STR Constructors Ltd. and Arch Insurance Company v. Newman Tile, Inc.

CourtCourt of Appeals of Texas
DecidedFebruary 20, 2013
Docket08-10-00210-CV
StatusPublished

This text of STR Constructors Ltd. and Arch Insurance Company v. Newman Tile, Inc. (STR Constructors Ltd. and Arch Insurance Company v. Newman Tile, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
STR Constructors Ltd. and Arch Insurance Company v. Newman Tile, Inc., (Tex. Ct. App. 2013).

Opinion

COURT OF APPEALS

EIGHTH DISTRICT OF TEXAS

EL PASO, TEXAS

STR CONSTRUCTORS, LTD. and ARCH INSURANCE COMPANY,

                            Appellants,

v.

NEWMAN TILE, INC.,

                            Appellee.

§

No. 08-10-00210-CV

Appeal from the

225th District Court

of Bexar County, Texas

(TC# 2005-CI-04950)

O P I N I O N

In this breach-of-contract action between STR Constructors, Ltd. (STR), a general contractor, and Newman Tile, Inc. (NTI), a subcontractor, the trial court rendered judgment for NTI and against STR and its insurer, Arch Insurance Co (Arch).  In six issues, STR and Arch appeal from the trial court’s judgment, contending that the evidence is legally insufficient to support the jury’s findings that STR breached the contract and breached it first and to support the jury’s award of damages, quantum meruit, and attorney’s fees.[1]  Because we conclude that the evidence is legally sufficient, we affirm.

FACTUAL AND PROCEDURAL BACKGROUND

            STR was hired by the Northeast Independent School District (the district) to renovate one of its middle schools.  One of the spaces to be renovated was the school’s kitchen.[2]  As the general contractor, STR solicited bids for the installation of tile in the kitchen.  After reviewing the architectural plans and the specifications book, NTI tendered its bid.  As the low bidder, NTI was awarded the contract.

            Problems arose between STR and NTI during the renovation of the school.  According to Harold B. Newman, owner and president of NTI, “[t]he project was . . . far behind” at the time NTI was scheduled to begin installing tile in the kitchen.  In Newman’s mind, the project was behind because STR failed not only to adhere to the schedule it had created, but also to design the schedule properly in the first place.  On the other hand, STR blamed the delays on NTI’s failure to supply a workforce adequate and skilled enough to install the tile properly and in a timely manner.

            Tensions escalated when an issue surfaced concerning epoxy grout.  STR maintained that epoxy grout was required to install the quarry tile in the kitchen and that the specification book made this clear.  Newman disputed STR’s contention and insisted that NTI’s bid excluded epoxy grout.  STR ordered NTI to use epoxy grout.  Under protest, NTI ordered the epoxy grout and used it to install the quarry tile in the kitchen.  Claiming that the epoxy grout and the labor necessary to install it were not within the scope of the contract, NTI submitted a change order to STR seeking reimbursement.  STR never paid the change orders related to the epoxy grout nor did it pay change orders for work performed by NTI alleged to have been outside the scope of the contract.

            As a courtesy, the district scheduled a walk-through of the kitchen.  At the inspection, district officials informed Newman and representatives from STR that the kitchen, including its tile work, would not be accepted.  In response, STR ordered NTI to make the necessary repairs, and to do so quickly.  Becoming increasingly dissatisfied with one another’s expectations, the parties wrote each other several letters outlining their respective positions.  The correspondence between the parties reveal that STR was growing increasingly dissatisfied with the work, or lack thereof, performed by NTI, so much so that one week after the inspection, STR informed NTI that STR was terminating the contract.  NTI then sued for breach of contract and quantum meruit, alleging that STR’s mismanagement made it impossible for NTI to perform on the contract.

BREACH AND FIRST TO BREACH

            In its first and second issues, STR argues that the evidence is legally insufficient to support the jury’s findings that STR breached the contract and that STR breached the contract first.  We disagree.

Standard of Review

            To determine whether the evidence is legally sufficient to support the jury’s findings, we review the entire record, crediting favorable evidence if reasonable jurors could and disregarding contrary evidence unless reasonable jurors could not.  City of Keller v. Wilson, 168 S.W.3d 802, 827 (Tex. 2005).  If more than a “scintilla of evidence” exists to support the jury’s findings, it is legally sufficient.  Id. at 822.  More than a “scintilla of evidence” exists when the evidence supporting the finding, as a whole, would enable reasonable and fair-minded people to differ in their conclusions.  Id.  As the sole judge of the weight and credibility of the evidence, the jury is entitled to resolve any conflicts in the evidence and to choose which testimony to believe.  Id. at 819.  We therefore assume that jurors decided questions of credibility or conflicting evidence in favor of the verdict if they reasonably could do so.  Id. at 819, 820.  Accordingly, we do not substitute our judgment for that of the jurors if the evidence falls within this zone of reasonable disagreement.  City of Keller, 168 S.W.3d at 822.

Applicable Law

            A party breaches a contract when he fails to perform an act that he has expressly or impliedly promised to perform.  Examination Mgmt. Svcs., Inc. v. Kersh Risk Mgmt., Inc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Truly v. Austin
744 S.W.2d 934 (Texas Supreme Court, 1988)
Dobbins v. Redden
785 S.W.2d 377 (Texas Supreme Court, 1990)
MBM Financial Corp. v. Woodlands Operating Co.
292 S.W.3d 660 (Texas Supreme Court, 2009)
Tips v. Hartland Developers, Inc.
961 S.W.2d 618 (Court of Appeals of Texas, 1998)
Tenneco Inc. v. Enterprise Products Co.
925 S.W.2d 640 (Texas Supreme Court, 1996)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Sun Exploration and Production Co. v. Benton
728 S.W.2d 35 (Texas Supreme Court, 1987)
Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)
Examination Management Services, Inc. v. Kersh Risk Management, Inc.
367 S.W.3d 835 (Court of Appeals of Texas, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
STR Constructors Ltd. and Arch Insurance Company v. Newman Tile, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/str-constructors-ltd-and-arch-insurance-company-v--texapp-2013.