Stepanek v. Kober Construction

625 P.2d 51, 191 Mont. 430
CourtMontana Supreme Court
DecidedMarch 10, 1981
Docket80-333
StatusPublished
Cited by58 cases

This text of 625 P.2d 51 (Stepanek v. Kober Construction) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stepanek v. Kober Construction, 625 P.2d 51, 191 Mont. 430 (Mo. 1981).

Opinion

MR. JUSTICE MORRISON

delivered the opinion of the Court.

Appellant, an employee of a subcontractor hired by the respondent general contractor, appeals from summary judgment granted to the defendants in the District Court. However, appellant limits his appeal to the general contractor, Kober Construction.

In December of 1973, the respondent and Yellowstone County entered into a contract for the construction of the Metra, a multipurpose recreational facility in Billings, Montana. In January of 1974, the respondent entered into a subcontract with Albert D. Wardell Masonry for the completion of masonry work required in the Metra project. Appellant was injured in a fall from the subcontractor’s scaffolding on April 17, 1975.

The trial court granted summary judgment for defendants but failed to state the reasons therefor. Disapproval of such failure has been recently stated in a concurring opinion filed in Big Man v. *432 State of Montana and Case, ---P.2d-- (No. 80-265, decided March 10, 19 81). In the future, we ask that the District Courts state the reasons for granting summary judgment. Here we will review all issues argued to this Court.

For purposes of this appeal, all factual disputes must be resolved in favor of appellant, against whom summary judgment was granted. Harland v. Anderson (1976), 169 Mont. 447, 450, 548 P.2d 613, 615.

Defendant and respondent, Kober Construction, will hereafter be referred to as general contractor. Albert D. Warded Masonry will be referred to as subcontractor.

The primary contract between the general contractor and Yellowstone County required the general contractor to be “responsible for initiating, maintaining, and supervising all safety precautions and programs” connected with the construction. Consistent with this provision, the general contractor’s job superintendent conducted regular safety meetings with all subcontractors on the project and in one instance, the subcontractor was ordered to remove a workman from scaffolding because the general contractor felt the workman’s negligent conduct would cause injury.

The subcontract provided that the subcontractor comply with all applicable safety and health laws and further:

“. . . provide all safeguards, safety devices, and protective equipment and take any other needed actions on his own responsibility; or as the Contractor may determine reasonably necessary to protect the life and health of employees on the job and the safety of the public and to protect property in connection with the performance of the work covered herein.”

The significant issue raised in this appeal is whether the general contractor owed a duty of care to the appellant and if so, upon what basis. If there was no duty owed, then there can be no issues of material fact and granting of summary judgment was proper. Rennick v. Hoover (1980), 186 Mont. 167, 606 P.2d 1079, 1081, 37 St.Rep. 308, 310.

*433 Appellant contends the general contractor owed him a duty of care predicated upon (1) control of the subcontractor’s work reserved in the subcontract and in fact, exercised by the general contractor; (2) the Scaffolding Act, section 50-77-101, M.C.A.; (3) the Safe Place statute, section 50-71-201, M.C.A.; and (4) the primary contract requiring the general contractor to be responsible for safety on the project.

The general contractor contends (1) control of the subcontractor was neither reserved nor exercised; (2) application of the statutes would be improper because the requisite element of control was lacking; (3) safety obligations assumed in the primary contract were delegated; and (4) appellant’s contributory negligence bars recovery.

Appellant further contends that if the case is remanded for trial, Occupational Safety and Health Administration (O.S.H.A.) violations should be treated as negligence per se. The effect of those regulations is herein discussed.

GENERAL CONTRACTOR’S CONTROL:

Montana recognizes the general rule that “absent some form of control over the subcontractor’s method of operation, the general contractor and owner of the construction project are not liable for injuries to the subcontractor’s employees.” Shannon v. Howard S. Wright Construction Co. (1979), 181 Mont. 269, 593 P.2d 438, 441, 36 St.Rep. 632, 636; 2 Restatement of Torts 2d, section 414 (1965). Both parties rely upon Shannon as the controlling statement of law. Appellant contends that the requisite “control” exists if the general contractor had a nondelegable duty to “control.”

A review of the record before us indicates the general contractor’s degree of actual control is disputed. First, the subcontract clause purported by respondent to have delegated all safety responsibility to the subcontractor, does not do so. The general contractor reserved right to control safety compliance on the project.

*434 Second, the depositions of the subcontractor and the job superintendent for the general contractor, demonstrate the subcontractor’s acquiescence in the general contractor’s supervision of the project’s safety. The subcontractors attended weekly safety meetings conducted by the general contractor. Subcontractor Wardell complied with the general contractor’s request that an employee be removed from the scaffolding and assigned to work on the ground. However, appellant’s claim is not limited by a showing of actual control.

The general contractor assumed contractual obligations under the contract with Yellowstone County. Specifically, the general contractor agreed to maintain and supervise job safety.

Montana has previously held that similar contractual arrangements result in creation of a nondelegable duty. Ulmen v. Schwieger (1932), 92 Mont. 331, 12 P.2d 856. In Ulmen the duty extended to a third person not employed by a subcontractor. Here we must decide if that nondelegable duty extends to employees. We hold that it does, and the basis for our holding is discussed in connection with application of the Scaffolding Act.

APPLICATION OF THE SCAFFOLDING ACT:

Section 50-77-101, M.C.A., states:

“All scaffolds erected in this state for use in the erection, repair, alteration, or removal of buildings shall be well and safely supported, of sufficient width, and properly secured so as to ensure the safety of persons working on them or passing under them or by them and to prevent them from falling or to prevent any material that may be used, placed, or deposited on them from falling.”

The statute does not explicitly state what persons owe the duty imposed. In State ex rel. Great Falls Nat. Bank v. District Court (1969), 154 Mont.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Buckles v. Continental Resources Inc.
2020 MT 107 (Montana Supreme Court, 2020)
McDonald v. Ponderosa Enterprises, Inc.
2015 MT 160 (Montana Supreme Court, 2015)
Paull v. Park County
2009 MT 321 (Montana Supreme Court, 2009)
United National Insurance v. St. Paul Fire & Marine Insurance
2009 MT 269 (Montana Supreme Court, 2009)
Olson v. Shumaker Trucking & Excavating Contractors, Inc.
2008 MT 378 (Montana Supreme Court, 2008)
Beckman v. Butte-Silver Bow County
2000 MT 112 (Montana Supreme Court, 2000)
Harwood v. Glacier Electric Cooperative, Inc.
949 P.2d 651 (Montana Supreme Court, 1997)
Stratemeyer v. Lincoln County
915 P.2d 175 (Montana Supreme Court, 1996)
Porter v. Galarneau
911 P.2d 1143 (Montana Supreme Court, 1996)
Gibby v. Noranda Minerals Corp.
905 P.2d 126 (Montana Supreme Court, 1995)
Pierce v. ALSC Architects, P.S.
890 P.2d 1254 (Montana Supreme Court, 1995)
Steiner v. Department of Highways
887 P.2d 1228 (Montana Supreme Court, 1994)
Brockie v. Omo Construction Inc.
844 P.2d 61 (Montana Supreme Court, 1992)
Maguire v. State
835 P.2d 755 (Montana Supreme Court, 1992)
Nave v. Harlan Jones Drilling
827 P.2d 1239 (Montana Supreme Court, 1992)
Johnston v. American Reliable Insurance
810 P.2d 1189 (Montana Supreme Court, 1991)
Kemp v. Big Horn County Electric Co-Operative
798 P.2d 999 (Montana Supreme Court, 1990)
Micheletto v. State
798 P.2d 989 (Montana Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
625 P.2d 51, 191 Mont. 430, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stepanek-v-kober-construction-mont-1981.