Stillwater of Crown Point Homeowner's Ass'n v. Kovich

865 F. Supp. 2d 922, 2011 U.S. Dist. LEXIS 117098, 2011 WL 4816743
District Court, N.D. Indiana·Decided October 11, 2011·No. Cause No. 2:09-CV-157-PRC·Published·Cited by 2 cases

Opinion

OPINION AND ORDER

PAUL R. CHERRY, United States Magistrate Judge. -

This matter is before the Court on Plaintiffs’ Motion for Partial Summary Judgment Against Defendant City of Crown Point, Indiana [DE 97], filed by Plaintiffs Stillwater of Crown Point Homeowner’s Association, Inc., individually and on behalf of its members; Roger P. Mahoney; Kent Kolodziej; Kevin J. McKenna; and Margaret McKenna (collectively “Plaintiffs”) on March 4, 2011. A response was filed by the City of Crown Point, Indiana (the “City”) on April 19, 2011. Plaintiffs filed a reply on May 17, 2011, and, with leave of Court, Plaintiffs filed an amended reply on May 18, 2011.

This is the story of two subdivisions and three road crossings in Crown Point, Indiana. The Stillwater of Crown Point Subdivision (“Stillwater Subdivision”) was developed by Stillwater Properties, LLC, Innovative Enterprises, Ltd., Robert Stiglich, and Jack Kovich. The Pine Hill Subdivision (“Pine Hill”) was developed by Hawk Development Corp. Located near the border of the Stillwater Subdivision and Pine Hill is Smith Ditch. Three road crossings — Greenview Place, Stillwater Parkway, and Crooked Creek Trail-span Smith Ditch. The crossings at Greenview Place and Stillwater Parkway are contained within the Stillwater Subdivision. The crossing at Crooked Creek Trail connects the Stillwater Subdivision and Pine Hill, with Hawk constructing a “stub section” of the crossing up to the property line, and Stillwater Properties, LLC constructing the remainder of the crossing, including that portion that spans the channel of Smith Ditch. Each crossing was constructed by placing fill material in Smith Ditch and the adjacent wetlands [926]*926along with two thirty-six inch culverts to convey the flow of water in Smith Ditch under the crossings. In September 2008, flooding occurred in the subdivisions as water backed up behind the crossings, adversely affecting homes in the subdivisions, including those of Kent Kolodziej in Pine Hill and Roger P. Mahoney and Kevin J. and Margaret McKenna in Stillwater Subdivision.

In the instant motion, Plaintiffs seek summary judgment against the City only on their claim of negligence per se for alleged violations of the Indiana Flood Control Act and Crown Point Flood Control Ordinance, arguing that the City violated its duties under both laws by allowing the unpermitted construction of the three crossings, which led to flooding damages to homeowners’ property.

PROCEDURAL BACKGROUND

On June 4, 2009, Plaintiffs filed a Complaint against Jack Kovich, Innovative Enterprises, Ltd., Robert Stiglich, Stillwater Properties, LLC, Hawk Development Corp., and the City of Crown Point, Indiana, seeking injunctive relief and damages.

Count IV of the Complaint alleges that the City was negligent per se because it violated the Indiana Flood Control Act and Crown Point Ordinance by permitting the construction of three crossings of Smith Ditch in the Stillwater of Crown Point and Pine Hill subdivisions, despite the fact that the developers had not obtained floodway construction permit for the crossings from the Indiana Department of Natural Resources. Count V of the Complaint alleges that the City breached its duty owed to Plaintiffs to exercise reasonable care in undertaking, approving, and upgrading the development of streets and drainage infrastructure in the two developments. Count VI alleges that the three crossings constitute public and private nuisances and that Plaintiffs have been harmed by the nuisance conditions created by the City.

Hawk Development Corporation filed an Answer on August 6, 2009. Innovative Enterprises, Ltd. and Jack Kovich filed an Answer on August 14, 2009. The City of Crown Point filed an Answer on September 1, 2009. Robert Stiglich filed an Answer on November 30, 2009.

On October 9, 2009, a Clerk’s Entry of Default was entered against Stillwater Properties, LLC. On November 16, 2009, Defendant Stillwater Properties, LLC was severed as a party defendant for purposes of 28 U.S.C. § 636(c), and the case against Stillwater Properties, LLC only remains pending before Chief Judge Philip P. Simon.

As the remainder of the parties filed forms of consent to have this case assigned to a United States Magistrate Judge to conduct all further proceedings and to order the entry of a final judgment in this case, this case was reassigned to the undersigned Magistrate Judge. Therefore, this Court has jurisdiction to decide this case pursuant to 28 U.S.C. § 636(c).

SUMMARY JUDGMENT STANDARD

The Federal Rules of Civil Procedure mandate that motions for summary judgment be granted “if the pleadings, the discovery and disclosure materials on file, and any affidavits show that there is no genuine issue as to any material fact and that the movant is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(c). Rule 56(c) further requires the entry of summary judgment, after adequate time for discovery, against a party “who fails to make a showing sufficient to establish the existence of an element essential to that party’s case, and on which that party will bear the burden of proof at trial.” Celotex [927]*927Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). “[S]ummary judgment is appropriate — in fact, is mandated — -where there are no disputed issues of material fact and the movant must prevail as a matter of law. In other words, the record must reveal that no reasonable jury could find for the non-moving party.” Dempsey v. Atchison, Topeka, & Santa Fe Ry. Co., 16 F.3d 832, 836 (7th Cir.1994) (citations omitted).

A party seeking summary judgment bears the initial responsibility of informing the court of the basis for its motion and identifying those portions of the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, that it believes demonstrate the absence of a genuine issue of material fact. See Celotex, 477 U.S. at 323, 106 S.Ct. 2548; Fed.R.Civ.P. 56(c). The moving party may discharge its initial responsibility by simply “ ‘showing’ — that is, pointing out to the district court — that there is an absence of evidence to support the nonmoving party’s case.” Celotex, 477 U.S. at 325, 106 S.Ct. 2548. When the nonmoving party would have the burden of proof at trial, the moving party is not required to support its motion with affidavits or other similar materials negating the opponent’s claim. Celotex, 477 U.S. at 323, 325, 106 S.Ct. 2548; Green v. Whiteco Indus., Inc., 17 F.3d 199, 201 n. 3 (7th Cir.1994); Fitzpatrick v. Catholic Bishop of Chicago, 916 F.2d 1254, 1256 (7th Cir.1990).

Free access — add to your briefcase to read the full text and ask questions with AI

Stillwater of Crown Point Homeowner's Ass'n v. Kovich, 865 F. Supp. 2d 922, 2011 U.S. Dist. LEXIS 117098, 2011 WL 4816743 (N.D. Ind. 2011).

865 F. Supp. 2d 922 (Stillwater of Crown Point Homeowner's Ass'n v. Kovich) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Richard Brown and Janet Brown v. City of Valparaiso, Indiana