was invited to meet with CHA officials to discuss taking over the project. Before the CHA declared Industrial in default, Stringer had been engaged as a subcontractor on the project and was therefore familiar with the project. At the CHA office, Stringer met with William Lebsock, the CHA’s director of engineering, and his assistant. Stringer was provided with the plans and specifications for the project and was asked to submit a preliminary estimate for completion of the work. After computing prices for completing the project and obtaining estimates from subcontractors, Stringer submitted a proposal to Lebsock. Lebsock then instructed Stringer to meet with American. After negotiations, American approved Stringer’s proposal. On April 21, 1977, the CHA sent a triparty contract proposal to Stringer, subject to Stringer’s obtaining an acceptable performance bond. On April 28, the CHA’s board of commissioners approved signing of the tri-party contract with American and Stringer, and Stringer immediately took over the project with the understanding that the contract would become effective once it obtained a performance bond.

Stringer commenced operations a week later, but had not yet received a response from its application for a performance bond. Construction progressed smoothly through the month of May and the first half of June. On June 15, Stringer was told to stop work because the CHA was contemplating a design change. As originally designed, each unit was to be equipped with its own kitchen. The CHA decided, however, to seek approval from HUD to eliminate the kitchens and install a central kitchen and dining facility on the first floor, a design the CHA refers to as the “congregate kitchen” format. At the time, Stringer had already installed the plumbing, heating, telephone risers and electrical lines in the walls and floors in 20 of the 86 units. A letter dated July 21, 1977, was sent to HUD from the CHA’s executive director submitting a preliminary cost estimate for the conversion and requesting HUD’s approval and additional funding. The letter noted that additional HUD funding was required because “surplus funds [were] not available from other development programs.” Stringer protested to the CHA’s project inspector, A.B. Lundquist, complaining of the inevitable cost increases that would result from any delay.

The project lay dormant until mid-August of 1977 when Stringer was advised by American that HUD had disapproved of the congregate kitchen proposal. During the work stoppage, Stringer had learned that it could not obtain a performance bond because the bonding companies would not write a bond for a project where another contractor had previously defaulted. The parties subsequently entered into a new arrangement under which American contracted with the CHA for completion of the project and with American entering into a separate contract to retain Stringer as the general contractor. The two contracts were signed on August 15, 1977. Stringer was paid the following day for work done prior to the June 15 stop order. Under its contract with American, Stringer agreed to

“complete all of the obligations of INDUSTRIAL MECHANICAL INC., in full accord with the specifications, not inconsistent herewith, for Project Ill. 2-71 (contract EP-991), the term specifications meaning, without limiting the generalization thereof, the general conditions, special conditions, and technical specifications and blueprints and drawings including all addenda thereto and change orders thereto, outlining such obligations, including all corrective and warranty work, for the sum of $992,517.00 pursuant to contractor’s proposal dated March 22,1977 as amended April, 1977.”

The contract stated further:

“In the event that CHA orders extra work to be performed subsequent to the date of this agreement Contractor shall be authorized to negotiate the price of such extra work directly with the CHA and shall accept in full payment for said extra work the amount paid by the CHA to American.”

Pursuant to provision GC.09 of the general conditions, Stringer also agreed:

“A. The Chicago Housing Authority may make changes in the work of the Contractor by making alterations therein, or by making additions thereto *** without invalidating the Contract. * * *
C. Except in an emergency endangering life or property, no change shall be made by the Contractor unless he has received a prior written order from the Chicago Housing Authority countersigned by the Architect and approved on its face by the HUD, authorizing the change, and no claim for an adjustment of the Contract Price or time shall be valid unless so ordered.”

On the same day that the two contracts were signed, the CHA’s executive director sent a letter to HUD requesting HUD’s approval for the same design change that HUD had previously rejected. Stringer testified that had he known that the CHA was still contemplating the congregate kitchen format, he never would have entered into the second contract with American.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Postula v. Blackard
2025 IL App (3d) 240464-U (Appellate Court of Illinois, 2025)
Callahan v. Wisdom
N.D. Illinois, 2020
Mandel v. Hernandez
936 N.E.2d 1079 (Appellate Court of Illinois, 2010)
Village of Wadsworth v. Kerton
Appellate Court of Illinois, 2000
Terry v. Metropolitan Pier & Exposition Authority
648 N.E.2d 1047 (Appellate Court of Illinois, 1995)
Bank of Chicago v. Park National Bank
640 N.E.2d 1288 (Appellate Court of Illinois, 1994)
Board of Trustees of Community College District No. 508 v. Rosewell
635 N.E.2d 413 (Appellate Court of Illinois, 1992)
Pry v. Alton & Southern Railway Co.
598 N.E.2d 484 (Appellate Court of Illinois, 1992)
Uhr v. Lutheran General Hospital
589 N.E.2d 723 (Appellate Court of Illinois, 1992)
Moore v. Roberts
577 N.E.2d 538 (Appellate Court of Illinois, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
563 N.E.2d 819, 206 Ill. App. 3d 250, 150 Ill. Dec. 692, 1990 Ill. App. LEXIS 1474, 1990 WL 139468, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stringer-construction-co-v-chicago-housing-authority-illappct-1990.