Stonehenge Engineering Corp. v. Employers Insurance of Wausau

201 F.3d 296, 2000 U.S. App. LEXIS 426, 2000 WL 20895
CourtCourt of Appeals for the Fourth Circuit
DecidedJanuary 13, 2000
Docket98-2673, 98-2680
StatusPublished
Cited by22 cases

This text of 201 F.3d 296 (Stonehenge Engineering Corp. v. Employers Insurance of Wausau) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stonehenge Engineering Corp. v. Employers Insurance of Wausau, 201 F.3d 296, 2000 U.S. App. LEXIS 426, 2000 WL 20895 (4th Cir. 2000).

Opinions

Affirmed in part, vacated in part, and remanded by published opinion. Senior Judge HAMILTON wrote the opinion, in which Judge GOODWIN joined. Judge TRAXLER wrote a separate opinion concurring in part and dissenting in part.

OPINION

HAMILTON, Senior Circuit Judge:

Two corporately related general contractors, Stonehenge Engineering Corporation and National Stonehenge Corporation (collectively Stonehenge) brought this diversity action against Employers Insurance of Wausau (Wausau) seeking indemnification, under three successive standard commercial general liability policies issued by Wausau to Stonehenge, for an amount Stonehenge agreed to pay to settle a lawsuit against it alleging defective construction of condominium units. In its complaint, Stonehenge also alleged two bad faith claims against Wausau, one asserting bad faith refusal to indemnify and defend, the other alleging bad faith refusal to settle.

The district court granted Stonehenge’s motion for summary judgment on its breach of contract claim, i.e., its indemnification claim, and granted Wausau’s motion for summary judgment on Stonehenge’s two bad faith claims. On appeal, Wausau challenges the district court’s grant of Stonehenge’s motion for summary judgment on the breach of contract claim. Stonehenge cross appeals the district court’s grant of Wausau’s motion for summary [298]*298judgment on the two bad faith claims. Stonehenge also assigns error to the district court’s refusal to award it interest for the period of time between the settlement of the underlying lawsuit and the date of the entry of judgment on its breach of contract claim.

We affirm the district court in all respects, except we vacate the damage portion of the judgment in favor of Stonehenge and remand for entry of judgment in a specified lesser amount.

I.

During the early to mid-1980s, Stonehenge constructed Phase III of a condominium project known as “Yacht Cove” in Lexington County, South Carolina on the shores of Lake Murray. Phase III consisted of nineteen buildings, totaling 130 residential units. Thirty-two of the units were known as “villa” units, while the remaining ninety-eight units were known as “townhouse” units. Stonehenge completed construction of Phase III in March 1987.

In approximately 1989, the owners of residential units constructed in Phase III began experiencing problems with Phase III buildings. For example, the owners noticed buckled siding, cracks in foundations, and sagging balconies. As a result, the Yacht Cove Owners Association (the Owners Association) hired G. Allen Moore (Moore), a private building inspector, to inspect the buildings at issue and prepare a report. On March 19, 1990, Moore submitted his report (the Moore Report) to the Owners Association. The Moore Report identified defects in the balconies, roofs, foundations, basement walls, porches, decks, handrails, pickets, stairs, siding, and flashing of Phase III buildings. In the fall of 1996, Moore also identified defects in the subflooring of Phase III buildings.

The Owners Association subsequently sent a copy of the Moore Report to the developer of Yacht Cove, Equitable Real Estate Investment Management, Inc., which in turn sent a copy to Stonehenge on September 25, 1990. Stonehenge investigated the alleged defects identified in the Moore Report and responded in writing to the report on November 12, 1990. In its response, Stonehenge completely denied responsibility for the alleged defects on the basis that it constructed Phase III in accordance with the building code in effect for Lexington County at the time of construction, and on the basis that the damage identified in the Moore Report resulted from lack of proper owner maintenance and/or owner alteration of certain portions of Phase III buildings. Stonehenge admitted the existence of a “riser” code violation on the front of a particular Phase III building, but attributed its existence to settlement of the right corner of the adjacent sidewalk.

On April 16, 1992, the Owners Association notified Stonehenge by letter that if a representative of Stonehenge did not contact its attorney within ten days, it would assume that Stonehenge did not intend to voluntarily address the defects identified in the Moore Report, thus requiring it to take legal action against Stonehenge. The record does not disclose whether Stonehenge responded to this letter, but shortly after receiving it, Stonehenge notified Maryland Casualty Insurance Company (Maryland Casualty) of the Owners Association’s claims. Maryland Casualty insured Stonehenge under a commercial general liability policy from July 1,1986 to November 1, 1987. Of relevance to this appeal, several other general liability insurance carriers successively insured Stonehenge under commercial general liability policies from November 1, 1987 until November 1, 1995. Aetna Casualty and Surety Company (Aetna) insured Stonehenge from November 1, 1987 to November 1, 1991. Home Insurance Company (Home) insured Stonehenge from November 1,1991 to November 1, 1992. Finally, Wausau insured Stonehenge under three annual standard commercial general liability policies for the [299]*299time period November 1, 1992 to November 1, 1995 (the Three Wausau Policies).1

After receiving notice of the Owners Association’s claims against Stonehenge, Maryland Casualty investigated Phase III buildings under a reservation of rights and requested additional information from Stonehenge. Maryland Casualty conducted an on-site investigation that revealed, inter alia, some problems with the lightweight concrete floors in two villa units, primarily in the kitchen area underneath the vinyl flooring.2 On September 29, 1992, Stonehenge submitted an extensive written response to a request by Maryland Casualty for more information. In its response, Stonehenge stated that its first notice of any problems with Phase III buildings was its receipt of the Moore Report in September 1990.

Stonehenge notified Aetna of the Owners Association’s claims on October 21, 1992. Like Maryland Casualty, Aetna investigated the claims under a reservation of rights.

On April 6,1993, the Owners Association filed suit against Stonehenge in the Court of Common Pleas for Lexington County, South Carolina. The suit alleged that in constructing Phase III buildings, Stonehenge was negligent and breached its implied warranty to perform work in a careful, diligent, and workmanlike manner. The Owners Association sought 1.27 million dollars in damages, with the bulk of this figure constituting the amount the Owners Association believed would be necessary to reside the exterior of every building in Phase III and replace the lightweight concrete floors in every villa unit.

By March 1996, the Owners Association could ill afford to pay the ongoing fees generated by its attorneys, who had taken the case on an hourly-rate basis, rather than on a contingency-fee basis. As a result, the Owners Association offered to settle its suit against Stonehenge for $400,-000 with a “drop dead” date to accept the offer by April 11, 1996. Stonehenge refused the settlement offer.

Wausau did not receive notice of the Owners Association’s suit against Stonehenge or its presuit claims until late March 1996, just after Stonehenge received the settlement offer.3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New Hampshire Insurance Compan v. William Carleton, II
502 F. App'x 478 (Sixth Circuit, 2012)
Pocisk v. SEA COAST CONSTRUCTION OF BEAUFORT
671 S.E.2d 98 (Court of Appeals of South Carolina, 2008)
Buckeye Ranch, Inc. v. Northfield Insurance Co.
2005 Ohio 5316 (Court of Common Pleas of Ohio, Franklin County, Civil Division, 2005)
State v. Hydrite Chemical Co.
2005 WI App 60 (Court of Appeals of Wisconsin, 2005)
Mendez v. Dollar Tree Stores Inc.
114 F. App'x 149 (Fifth Circuit, 2004)
Auto-Owners Ins. Co., Inc. v. Zurich US
377 F. Supp. 2d 496 (D. South Carolina, 2004)
Great American Insurance v. Calli Homes, Inc.
236 F. Supp. 2d 693 (S.D. Texas, 2002)
Stolting v. Jolly Roger Amusement Park, Inc.
37 F. App'x 80 (Fourth Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
201 F.3d 296, 2000 U.S. App. LEXIS 426, 2000 WL 20895, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stonehenge-engineering-corp-v-employers-insurance-of-wausau-ca4-2000.