Stephan v. Maloof

274 Cal. App. 2d 843, 79 Cal. Rptr. 461, 1969 Cal. App. LEXIS 2123
CourtCalifornia Court of Appeal
DecidedJuly 17, 1969
DocketCiv. 33642
StatusPublished
Cited by13 cases

This text of 274 Cal. App. 2d 843 (Stephan v. Maloof) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stephan v. Maloof, 274 Cal. App. 2d 843, 79 Cal. Rptr. 461, 1969 Cal. App. LEXIS 2123 (Cal. Ct. App. 1969).

Opinion

LILLIE, J.

Judgment was entered for plaintiff, a licensed general contractor, and against defendants in the sum of $12,597 for loss of profits arising from breach of an oral agreement to construct a, one-story shopping center on certain Los Angeles property belonging to defendants as co-owners (tenants in common). Three points,are made on defendants’ appeal from the judgment—first, contrary to the parties’ intentions, the agreement was never reduced to writing and henee no binding agreement resulted; second, the trial court erroneously found that defendant George Maloof while dealing with plaintiff had authority to bind his co-owners;' and finally, the trial court erred in the amount of damages awarded.

Necessarily viewed in a light most favorable to plaintiff-respondent, the evidence reveals among other things that plaintiff was first approached by defendant George Maloof (referred to hereinafter as “George”), and his mother, defendant Annie Maloof, in November of 1965; at that time plaintiff was in the midst of a construction job at a site some eight blocks from defendants’ property. During the conversation which followed, they sought plaintiff’s advice regarding the demolition of certain structures on their land where they proposed to erect a one-story shopping center. A few days *846 later, in response to an inquiry by George, plaintiff indicated he was interested in bidding on the proposed shopping center. Thereafter George delivered to plaintiff two sets' of plans and specifications, together with an “Invitation to Bid” which contained a “Bid Form.” The “Invitation to Bid,” prepared by defendants’ architect at their direction, included the following: “Selected bidder shall execute a contract for construction of the work within five days of notice of selection. ’ ’ The 1 ‘ Bid Form, ’ ’ in turn, provided in pertinent part that “The undersigned further agrees, if awarded the contract, to sign the contract and to furnish a performance bond.

On January 14, 1966, plaintiff delivered his bid to George upon the form he had been furnished. Thereafter, at meetings held on various dates in January and February, plaintiff and George discussed certain proposed changes in the plans and specifications; revised bids were prepared and delivered by plaintiff as a result of such meetings. Subsequently, on February 21, George delivered to plaintiff his latest revised plans which included a doughnut shop addition to the center; after reviewing them, on February 25 plaintiff submitted his latest revised bid. On February 27 plaintiff and George met at the latter’s home and agreed that there would be no further changes in the revised plans which were complete and specific as to type and grade of materials. The parties also agreed on the method of compensating plaintiff, the commencement of construction by March 4, 1966, a construction period of 120 days, and the necessity of securing a. construction bond.

The following morning (February 28) plaintiff recéived a telephone call from George; during the course of their conversation plaintiff stated that he could do the job for $79,453. To this statement, according to plaintiff, George replied: “If you can do the job for $79,000, you have it.” Plaintiff’s rejoinder was: “I accept your offer and I thank you very much for the job.” George then told plaintiff to go ahead: “Let’s get on the ball. Let’s get this thing rolling.” Plaintiff replied: ‘ Fine, I will get right on the phone now and start. ’ ’ Immediately thereafter plaintiff telephoned his concrete man, telling him to come on the job the following day (March 1); a chemical toilet was also ordered, and calls made by plaintiff to the plumber, electrician, steel man and other subcontractors.

Later that same day (February 28) George telephoned plaintiff to “hold off” until he (George) “ha[d] á completion bond in hand.” Plaintiff then went to a bonding com *847 pany, obtained the issued completion bond and delivered it to George that evening. 1 At an earlier meeting that same day, it appears that plaintiff also delivered to George a letter stating in part that " I am pleased to be awarded this work and hope to produce a structure we can both be proud to be associated with. ’ ’

Still later on February 28, plaintiff was again at George’s house. Present for the first time were the remaining defendants. Various questions were asked of plaintiff with reference to plans and specifications. A completed and standard A.I.A. contract was presented' to plaintiff which contained all the terms and conditions reached at previous meetings. Plaintiff signed, requesting defendants to do the same; they declined to do so. On March 3 plaintiff telephoned George, directing attention to the necessity of commencing construction by March 4; George told plaintiff not to worry as he (George) had obtained an extension of time, adding: “Do nothing until you hear from me. ’ ’ Shortly thereafter, while passing the site in question, plaintiff noticed a building under construction; he testified that the same plans and specifications were being followed. The court made a finding (unchallenged by defendants) that the center was eventually completed for the total sum of $77,000, materials of a lesser cost being substituted.

In support of their first contention, defendants cite the decision of this court in Apablasa v. Merritt & Co., 176 Cal.App.2d 719 [1 Cal.Rptr. 500], adhering to the settled rule that “if the parties intend a reduction of their proposed agreement to writing before it can be considered complete, there is no contract until the formal agreement is signed [citations].” (P. 729.) The difference between that ease and the case at hand is that there the preliminary negotiations relating to the production of plaintiff’s invention, and assertedly resulting in a binding agreement, never reached the point where there was a meeting of the minds on all material matters: “ ‘There is no meeting of the minds of the parties while they are merely negotiating as to the terms of the agreement to be entered into. To be final, the agreement must extend to all terms which the parties intend to intro *848 duce, and material terms cannot be left for future settlement. . . . [citation]. ’ ” (P. 730.) Here, however, it is not contended that all of the material conditions and terms were not agreed upon. Thus, defendants’ brief is singularly silent with respect to any claim that further negotiations were necessary to effect a mutual understanding of the parties. Instead, it is simply argued that since plaintiff tried to secure the signature of all defendants on the contract tendered to him at the February 28 meeting in George’s home, his act in so doing indicated unanimity among the parties that no one would be bound until each such signature was obtained.

There is no merit to such argument, likewise rejected in Clarke v. Fiedler, 44 Cal.App.2d 838 [113 P.2d 275], upon facts closely analagous to those at bar. There,, the parties finally (and orally) agreed upon the terms of the agreement after several previous meetings; the following day plaintiff presented a written contract for defendant’s signature, but the latter refused to sign.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CSAA Insurance Exchange v. Hodroj
California Court of Appeal, 2021
CSAA Ins. Exchange v. Hodroj CA6
California Court of Appeal, 2021
FTE Networks, Inc. v. Ivie (In re Ivie)
587 B.R. 729 (D. Idaho, 2018)
Van Vliet v. Escobar CA2/5
California Court of Appeal, 2014
King v. Batim Property Management CA2/8
California Court of Appeal, 2014
Bohm v. Horsley Co. (In Re Groggel)
333 B.R. 261 (W.D. Pennsylvania, 2005)
Oshkosh Truck Corp. v. Lockheed Missiles & Space Co.
678 F. Supp. 809 (N.D. California, 1987)
Mitchell v. Exhibition Foods, Inc.
184 Cal. App. 3d 1033 (California Court of Appeal, 1986)
Collins v. Swope
605 S.W.2d 538 (Missouri Court of Appeals, 1980)
Pacific Grove-Asilomar Operating Corp. v. County of Monterey
43 Cal. App. 3d 675 (California Court of Appeal, 1974)
Battistelli v. Corso
304 A.2d 676 (Connecticut Superior Court, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
274 Cal. App. 2d 843, 79 Cal. Rptr. 461, 1969 Cal. App. LEXIS 2123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stephan-v-maloof-calctapp-1969.