Stephens v. International Paper Co.

542 So. 2d 35, 1989 La. App. LEXIS 563, 1989 WL 30767
CourtLouisiana Court of Appeal
DecidedMarch 29, 1989
Docket20302-CA
StatusPublished
Cited by14 cases

This text of 542 So. 2d 35 (Stephens v. International Paper Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stephens v. International Paper Co., 542 So. 2d 35, 1989 La. App. LEXIS 563, 1989 WL 30767 (La. Ct. App. 1989).

Opinion

542 So.2d 35 (1989)

William R. STEPHENS, Plaintiff-Appellant,
v.
INTERNATIONAL PAPER COMPANY, Defendant-Appellee.

No. 20302-CA.

Court of Appeal of Louisiana, Second Circuit.

March 29, 1989.

Claudius E. Whitmeyer, Shreveport, for plaintiff-appellant.

Cook, Yancey, King & Galloway by Eskridge E. Smith, Jr., and Lunn, Irion, Johnson, Salley & Carlisle by Brian D. Smith, Shreveport, for defendant-appellee.

Before MARVIN, NORRIS and LINDSAY, JJ.

LINDSAY, Judge.

The plaintiff, William R. Stephens, appeals from a trial court judgment sustaining peremptory exceptions of prescription filed by the defendant, International Paper Company, and the third party defendant, *36 Bedsole Wood Corporation (hereinafter referred to as "Bedsole").

FACTS

On April 2, 1984, the plaintiff and his brother-in-law, Dr. Donald E. Wolfe, entered into a timber contract with the defendant International Paper Company. The contract allowed the defendant to cut and harvest Timber on property jointly owned by the plaintiff and Dr. Wolfe. The contract also provided for the grant of a servitude allowing defendant ingress, egress and regress across the plaintiff's lands.

On June 22, 1984, the defendant entered into a contract with Bedsole to carry out the actual cutting. Bedsole, in turn, further subcontracted the job to a local contractor, Travis Broadway. Broadway and his crew began operations on or about June 23, 1984, and continued until early August, 1984. During this time, members of the cutting crew allegedly failed to close two gates on the property on numerous occasions, thus allowing portions of the plaintiff's cattle herd to escape. Some of the animals were not recovered.

On August 12, 1985, the plaintiff filed suit against the defendant, seeking a total of $17,590 in damages. This amount included $14,040 for lost cattle (21 yearlings valued at $440 each and 8 cows valued at $600 each), $2,800 for "cowboy" wages, and $100 for fence damage. The plaintiff also asserted that property he owned jointly with Dr. Wolfe was damaged to the extent of $500 as a result of the logging and cutting operations. The plaintiff also alleged that he personally spent 72 hours of his time in searching for the lost cattle.

In his petition, the plaintiff asserted his claim in contract, or alternatively, in tort. Under his tort claim, plaintiff alleged that the actions of the defendant's employees were a continuing tort which did not cease until all of the work on the property was completed.

The defendant filed a third party demand against Bedsole, in which it asserted that Bedsole had contractually agreed to hold the defendant harmless for any damage caused by Bedsole's employees. Both the defendant and Bedsole filed peremptory exceptions of prescription. Each asserted that the one year prescriptive period for tortious activity under LSA-C.C. Art. 3492 was applicable, and that the last logging activity on the plaintiff's property occurred on August 6, 1984. Thus, the filing of suit on August 12, 1985, was not timely.

Depositions were taken of the testimony of the plaintiff, two of defendant's employees, John Marshall Chamberlin and James B. Babcock, and Billy Ray Bedsole, the owner of Bedsole Wood Corporation, the third party defendant. All parties agreed to submit the exceptions of prescription to the court on depositions and briefs in lieu of live testimony.

In his deposition, the plaintiff described the property at issue and drew a diagram. (See our attached schematic drawing which is based upon the diagram drawn by the plaintiff.) The plaintiff testified that he and his brother-in-law jointly owned Tracts B and C, from which timber was removed pursuant to the contract with the defendant. He stated that he also possessed, as lessee, Tract A, individually. His cattle were fenced in on Tract A. In order to reach Tract B, timber cutters were instructed to enter the front gate of Tract A and then pass through Tract A to the back wire gate cut to allow entry into Tract B. This route was specifically approved by one of the defendant's representative, Walt Salter. The plaintiff testified that the men in the cutting crew left one or both of these gates open on numerous occasions, thus allowing portions of his herd to escape. Although the plaintiff was able to recover most of the strays, some of the cattle were never found.

The plaintiff further testified that the logging crew damaged the front gate of Tract A and a 200-foot portion of the barbed wire fence around Tract C. Additionally, the plaintiff claims that they damaged a tree which subsequently fell on the fence between Tracts A and B.

The defendant's employees, James B. Babcock and John Chamberlin, acknowledged that they knew the gates were to be *37 kept closed to keep the cattle from straying. They also acknowledged that the logging crew did not keep the gates closed. For example, Mr. Babcock admitted that he spoke to the plaintiff several times during the course of the timber operation about the problems with the cattle. Mr. Babcock testified that he sent a man to discuss the situation with the foreman of the crew on more than one occasion; he stated that he also wrote to Mr. Bedsole and informed him of the problem.

Mr. Chamberlin, the defendant's forest technician, inspected the work on the plaintiff's land on the following dates in 1984: June 26, July 9, July 19, July 26, and August 15. The final report was dated August 15, 1984, by which time all of the work had been completed. He testified that the crew usually moved off of the property once the last load was removed. He was unaware of any work which the crew would have done after the last load was taken out.

Mr. Bedsole received the load tickets from his subcontractor, Mr. Broadway. These load tickets represented receipts from the wood mill for each delivery. He testified that it was his experience that the last load ticket from the mill indicated that the work had been completed. The last load ticket for timber removed pursuant to the service contract on the plaintiff's land was dated August 6, 1984. Based upon this load ticket, Bedsole settled up with Broadway for the work done on plaintiff's property.

According to the load tickets in Mr. Bedsole's possession, Mr. Broadway submitted a load ticket dated August 7, 1984, on another job on a different tract of land. This indicated that Bedsole's crew had already completed the work on the plaintiff's land and moved on.

Mr. Bedsole testified that after the timber cutting crew finished its work, the only thing left to be done was a final inspection by the defendant's representative. He stated that the job would not be truly completed until final inspection was conducted by the defendant to determine whether the work was done properly and whether any penalty could be assessed against Bedsole under their contract for not properly executing its terms.

On January 19, 1988, the trial court issued its written opinion, sustaining the exceptions of prescription. It found that the plaintiff had no valid action for breach of contract, which would allow application of a ten-year prescriptive period under LSA-C.C. Art. 3499. Additionally, the court found that the plaintiff's only remedy, if any, was in tort.

In considering whether plaintiff's action in tort was timely filed, the court relied upon the load tickets which Bedsole received from Mr. Broadway in determining that the logging operations on the plaintiff's property ceased on August 6, 1984. Thus, the filing of suit on August 12, 1985 was not within the applicable one year prescriptive period.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Whitney Bank v. SMI Companies Global, Inc.
949 F.3d 196 (Fifth Circuit, 2020)
Carriere v. JACKSON HEWITT TAX SERVICE INC.
750 F. Supp. 2d 694 (E.D. Louisiana, 2010)
Rose v. Tennessee Gas Pipeline Co.
508 F.3d 773 (Fifth Circuit, 2007)
Hanks v. Entergy Corp.
921 So. 2d 1130 (Louisiana Court of Appeal, 2006)
Roche v. Jefferson Davis Electric Cooperative, Inc.
922 So. 2d 759 (Louisiana Court of Appeal, 2006)
Terrebonne Parish School Board v. Mobil Oil Corp.
310 F.3d 870 (Fifth Circuit, 2002)
Baugh v. PARISH GOV'T RISK MANAGEMENT AGENCY
715 So. 2d 645 (Louisiana Court of Appeal, 1998)
Harrison v. Gore
660 So. 2d 563 (Louisiana Court of Appeal, 1995)
Guste v. Hibernia Nat. Bank in New Orleans
655 So. 2d 724 (Louisiana Court of Appeal, 1995)
Ridge Oak Development, Inc. v. Murphy
641 So. 2d 586 (Louisiana Court of Appeal, 1994)
United Gas Pipe Line Co. v. Cargill, Inc.
612 So. 2d 783 (Louisiana Court of Appeal, 1992)
Hampton v. Hibernia Nat. Bank
598 So. 2d 502 (Louisiana Court of Appeal, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
542 So. 2d 35, 1989 La. App. LEXIS 563, 1989 WL 30767, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stephens-v-international-paper-co-lactapp-1989.