Stratton v. City of Detroit

224 N.W. 649, 246 Mich. 139, 1929 Mich. LEXIS 853
CourtMichigan Supreme Court
DecidedMarch 28, 1929
DocketDocket 163, Calendar 34,136
StatusPublished
Cited by8 cases

This text of 224 N.W. 649 (Stratton v. City of Detroit) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stratton v. City of Detroit, 224 N.W. 649, 246 Mich. 139, 1929 Mich. LEXIS 853 (Mich. 1929).

Opinion

North, C. J.

By a bond issue, the city of Detroit provided one million dollars to be expended in the erection of a municipal tuberculosis sanitarium in Wayne county. Three hundred thousand dollars of this amount was expended for the site, leaving *141 $700,000 for building purposes. This project was under the supervision of tbe Detroit board of health. After practically two years of preliminary consideration and investigation, the city of Detroit, acting through its board of health, on October 21, 1919, entered into a contract with the plaintiffs to render services as architects and in part to supervise the construction. The contract provided a group of buildings was to be constructed:

“For the housing of not to exceed 300' patients and the necessary service buildings, the total cost of which is not to exceed $700,000 including all architect’s fees. * * *
“It is hereby mutually agreed between the parties hereto that the board of health, shall pay the architect for service rendered hereunder as follows: The architect shall receive a commission of 3 per cent, on acceptance by the board of the plans and specifications, and 2 per cent, on the total amount of certificates issued to contractors for work completed each month.” (This 2 per cent, being for partial supervision.)

This contract was approved by the common council on November 18, 1919. The minutes of the meeting of the board of health, held December 16, 1919, contain the following:

“Dr. A. H. Garvin informed the board that the cost of the proposed tuberculosis sanitarium complete on an estimated cost basis of forty cents per cubic foot, using the present proposed building dimensions, would cost approximately $1,700,000. By reducing the plans and making use of basements, decreasing the width of the corridors and service portions, Dr. Garvin stated that the essential buildings could be built for approximately $745,000, the total cost without equipment to be a little over one *142 million dollars. The study of the revised plans were deferred to another time.”

Another meeting of the hoard was held December 23,1919, and the following appears in the record thereof:

“Commissioner Pope moved that the architects, Stratton and Snyder, be instructed to prepare plans for a complete sanitarium, as understood under the terms of the existing contract, but not including the clause containing the limiting the amount, $700,000, the plans to be so arranged as to allow the deduction of certain units, as decided upon by the board, to bring the cost of the proposed buildings within the amount appropriated, which motion prevailed.”

This proposed change in the contract was not approved by the common council, and so far as appears from the record it was not submitted to that body. The Detroit city charter, tit. 6, chap. 7, § 2, _ provides :

“Sec. 2. No contract shall be let or entered into for the construction of any public work, or for any work to be done, or for the purchasing or furnishing of supplies for said city not herein provided for, and no such public work, performance, purchasing or supplying shall be commenced until approved by the common council, and until the contract therefor has been duly approved and confirmed by the common council, and a tax or assessment levied to defray the cost and expense of the same, and no such work, supplies and materials shall be paid for or contracted to be paid for, except out of the proceeds of the tax or the assessment thus levied.”

Following the action taken by the board of health on December 23, 1919, the plaintiffs prepared plans and specifications which were used in erecting the municipal sanitarium, but at a cost of approximately $1,700,000. For supervising the construction the *143 plaintiffs were paid $33,231.23; and the defendants admit they are still indebted to the plaintiffs for supervision (on the basis of 2 per cent, of the cost) in the amount of $678.34. At the close of the proofs the defendants moved the court to enter judgment for the plaintiffs in that amount and accrued interest, totaling $879.02. On this phase of the case there is no controversy. The city has also paid the plaintiffs for plans and specifications 3 per cent, of the total cost of $700,000 specified in the contract of October 21, 1919. The plaintiffs claim the right to recover in this suit $31,909.90 as a balance due them for the plans and specifications, this being computed on the basis of 3 per cent, of the total cost of the buildings for which such plans and specifications were accepted by the board of health.

The plaintiffs’ declaration as originally framed planted the right to recover on the contract of October 21, 1919, and the action of the board of health taken on December 23, 1919. It was their claim that these constituted an express contract on which the defendants were liable. At the close of the proofs, and over defendants’ objection, plaintiffs were allowed to amend the declaration by declaring on an implied contract and adding the common counts. Each of the parties moved for a directed verdict. The trial court held that the plaintiffs had not established a right to recover upon an express contract; but he submitted to the jury the question of plaintiffs’ right to recover on a quantum meruit. The following is from the charge to the jury:

“I do not believe that the passage of the resolution by the board of health was sufficient, being an alteration or change of a material part of the contract, to make it legal and binding. A new contract, of course, should have' been entered into at that time by the plaintiffs and by the defendants. Well, *144 that was not done. If a brand new contract, which would have been the best way to have proceeded, was not entered into, it could have been done in this way, by resolution, but I believe that the resolution would have to be approved by the common council in order to change the original contract without entering into a new one, and that was not done. The limit also could not at that time be raised, because at that time the money was not available in excess of the $700,000 but the money was available, of course, and on hand to much more than cover the fees of the plaintiffs. * * *
“The city contends that the plaintiffs are limited in what they can recover to three per cent, of that original amount of $700,000, and they claim that they have been paid that. I am rather convinced that as far as an express contract is concerned, perhaps that is so, but no law has been cited to me which says that a city cannot be liable on a quantum meruit for services actually performed in the same way that an individual or company can be. So, what I am leaving to you in this case is this: What is a reasonable amount for services that were performed by the plaintiffs ?”

The plaintiffs had verdict and judgment for $42,183.56. The defendants are here by writ of error.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Doyle & Associates, Inc.
132 N.W.2d 99 (Michigan Supreme Court, 1965)
Standard Transformer Co. v. City of Detroit
146 F. Supp. 740 (E.D. Michigan, 1956)
Ely v. City of Detroit
10 N.W.2d 892 (Michigan Supreme Court, 1943)
Knights of Iron Horse v. City of Detroit
2 N.W.2d 466 (Michigan Supreme Court, 1942)
Utica State Savings Bank v. Village of Oak Park
273 N.W. 271 (Michigan Supreme Court, 1937)
City of Pontiac v. Ducharme
270 N.W. 754 (Michigan Supreme Court, 1936)
Barlum Realty Co. v. Heggblom
262 N.W. 647 (Michigan Supreme Court, 1935)
A. J. Smith Construction Co. v. City of Marine City
255 N.W. 209 (Michigan Supreme Court, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
224 N.W. 649, 246 Mich. 139, 1929 Mich. LEXIS 853, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stratton-v-city-of-detroit-mich-1929.