Pope v. Rich

293 S.W. 373, 316 Mo. 1206, 1927 Mo. LEXIS 700
CourtSupreme Court of Missouri
DecidedApril 11, 1927
StatusPublished
Cited by4 cases

This text of 293 S.W. 373 (Pope v. Rich) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pope v. Rich, 293 S.W. 373, 316 Mo. 1206, 1927 Mo. LEXIS 700 (Mo. 1927).

Opinion

*1209 RAGLAND, J.

This case comes to the writer for opinion on reassignment. It is a suit to enforce the lien of a special tax bill for a street improvement. In the trial court plaintiff was awarded judgment for a less sum than that called for by the tax bill; both parties appealed. The Kansas City Court of Appeals, where the appeals were lodged, deeming the conclusions reached by it to be in conflict with Stover v. City of Springfield, 167 Mo. App. 328, certified the cause to this court.

The tax bill was issued by the City of Jefferson April 10, 1916. It recited among other things: that it was issued for work done and material furnished by plaintiff, as contractor, in grading, curbing, guttering and asphalt macadamizing that portion of Marshall Street which lies between Main and Water Streets in said city; that the total cost of such improvement was $5,553.53; that the aggregate number of front feet contained in the aggregate lots or pieces of ground abutting said improved street was 795 lineal feet; that the lot owned by defendant had an aggregate frontage of 198 feet and 9 inches; and that the proportionate part of the total cost of the improvement levied and assessed against said lot was $1,388.48.

The city engineer’s estimate of the total cost of the improvement according to specified unit prices was $3,978.15. The plaintiff’s proposal or bid for the work on the basis of unit prices aggregated $3,799,50. The total cost of the work when completed, according to the unit prices designated in the proposal, was $5,553.53, and that amount was made the basis of the tax bill. The circuit court gave plaintiff judgment for the amount of his bid, with interest. As the principal question arising on the record is whether the contract for the improvement was made for a price exceeding the engineer’s estimate, a statement in detail with respect to the estimate, the proposal and the contract is necessary.

*1210 The engineer’s estimate was as follows:

1200 Cu. Yds. Earth Excavation at $0.35 420.00
3000 Cu. Yds. Earth Excavation borrow at $0.35 1050.00
3000 Overhaul 3000 yds. 2000 feet at $0,015 900.00
955 Sq. Yds. Asphalt Macadam at $0.93 888.15
900 Lin. Feet Curb’ at $0.40 360.00
900 Lin. Feet Gutter at $0.40 360.00
$3978.15

The proposal was “to furnish all appliances, materials and labor, and do all the work necessary for the improvement of — Marshall— Street between — Main—'Street and "Water — Street, in accordance with the plans, specifications and ordinances for said work, ’ ’ for the following prices to-wit:

Quantity * Classification Price Amount
1200 Cu. Yds. Earth Excavation at $0.35 420.00
3000 Cu. Yds. Earth Excavation borrow at $0.35 1050.00
3000 Cu. Yds. Earth overhaul 2000 overhaul — per cu. yd. hauled 100 feet at $0.01% 750.00
955 Sq. Yds. Asphalt Macadam at $0.90 859.50
900 Lin. Feet Curb at $0.40 360.00
900 Lin. Feet Gutter at $0.40 360.00
Borrowed earth shall be paid for by the Street if - there should be any charges
Total $3799.50

The contract, omitting formal recitals, provided as follows:

“Now therefore, for and in consideration of the awarding of this contract, and work thereunder by said first party hereto, the City of Jefferson, to the second party, said Joseph Pope — he does hereby contract and agree to do and perform said work, above specified and referred to for the following prices and to accept in payment therefor, special tax-bills to be issued by the said City of Jefferson, against the abutting real estate, upon the acceptance of said work by the Council of the City of Jefferson:
Earth excavation per cubic yard x35 cents.
Earth excavation per cubic yard borrow x35 cents.
Cub. yd. earth overhaul 100 feet per cub. yd. x01% cents.
Apphalt macadam per square yard x90 cents.
Curb per foot x40 cents.
Gutter per foot x40 cents.
Borrowed earth shall be paid for by the street if there be any charge.
“Now, by these presents it is agreed to and understood by the parties hereto, that this contract is entered into subject to all existing ordinances of the city, and charter thereof, pertaining to the work *1211 awarded and subject to the plans and specifications and estimate of cost for such work on file in the office of the city clerk, and which shall be considered a part and parcel of this contract.”

The excess of the actual cost of the work over the estimate is explained' by the following note appended to the city engineer’s report:

“Note: The earth as shown in the estimate was not available when the street was constructed, and the earth entering into the cost was necessarily hauled from a long distance practically entirely. . . .
‘ ‘ The contract provided for a certain price on each item, and as the quantity of material used was above the estimate, and as it was necessary to haul the earth a considerably longer distance than was provided in the estimate owing to the fact that the earth shown in the estimate was not available when the street was constructed, thereby increasing the length of the haul, the cost of the work was considerable increased.”

I. The City of Jefferson is a city of the third class. Section 8324, Revised Statutes 1919, relating to the power of cities of that class to improve streets and the method of paying the cost of such improvements, provides: “But before the city shall make any contract for any of said improvements, excepting repairs, an estimate of the cost thereof shall be made by the city engineer. . . . Such estimate shall be filed with the city clerk and no contract shall be made for a price exceeding such estimate.” It is plaintiff’s position that his contract with the city was an open one so far as quantities were concerned; that only the prices per unit were fixed; and that, as such prices did not in any respect exceed the estimates, the contract was not obnoxious to the statutory provision just quoted. This latter proposition has been ruled adversely to plaintiff’s contention. In the recent case of Williams v. Hybskmann, 278 S. W. 377, this court had occasion to construe Section 8506, Revised Statutes 1919, found in the article relating to the government of cities of the fourth class. The language of that section is almost identical with that of the part of Section 8324 above quoted. In construing it we held:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harry H. Houf & Sons, Contractors, Inc. v. City of Wellsville
796 S.W.2d 435 (Missouri Court of Appeals, 1990)
Voogd v. JOINT DRAIN. DIST., KOSSUTH & WINNEBAGO COS.
188 N.W.2d 387 (Supreme Court of Iowa, 1971)
State Ex Rel. Melrose Sewer District v. Smith
120 S.W.2d 1102 (Supreme Court of Missouri, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
293 S.W. 373, 316 Mo. 1206, 1927 Mo. LEXIS 700, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pope-v-rich-mo-1927.