Stormwater Plans LLC v. Cincinnati Insurance Company

CourtDistrict Court, D. Arizona
DecidedOctober 6, 2023
Docket2:23-cv-01184
StatusUnknown

This text of Stormwater Plans LLC v. Cincinnati Insurance Company (Stormwater Plans LLC v. Cincinnati Insurance Company) is published on Counsel Stack Legal Research, covering District Court, D. Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stormwater Plans LLC v. Cincinnati Insurance Company, (D. Ariz. 2023).

Opinion

1 WO 2 3 4 5 6 IN THE UNITED STATES DISTRICT COURT 7 FOR THE DISTRICT OF ARIZONA

9 Stormwater Plans LLC, No. CV-23-01184-PHX-ROS

10 Plaintiff, ORDER

11 v.

12 Cincinnati Insurance Company, et al.,

13 Defendants. 14 15 Defendant Arrow Indian Contractors agreed to be the general contractor on a 16 project for the United States Federal Highway Administration. Plaintiff Stormwater 17 Plans, LLC, (“SWP”) executed a subcontract with Arrow to perform work on that project. 18 SWP performed the work, but Arrow has not paid SWP. After Arrow and SWP had 19 some informal discussions, SWP filed this suit seeking payment. Arrow then filed a 20 motion to stay, arguing the subcontract prevents SWP from pursuing litigation now or in 21 the future. Arrow has not carried its burden of establishing a stay is appropriate. 22 BACKGROUND 23 In 2021, Arrow contracted with the United States Federal Highway Administration 24 (“FHA”) as the general contractor for a road project. Arrow obtained the required Miller 25 Act Payment bond from Cincinnati Insurance Company.1 Arrow then executed a

26 1 “The Miller Act requires a general contractor on a federal construction project to furnish ‘[a] payment bond . . . for the protection of all persons supplying labor and material in the 27 prosecution of the work provided for in [the] contract.’” Mai Steel Serv., Inc. v. Blake Const. Co., 981 F.2d 414, 416 (9th Cir. 1992) (quoting 40 U.S.C. § 270a(a)(2)). Under 28 the Miller Act, a subcontractor may sue both a general contractor and its surety. See, e.g., U.S. for Use & Benefit of Owens v. Olympic Marine Servs., Inc., 827 F. Supp. 1232, 1234 1 subcontract with SWP for SWP to perform excavation and grading work on the project. 2 The subcontract between Arrow and SWP contains a section titled “Claims and 3 Disputes” establishing how the parties would resolve any disagreements. That section 4 requires that if there is a dispute between Arrow and SWP, and that dispute is connected 5 to an ongoing dispute between Arrow and FHA, any litigation between Arrow and SWP 6 must be stayed until resolution of the Arrow/FHA dispute. In addition, if there is a 7 dispute between SWP and Arrow that is not connected to an ongoing Arrow/FHA 8 dispute, SWP and Arrow must first “endeavor to settle the dispute through direct 9 discussion.” If that discussion fails, Arrow can demand mediation. And if mediation 10 fails, Arrow and SWP must pursue arbitration or litigation. As discussed later, the 11 subcontract identifies arbitration and litigation as mutually exclusive options, but it does 12 not state which option applies. 13 After executing the subcontract, SWP allegedly “performed and completed all 14 [required] work.” (Doc. 1 at 2). In early October 2022, “SWP sent Arrow a demand for 15 payment of $742,093.” (Doc. 28 at 2). SWP also demanded payment of $66,435 “for 16 work under the subcontract . . . that is unrelated to Arrow receiving payment from the 17 FHA.” (Doc. 28 at 2). Arrow did not pay either amount. SWP then sent Cincinnati 18 Insurance Co. (“CIC”) a “notice of claim” stating Arrow had refused to pay and SWP 19 expected payment from CIC. Like Arrow, CIC refused to pay. 20 On March 30, 2023, SWP sent Arrow a proposed resolution that would require 21 Arrow make “installment payments” of the owed amounts. (Doc. 28 at 44). Arrow did 22 not respond. On April 19, 2023, SWP sent a follow-up communication stating it had not 23 “heard anything back from [Arrow] regarding [SWP’s] proposed settlement and payment 24 [offer].” The April communication noted “[u]nfortunately, the time to file suite [sic] is 25 coming up” and SWP would “be filing suit and start the collection process.” (Doc. 28 at 26

27 (E.D. Va. 1993) (noting subcontractor may sue surety and general contractor). Arrow and Cincinnati Insurance Company are represented by the same counsel, and both seek a 28 stay. For purposes of this Order, the Court will not differentiate between the two defendants. 1 47). Arrow did not respond. On June 26, 2023, SWP filed this suit. 2 Arrow was served but, instead of answering, filed a motion to stay. That motion 3 argues the FHA has failed to pay Arrow for all the work performed on the project, 4 including the work performed by SWP. Arrow states it “is still petitioning the [FHA] for 5 payment” and has a meeting with FHA personnel on an undisclosed date “to discuss and 6 potentially overcome obstacles to payment.” (Doc. 24 at 3). Arrow’s motion argues the 7 ongoing discussions between Arrow and FHA trigger the provision of the subcontract 8 that requires a stay of any proceedings to resolve disputes between Arrow and SWP. 9 Arrow also points to the subcontract’s provision requiring mediation and argues this case 10 cannot proceed because mediation has not yet occurred. Finally, Arrow argues SWP 11 cannot pursue its claims in litigation because the subcontract requires all disputes be 12 resolved via arbitration. 13 ANALYSIS 14 The parties disagree on the appropriate framework for evaluating Arrow’s motion 15 to stay. Neither party’s framework appears correct. Arrow argues a stay is appropriate 16 because SWP’s claims are not yet “ripe.” According to Arrow, there are certain events 17 that must occur before any litigation may proceed. (Doc. 24 at 3). Thus, Arrow asks for 18 a stay until those events occur. However, when claims are not “ripe,” the usual course is 19 to dismiss the claims, not issue a stay. Addington v. U.S. Airline Pilots Ass’n, 606 F.3d 20 1174, 1179 (9th Cir. 2010) (“If the claim before us is not ripe, we must dismiss.”). 21 As for SWP, it invokes the standard applicable for a party seeking to stay a 22 judgment pending appeal. Nken v. Holder, 556 U.S. 418, 421 (2009). That standard is 23 “similar to that employed by district courts in deciding whether to grant a preliminary 24 injunction.” Feldman v. Arizona Sec’y of State's Off., 843 F.3d 366, 367 (9th Cir. 2016). 25 But Arrow is not seeking a stay pending appeal nor is Arrow seeking an injunction to 26 prevent other ongoing proceedings. Thus, SWP’s proposed standard appears 27 inapplicable. 28 Because neither party has identified the standard that should be applied to the 1 motion to stay, the Court must determine the appropriate standard on its own. There are 2 two likely possibilities. First, Arrow’s assertion that a stay should be granted pending 3 resolution of other proceedings may be a request for a stay under the Court’s inherent 4 power. Second, Arrow’s argument that SWP must arbitrate its claims appears to be a 5 request for a stay under the Federal Arbitration Act (“FAA”). Arrow makes two 6 arguments for a stay that fall under the Court’s inherent power and one argument under 7 the FAA. 8 I. “Dispute Resolution Proceeding” 9 Courts have the inherent power to stay cases. See Landis v. North American Co., 10 299 U.S. 248, 254 (1936). This inherent power is often the basis for a stay “pending 11 resolution of independent proceedings which bear upon the case.” Leyva v. Certified 12 Grocers of California, Ltd., 593 F.2d 857, 863 (9th Cir. 1979).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Landis v. North American Co.
299 U.S. 248 (Supreme Court, 1936)
Dean Witter Reynolds Inc. v. Byrd
470 U.S. 213 (Supreme Court, 1985)
Nken v. Holder
556 U.S. 418 (Supreme Court, 2009)
Grosvenor Holdings, L.C. v. Figueroa
218 P.3d 1045 (Court of Appeals of Arizona, 2009)
Lockyer v. Mirant Corp.
398 F.3d 1098 (Ninth Circuit, 2005)
Leslie Feldman v. Arizona Sec'y of State's Ofc.
843 F.3d 366 (Ninth Circuit, 2016)
Kevin Johnson v. Walmart Inc.
57 F.4th 677 (Ninth Circuit, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
Stormwater Plans LLC v. Cincinnati Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stormwater-plans-llc-v-cincinnati-insurance-company-azd-2023.