Stover v. City of Springfield

152 S.W. 122, 167 Mo. App. 328, 1912 Mo. App. LEXIS 647
CourtMissouri Court of Appeals
DecidedDecember 2, 1912
StatusPublished
Cited by7 cases

This text of 152 S.W. 122 (Stover v. City of Springfield) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stover v. City of Springfield, 152 S.W. 122, 167 Mo. App. 328, 1912 Mo. App. LEXIS 647 (Mo. Ct. App. 1912).

Opinion

COX, J.

Action by certain property owners to cancel special taxbills issued to defendant Plummer as contractor in payment for the construction of a district sewer in the city of Springfield. The defendants in their answer alleged compliance with the law and ordinances of the city and asked for a foreclosure of the lien of the taxbills issued against the property of the plaintiffs. The trial court found for the defendants except that he reduced the amount of each bill [335]*335ten per cent and then ordered foreclosure for the .remainder of the taxbills. Plaintiffs have appealed.

The questions upon which plaintiffs rely for a reversal of the judgment are:

First: That the contract for putting in the sewer was let at a price in excess of the preliminary estimate of the city engineer.

Second: That material changes were made in the construction of the sewer after the contract was let., by the addition of laterals not called for in the contract and by omitting other parts that were called for in the contract.

Third: That there was a change of grade after the contract was made.

Fourth: That there was a double charge for excavating by charging for both dirt and rock in the same part of the ditch.

Fifth: That the court erred in excluding certain testimony offered by the plaintiffs.

As to the first point, we do not think the contention is sustained by the testimony. The estimate of the engineer itemized the work and the cost. He estimated that it would require 1705 lineal feet of eight inch pipe including Ys, branches and joints, two lamp holes, two flush tanks, four manholes, etc. The excavation was classified and a separate estimate put upon all excavations including back filling; six feet and under eight feet being in one class; eight feet and under ten feet in another; ten feet and under twelve feet in another; twelve feet and under fourteen feet in another; fourteen feet and under sixteen feet in another; sixteen feet and under eighteen feet in another; and on each of these a separate estimate was made. There was an estimate of 2800 lineal feet for a rock trench and 3400 lineal feet of flint excavation. These with some other items all of which were specified made a total of $3189.15. The contract also specified same items and was at a less price for each item than the estimate of the engi[336]*336neer. There was also a provision in the contract that extra work should be done according to the engineer’s estimate and if this made an increase in the amount of work, it should be paid for according to the quantity actually’ done and at the price stipulated in' the contract. ' •

The basis for the contention that the contract price exceeded the estimate of the engineer is not based upon the fact that the contract was let at a higher price on any item of the contract but is based upon the fact that after the work was completed and the work actually done was computed that by the addition of laterals, the length of the ditch was increased and also that the amount of flint excavation was increased over the estimate; and that being true, the total cost, instead of being as estimated $3189.15, amounted to $4247.35.

In the very nature of things it was impossible for the, engineer to ascertain before the ditch was actually dug how much flint and how much rock would be encountered in excavating the ditch, and for that réason, the parties could not understand that his estimate as to thé total cost should control over the estimate as’ per the items making up the total expenditure and as the contract was let at a price below the estimate on each item and, all the items going to make up the total having been specified, it would certainly be unreasonable to hold that because the engineer underestimated the amount of rock and flint to be found under the ground that the contractor could not recover for the work actually done. We are cited by appellants’ counsel to the case of G-ratz v. City of Kirkwood,. 165 Mo. App. 196, 145 S. W. 874, decided by the St. Louis Court of Appeals as authority for the- position that the contract or the total: amount of the taxbills could not exceed themstimate of the engineer as to the .total cost of the construction óf the: sewer, but a careful examination of that, case will show‘that instead, of; being an authority for that position, it is authority for. the position that the [337]*337estimate- of the total-cost does not control over the items when the items are specified and onr holding in this case that the evidence does not show the contract to be in excess of the estimate is in harmony with the Gfratz ease. ,

The second contention is that material changes were made after the contract was let, by shortening one of the ditches called for in the contract and by adding laterals at other places not called for in the contract. The evidence shows that this was done and that by doing so, the total length of the ditches dug and pipes laid was greater than that stated in the engineer’s preliminary estimate. But we do not think under the evidence in this case that these changes were fatal to the validity of the taxbills. It is the duty of the city in constructing any district sewer to place it in such a way that it will accommodate the property owners of the district. In this case,, an abstract of title was procured for the purpose of determining who the owners were and size of the lots and their location in order that the sewer might be so placed as to meet the demand for service from all the lots. It developed that some mistakes had been made in the abstracts and that when they went to do the work it became necessary to add some laterals in order to reach some parts of the district and it also was found unnecessary to dig one of the. ditches the full length estimated by the engineer. The addition of the laterals was necessary in order to furnish proper, drainage for the entire district and one ditch was shortened because it was found to be unnecessary to dig it as long as estimated and since the basis of this contract was the items of work, we think it was entirely right and proper for these changes to have been made and was in fact the duty of the city to make them so that the district could be properly accommodated and without unnecessary cost.

[338]*338It also appears that there were some changes in the grade of the main pipe and it is now contended that this vitiated the contract and taxbills. The evidence shows that this change lessened the cost without in any way impairing the service to be gendered the residents. These property owners, therefore, were benefited by the change rather than injured and since it did not increase but lessened the amount of the contract, it was not fatal and they cannot complain.

•It is next contended that plaintiffs offered to show that one lot about 50 by 100 feet lying within the district had been omitted in computing the area of the district and that bv reason thereof, the cost to these plaintiffs had been increased to that extent. When this offer was made the court excluded it upon objection of defendant. Afterward, however,'the same testimony was admitted without objection and it was further shown that certain other territory not lying in the district was included in computing the area so that the area as computed was not less than the actual area and the charge against the plaintiffs’ property was not thereby increased.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Missouri Service Co. v. City of Stanberry
108 S.W.2d 25 (Supreme Court of Missouri, 1937)
Pope v. Rich
293 S.W. 373 (Supreme Court of Missouri, 1927)
City of Washington Ex Rel. Bihr v. Mueller
287 S.W. 856 (Missouri Court of Appeals, 1926)
Williams v. Hybskmann
278 S.W. 377 (Supreme Court of Missouri, 1925)
Alsmeier v. Adams
105 N.E. 1033 (Indiana Court of Appeals, 1914)
City of Maryville v. Cox
167 S.W. 1166 (Missouri Court of Appeals, 1914)
Meyers v. Wood
158 S.W. 909 (Missouri Court of Appeals, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
152 S.W. 122, 167 Mo. App. 328, 1912 Mo. App. LEXIS 647, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stover-v-city-of-springfield-moctapp-1912.