Stevens Construction & Design, LLC v. Candice Rodgers Hillman

CourtLouisiana Court of Appeal
DecidedJune 12, 2020
Docket2019CA1329
StatusUnknown

This text of Stevens Construction & Design, LLC v. Candice Rodgers Hillman (Stevens Construction & Design, LLC v. Candice Rodgers Hillman) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stevens Construction & Design, LLC v. Candice Rodgers Hillman, (La. Ct. App. 2020).

Opinion

NOT DESIGNATED FOR PUBLICATION

STATE OF LOUISIANA

COURT OF APPEAL

FIRST CIRCUIT

2019 CA 1329

STEVENS CONSTRUCTION & DESIGN, LLC

VERSUS

CANDICE RODGERS HILLMAN

DATE OF JUDGMENT.• JUN 12 2020

ON APPEAL FROM THE TWENTY-SECOND JUDICIAL DISTRICT COURT NUMBER 2017- 14267, DIVISION F, PARISH OF ST. TAMMANY STATE OF LOUISIANA

HONORABLE MARTIN E. COADY, JUDGE

Charles K. Chauvin Counsel for Plaintiff A - ppellee Jane Williams Chauvin Stevens Construction & Design, LLC Destrehan, Louisiana

J. Andrew Murrell Counsel for Defendant -Appellant Baton Rouge, Louisiana Candice Rodgers Hillman

BEFORE: McDONALD, THERIOT, AND CHUTZ, JJ.

Disposition: AFFIRMED AND RENDERED. CHUTZ, J.

Defendant, Candice R. Hillman, appeals a summary judgment in favor of

plaintiff, Stevens Construction & Design, LLC ( SC& D), for the balance due under

a construction contract. SC& D answered the appeal. For the following reasons, we

affirm and render judgment on the answer to the appeal.

FACTUAL AND PROCEDURAL BACKGROUND

Ms. Hillman is an attorney. In March 2017, after negotiating the terms

thereof, she signed a construction contract for the repair and renovation of her home

in Ascension Parish, which had been damaged by a flood in August 2016. The

contract price was $ 47, 800. Ms. Hillman made an initial payment to SC& D in the

amount of $8, 500, and SC& D began work on her house. On August 14, 2017,

SC& D presented Ms. Hillman with an application for payment in the amount of

36, 420 for work it had completed.

On August 17, 2017, approximately one week before Ms. Hillman was to

move in, she and Adam Stevens, member/manager of SC& D, conducted a walk-

through of the house to review the work and establish a punch -list. A dispute arose

between Ms. Hillman and Mr. Stevens over whether a necessary permit had been

acquired and whether a change order was necessary for replacement of a certain

section of tile. During the dispute, Ms. Hillman accused SC& D of being in breach

of contract. She refused to make any payment on the amount SC& D claimed was

due.

By letter dated August 29, 2017, Ms. Hillman' s attorney, Andrew Murrell,

gave SC& D notice of the " termination of the contract." In the letter, Mr. Murrell

asserted SC& D was in default of the contract because necessary permits were not

obtained and there were numerous defects in the work performed that SC& D failed

to cure despite written notice from Ms. Hillman. In conclusion, Mr. Murrell stated

Ms. Hillman would " remit the amount owed to you for the value of the work you

2 actually performed minus the cost of repairing the defective work and the cost of

completing the project," once the additional cost of the repairs and completion of the

work was determined.

On September 14, 2017, SC& D filed suit against Ms. Hillman for breach of

contract seeking to recover $ 40, 175, the alleged balance due under the contract. On

August 16, 2018, approximately eleven months later, SC& D filed a motion for

summary judgment. The motion hearing was originally scheduled for October 30,

2018, but was twice continued. The hearing was finally held on March 20, 2019.

After taking the matter under advisement, the district court signed a judgment on

April 16, 2019, granting summary judgment in favor of SC& D in the amount of

40, 175, plus eighteen percent interest, costs, and $ 2, 500 in attorney fees, all as

provided in the contract.' Ms. Hillman has now appealed.

SUMMARY JUDGMENT

After an opportunity for adequate discovery, a motion for summary judgment

shall be granted if the motion, memorandum, and supporting documents show that

there is no genuine issue as to material fact and that the mover is entitled to judgment

as a matter of law. La. C. C. P. art. 966( A)(3). The summary judgment procedure is

favored and shall be construed to secure the just, speedy, and inexpensive

determination of every action. La. C. C. P. art. 966( A)(2). In determining whether

summary judgment is appropriate, appellate courts review evidence de novo under

the same criteria governing the trial court's determination of whether summary

judgment is appropriate. Riedel v. Fenasci, 18- 0540 ( La. App. 1st Cir. 12/ 28/ 18),

270 So. 3d 583, 590.

The burden of proof rests with the mover. La. C. C. P. art. 966( D)( 1). If the

mover will bear the burden of proof at trial, he must support his motion with credible

The contract grants the contractor the right to recover costs and attorney fees incurred in collecting delinquent approved payments. 3 evidence that would entitle him to a directed verdict if not controverted at trial. Such

an affirmative showing then shifts the burden of production to the party opposing

the motion. An adverse party may not rest upon the mere allegations or denials of

his pleadings, but must produce evidentiary materials demonstrating the existence

of a genuine issue for trial or submit an affidavit requesting additional time for

discovery. La. C. C. P. art. 967( B); Hines v. Garrett, 04- 0806 ( La. 6/ 25/ 04), 876

So. 2d 764, 766- 67 ( per curiam); Alpha Capital US Bank v. White, 18- 0827 ( La.

App. 1st Cir. 12/ 21/ 18), 268 So. 3d 1124, 1128, writ denied, 19- 0135 ( La. 3/ 18/ 19),

267 So. 3d 89.

DISCUSSION

Ms. Hillman argues the district court improperly granted summary judgment

because she did not have an adequate opportunity for discovery and because genuine

issues of material fact existed. Specifically, Ms. Hillman alleges there are factual

issues concerning the validity of the contract, the scope of the work to be performed,

the quality of SC& D' s work, and whether SC& D obtained all the required permits.

Ms. Hillman also contends the district court erred in ruling she did not give notice

of the defective work within forty- eight hours of receiving SC& D' s August 2017

pay application. She maintains she had already provided written notice to SC& D of

its defective work weeks prior to receiving the pay application.

In support of its motion for summary judgment, SC& D submitted, among

other evidence, the affidavit of its member/manager, Mr. Stevens, a copy of the

construction contract signed by Ms. Hillman, and a copy of Ms. Hillman' s initial

payment check in the amount of $8, 500. SC& D also presented a copy of the August

14, 2017 pay application submitted to Ms. Hillman in the amount of $36, 420. The

construction contract provides that, within forty-eight hours of receipt of a pay

application, the homeowner shall provide the contractor with written notice setting

forth a detailed explanation for withholding any portion of the pay application. If

0 such written notice is not given within forty-eight hours, " the application for

payment shall be considered approved by the Owner pursuant to which timely

payment must be made[.]" According to Mr. Stevens' affidavit, Ms. Hillman failed

to provide timely written notice disputing the August 14, 2017 pay application. Nor

did she make any further payments under the contract.

The August 14, 2017 pay application indicated the contracted work was

93. 29% complete. However, as of the date of Mr. Stevens' August 10, 2019

affidavit, he stated that with the exception of three special -order interior doors yet to

be delivered, SC& D had completed all remaining work under the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pennington Const., Inc. v. RA Eagle Corp.
652 So. 2d 637 (Louisiana Court of Appeal, 1995)
Zeller v. Webre
17 So. 3d 55 (Louisiana Court of Appeal, 2009)
Hines v. Garrett
876 So. 2d 764 (Supreme Court of Louisiana, 2004)
Hutchinson v. KNIGHTS OF COLUMBUS, NO. 5747
866 So. 2d 228 (Supreme Court of Louisiana, 2004)
Naquin v. Louisiana Power & Light Co.
951 So. 2d 228 (Louisiana Court of Appeal, 2006)
Naquin v. Louisiana Power & Light Company
949 So. 2d 441 (Supreme Court of Louisiana, 2007)
Mayeaux v. McInnis
809 So. 2d 310 (Louisiana Court of Appeal, 2001)
Rapp v. City of New Orleans
681 So. 2d 433 (Louisiana Court of Appeal, 1996)
Thomas v. Comfort Center of Monroe, LA, Inc.
48 So. 3d 1228 (Louisiana Court of Appeal, 2010)
Cerami v. Haas
197 So. 752 (Supreme Court of Louisiana, 1940)
Board of Ethics in the Matter of Jordan Monsour and Walter Monsour
249 So. 3d 808 (Supreme Court of Louisiana, 2018)
Cecil Blount Farms, L.L.C. v. MAP00-NET
104 So. 3d 1 (Louisiana Court of Appeal, 2012)
Pumphrey v. Harris
111 So. 3d 86 (Louisiana Court of Appeal, 2012)
McCastle-Getwood v. Professional Cleaning Control
170 So. 3d 218 (Louisiana Court of Appeal, 2015)
Thomas v. A. Wilbert & Sons, LLC
217 So. 3d 368 (Louisiana Court of Appeal, 2017)
Cook v. American Gateway Bank
49 So. 3d 23 (Louisiana Court of Appeal, 2010)
Blagg v. Blanch
649 So. 2d 1166 (Louisiana Court of Appeal, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Stevens Construction & Design, LLC v. Candice Rodgers Hillman, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stevens-construction-design-llc-v-candice-rodgers-hillman-lactapp-2020.