Stevens Construction Corp. v. Draper Hall, Inc.

242 N.W.2d 893, 73 Wis. 2d 104, 1976 Wisc. LEXIS 1124
CourtWisconsin Supreme Court
DecidedJune 14, 1976
Docket764 (1974)
StatusPublished
Cited by18 cases

This text of 242 N.W.2d 893 (Stevens Construction Corp. v. Draper Hall, Inc.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stevens Construction Corp. v. Draper Hall, Inc., 242 N.W.2d 893, 73 Wis. 2d 104, 1976 Wisc. LEXIS 1124 (Wis. 1976).

Opinion

Beilfuss, C. J.

This appeal involves a mechanics lien foreclosure by two lien claimants, the plaintiff-appellants, Stevens Construction Corporation and the Bruce Company, against the defendant-respondents, Draper Hall, Inc., Herman J. Wagen, Gladys P. Wagen, Germaine N. Fischer, Philip D. Pearson, Carol Dixon Pearson, Hugh C. Howard, Arlene L. Howard, E. H. Schultz, Fern E. Schultz, Earl P. Keyes, Dorothy C. Keyes, Clifford W. Auer, Mary E. Auer, Albert C. Schallock, Florence M. Schallock, Milo H. Janzen, Jr., Marian D. Janzen, Wau-kesha County Marine Bank, First Federal Savings & Loan Association of Menomonee Falls, and the additional added defendant-respondents, Henry J. Pyhel, Joan L. Pyhel, and Hartland Plastics, Inc. The trial court entered judgment imposing a proportional construction lien upon eight units of the Draper Hall Condominium located in Oconomowoc. The plaintiff-appellants appeal, claiming they are entitled to enforce the full dollar value of their liens against each individual unit.

The facts involved in this controversy are essentially undisputed. In January, 1971, Stevens Construction Corporation entered into a contract with Draper Hall, Inc., in which it agreed to provide general construction work for a structure to be known as Draper Hall. Stevens *108 commenced construction in July of 1971 and made its first substantial excavation during the first week of September, 1971.

In February, 1971, the Bruce Company entered into a contract with Draper Hall, Inc., whereby the Bruce Company agreed to furnish general landscaping work for the same Draper Hall project. The Bruce Company began its landscaping work oh February 12th.

On October 28, 1971, Draper Hall, Inc., complied with the provisions of ch. 703, Stats., relating to the development of condominiums, by recording in the office of the Waukesha .county Register of Deeds the Condominium Declaration required by sec. 703.03.

Stevens performed its final work on the project in February of 1973. On March 1, 1973, it filed a construction lien claim in an amount in excess of $90,000, after first giving notice of its intent to file a lien. An amended claim, containing the legal description of Draper Hall as a condominium with 35 discrete units, was filed on May 21, 1973. The Bruce Company completed its landscaping work on November 1, 1972, and, after giving notice of its intent to file a lien, filed a lien claim on March 29, 1973, in the amount of nearly ■ $12,000. This claim was similarly amended on May 17,1973:

First Federal Savings and Loan Association of Me-nomonee Falls provided the financing for this project, and secured its loan by a mortgage on the property recorded on October 28, 1971. Work on the project was substantially completed in August, 1972, although Stevens. and the Bruce Company worked on the project until early 1973. Between August 10, 1972, and October 24, 1972, the eight units in question on this appeal (out of a total of 35) were sold and conveyed to various purchasers. As provided in the mortgage, First Federal released these individual units from the blanket mortgage after the purchasers paid to First Federal the loan amount attributable to each unit.

*109 In April of 1973, Stevens began proceedings to foreclose upon its lien against, as relevant to this appeal, Draper Hall, Inc., First Federal, and the eight owners of the units which had been sold. Other owners and incumbrancers were eventually added to the action, as was the Bruce Company, which also claimed a lien.

First Federal then cross-complained, for foreclosure of the mortgage it still held on the 27 unsold units, claiming that, even though this mortgage was recorded subsequent to the commencement of construction work, it was nevertheless entitled to priority under sec. 215.21 (4) (a), Stats., which section accords priority to a mortgage executed to a chartered savings and loan association over a lien filed subsequent to the recording of the mortgage. In July of 1973 First Federal, Draper Hall, Inc., Stevens, and the Bruce Company worked out an agreement between themselves relating to the 27 unsold units. First Federal agreed to hold its foreclosure action in abeyance for 15 months during which time it would attempt to sell the unsold units. Stevens and the Bruce Company were to receive a certain sum per unit sold in reduction of their respective lien claims, with the balance going to First Federal. It was also agreed that at the end of the term First Federal could seek judgment of foreclosure and sale of units that were then unsold, with all the sale proceeds going to reduce its mortgage, with the remainder, if any, going to satisfy the lien claims of Stevens and the Bruce Company.

Six units were sold during the term of the agreement, and the claims of Stevens and the Bruce Company were reduced to approximately $70,000 and $8,000, respectively, exclusive of interest and costs.

In August of 1974 the trial court heard and determined the lien claims of Stevens and the Bruce Company with respect to the eight units which were first sold. The trial court rejected the claimants’ argument that they were entitled to look to these eight units for the full *110 dollar amounts of the remaining- claims, and concluded that each of the eight unit owners was entitled to a lien release upon payment of a proportional share (i.e., y35 th) of the amounts still due and owing the claimants. The amended judgment provided that the eight units should be sold unless these proportional shares were paid. It also provided that, if the proportional shares were paid, Stevens and the Bruce Company must release the units from the proportional liens. On October 28, 1974, after the eight unit owners and other interested parties paid $28,500 to Stevens and about $8,800 to the Bruce Company, Stevens and the Bruce Company executed lien releases in favor of the eight units.

When the agreement with First Federal ran out in November of 1974, First Federal foreclosed upon the 21 units which had not been sold. The proceeds from the sale of these units did not even cover the loan amounts due First Federal, so that Stevens and the Bruce Company received nothing from this sale.

A preliminary issue on appeal is presented by the motion of respondents to dismiss this appeal on the ground that the lien claimants, the plaintiff-appellants, waived their right to appeal by accepting the benefits of the foreclosure judgment. We disagree and deny the motion to dismiss the appeal.

The general rule applicable to waiver of appeal by acceptance of the benefits of the judgment appealed from was reiterated by this court in the recent case of Wyandotte Chemicals Corp. v. Royal Electric Mfg. 1 The rule is that an appellant is not permitted to take an appeal when he voluntarily accepts a benefit which is dependent upon that part of the order or judgment which he attacks on appeal. A corollary of that rule is that a party is not precluded from taking an appeal which does not involve a reversal of that part of the judgment under *111 which he has received payment. 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McFarland State Bank v. Sherry
2012 WI App 4 (Court of Appeals of Wisconsin, 2011)
Northern Air Services, Inc. v. Link
2011 WI 75 (Wisconsin Supreme Court, 2011)
Compass Bank v. Brickman Group, Ltd.
107 P.3d 955 (Supreme Court of Colorado, 2005)
Recycle Worlds Consulting Corp. v. Wisconsin Bell
592 N.W.2d 637 (Court of Appeals of Wisconsin, 1999)
Wilson v. Fullerton
964 S.W.2d 208 (Supreme Court of Arkansas, 1998)
Riley v. Lawson
565 N.W.2d 266 (Court of Appeals of Wisconsin, 1997)
Torke/Wirth/Pujara, Ltd. v. Lakeshore Towers of Racine
531 N.W.2d 419 (Court of Appeals of Wisconsin, 1995)
Projects Unlimited, Inc. v. Copper State Thrift & Loan Co.
798 P.2d 738 (Utah Supreme Court, 1990)
Wozniak v. Wozniak
359 N.W.2d 147 (Wisconsin Supreme Court, 1984)
Rainier Pacific Supply, Inc. v. Gray
633 P.2d 1355 (Court of Appeals of Washington, 1981)
Goebel v. National Exchangors, Inc.
277 N.W.2d 755 (Wisconsin Supreme Court, 1979)
State v. Lunz
273 N.W.2d 767 (Wisconsin Supreme Court, 1979)
In Re Estate of Haese
259 N.W.2d 54 (Wisconsin Supreme Court, 1977)
Estreen v. Bluhm
255 N.W.2d 473 (Wisconsin Supreme Court, 1977)
Hostetter v. Inland Dev. Corp. of Montana
561 P.2d 1323 (Montana Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
242 N.W.2d 893, 73 Wis. 2d 104, 1976 Wisc. LEXIS 1124, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stevens-construction-corp-v-draper-hall-inc-wis-1976.