Stinson, Lyons, Gerlin & Bustamante, P.A. v. Brickell Building 1 Holding Co.

923 F.2d 810
CourtCourt of Appeals for the Eleventh Circuit
DecidedFebruary 8, 1991
DocketNo. 90-5873
StatusPublished
Cited by1 cases

This text of 923 F.2d 810 (Stinson, Lyons, Gerlin & Bustamante, P.A. v. Brickell Building 1 Holding Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stinson, Lyons, Gerlin & Bustamante, P.A. v. Brickell Building 1 Holding Co., 923 F.2d 810 (11th Cir. 1991).

Opinion

JOHNSON, Circuit Judge:

This case arises on an expedited appeal of the district court’s finding that the plaintiff Stinson, Lyons, Gerlin & Bustamante (“the Tenant”) had not been constructively evicted from its leasehold by its landlord.

I. STATEMENT OF THE CASE

A. Background Facts

The Tenant is a general practice law firm with sixteen attorneys and approximately fifty-five total employees. Its offices are located in a fourteen-story professional office tower at 1401 Brickell Avenue in Miami, Florida. In March of 1973, the tenant entered into the Lease at issue for a period of ten years. The Lease granted the Tenant two successive five-year options to renew. On June 1, 1988, the Tenant exercised its final option, renewing the Lease until May 31, 1993. At the time the Tenant exercised this option, it had leased all of the ninth floor and part of the eighth floor.1

When the Lease was originally negotiated, the building provided its tenants with first-class amenities in a prestigious location. In the ensuing eighteen years, however, the building and its support systems gradually deteriorated. Because of advances in technology and revisions in the applicable codes, the building did not contain the state-of-the-art health, safety, and amenity features offered by newer buildings in the area. The Landlord found itself losing tenants to competitors. At the time of the trial, the building contained only four tenants and only twenty percent of its space was occupied. Faced with this situation, the Landlord decided to renovate the building and upgrade both its appearance and its mechanical systems in an effort to attract additional tenants.

In late March or early April of 1989, the Landlord informed the Tenant of its renovation plan. The following renovations and repairs had the greatest impact on the Tenant’s demised premises:2 (1) installation of a fire sprinkler system on each floor, except the Tenant’s, and pressurization of the fire stairs; (2) removal of asbestos on each floor, except the Tenant’s; (3) replacement of the existing plaza; (4) enclosure of a walkway connecting the building to the garage; (5) replacement of the exterior curtain wall with a new curtain wall; (6) replacement of the air-conditioning cooling towers and chillers; and (7) installation of high pressure air-conditioning ducts on each floor, except the Tenant’s.3

Without question the most controversial renovation was the Landlord’s plan to replace the existing pre-cast concrete exterior curtain walls and windows with new curtain walls and windows. This replacement necessitated exposing the Tenant’s exterior offices to the open environment. According to the plan, each wall was to be replaced over a single week-end. The removal of the pre-cast concrete panels would require the removal of two feet of the Tenant’s ceiling at the perimeter of the building. All partition walls separating the Tenant’s offices were to be cut back either one or two feet from the perimeter as well. The carpet in each perimeter office was to be rolled back at least two feet. At least four feet of clear working space was to be needed in each office, necessitating the removal or relocation of the Tenant's furniture and files in order to accomplish the wall replacement. The Tenant’s walls and ceilings were to be restored no later than the conclusion of the following weekend. The offices were to be fully useable, however, during the intervening week.

[813]*813The Landlord proposed various options to accommodate the Tenant during the renovation including: (1) building out renovated space above the Tenant’s floors and moving the Tenant to that new space, all at the Landlord’s expense, with the Tenant free to depart at the end of the lease term or to negotiate a new lease; (2) paying the Tenant’s moving expenses to a comparable office building nearby and paying any rental increase for the duration of the Tenant’s lease term;4 or, (3) allowing the Tenant to terminate the Lease with a cash payment from the Landlord of $350,000. The Tenant rejected all of these options and decided to move into a new building on its own by December 1, 1990.5

B. Procedural History

On October 30, 1989, the Tenant filed a complaint alleging that the Landlord was constructively evicting the Tenant from its leasehold by the Landlord’s renovation of the building. The Tenant sought to enjoin the renovation until December 1, 1990, when it was to have occupied its new offices. It also sought to recover damages of $1,575,000 for the market value of its remaining leasehold interest from December 1, 1990 through May 31, 1993, the value of its leasehold improvements, the cost of having to prematurely move and purchase new improvements, and the cost of lost profits to its law practice.6

The district court held a bench trial from August 6 through August 14, 1990. The district court found that the lease authorized the Landlord to undertake the challenged renovations without liability to the Tenant and that there was no support for the Tenant’s claim for constructive eviction. Accordingly, it entered judgment on October 1, 1990, in favor of the Landlord. The district court, however, found that, although the intrusion into the Tenant’s space as a result of the removal of the exterior curtain wall could not be avoided, redress was required. Accordingly, the court awarded a twenty percent reduction in rent during the weeks necessary for the installation of the curtain wall. 747 F.Supp. 1470.

The following issues are raised in this appeal: (1) whether the lease authorized the Landlord to undertake the challenged renovations and repairs without liability to the Tenant; (2) whether the Landlord has constructively evicted the Tenant from the premises; and (3) whether the district court erred in refusing to admit additional testimonial and videotape evidence after the close of evidence.

II. ANALYSIS

Interpretation of a lease contract is a question of law subject to de novo review on appeal. Gibbs v. Air Canada, 810 F.2d 1529, 1532 (11th Cir.1987). A district court’s findings of fact will not be reversed unless clearly erroneous. Centel Cable Television Co. of Fla. v. Thos. J. White Development Corp., 902 F.2d 905, 908 (11th Cir.1990).

A. Authorization for the Renovations

Under Florida law, every contract provision should be given meaning and effect. Excelsior Ins. Co. v. Pomona Park Bar & Package Store, 369 So.2d-938, 941 (Fla.1979). The intentions of the parties in entering the lease should be gleaned from the unambiguous terms of the agreement itself. The lease represents the deliberate distribution of risks and benefits by the parties. See Meyer v. Caribbean Interiors, Inc., 435 So.2d 936, 938 (Fla.Dist.Ct.App.1983). Florida law also recognizes that “in the absence of express covenants inconsistent therewith” the ordinary lease [814]*814includes an implied covenant of quiet enjoyment. See Hankins v. Smith, 103 Fla. 892, 138 So. 494, 496 (1931).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
923 F.2d 810, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stinson-lyons-gerlin-bustamante-pa-v-brickell-building-1-holding-ca11-1991.