Steinrock Roofing & Sheet Metal Inc. v. James S. McCulloch, PNC Bank, N.A.

CourtIndiana Court of Appeals
DecidedMarch 30, 2012
Docket22A05-1108-CC-457
StatusPublished

This text of Steinrock Roofing & Sheet Metal Inc. v. James S. McCulloch, PNC Bank, N.A. (Steinrock Roofing & Sheet Metal Inc. v. James S. McCulloch, PNC Bank, N.A.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steinrock Roofing & Sheet Metal Inc. v. James S. McCulloch, PNC Bank, N.A., (Ind. Ct. App. 2012).

Opinion

FILED Mar 30 2012, 9:41 am FOR PUBLICATION CLERK of the supreme court, court of appeals and tax court

ATTORNEY FOR APPELLANT: ATTORNEY FOR APPELLEE:

DENNIS J. STILGER TIMOTHY R. McCARTHY Dennis J. Stilger, P.S.C. Louisville, Kentucky Louisville, Kentucky

IN THE COURT OF APPEALS OF INDIANA

STEINROCK ROOFING & SHEET METAL, ) INC., ) ) Appellant-Plaintiff, ) ) vs. ) No. 22A05-1108-CC-457 ) JAMES S. McCULLOCH, PNC BANK, N.A. ) ) Appellee-Defendant. )

APPEAL FROM THE FLOYD SUPERIOR COURT The Honorable Maria D. Granger, Judge Cause No. 22D03-1002-CC-327

March 30, 3012

OPINION–FOR PUBLICATION

BAKER, Judge After the defendant-homeowner’s roof was severely damaged in a windstorm, the

plaintiff-contractor undertook to repair the damages. The homeowner failed to pay the

entire amount due under the contract because of the contractor’s allegedly deficient

workmanship. The contractor sued and the homeowner counterclaimed. Substantial

evidence was presented at trial establishing that the contractor’s work was deficient in a

number of respects. And the trial court, as the fact finder, properly awarded damages to

the homeowner on his counterclaim. The trial court also properly concluded that the

contractor had waived any claim to reduce the damage award under the Home

Improvement Warranties statute.

Appellant-plaintiff Steinrock Roofing & Sheet Metal, Inc. (Steinrock), appeals the

trial court’s judgment entered in favor of appellee-defendant James S. McCulloch, and

PNC Bank, N.A.1 Specifically, Steinrock argues that the trial court erred in excluding

discovery and the potential testimony of an insurance agent who inspected the work and

made the payments for repairs on the roof. Steinrock also maintains that the trial court

should have found in his favor on his defamation claim and that the trial court erred in

finding a material breach of contract by Steinrock. Moreover, Steinrock argues that the

trial court should have limited McCulloch’s damages to the difference in fair market

value in accordance with Indiana Code section 32-27-1-14, the Home Improvement

Warranties statute.

1 Although PNC Bank, N.A., is also a named defendant in this case, it did not appear at trial or assert any interest in the Real Estate.

2 Concluding that the trial court correctly determined that Steinrock breached the

contract, properly awarded damages to McCulloch, and finding no other error, we affirm.

FACTS

McCulloch owned an older home in New Albany. On September 14, 2008, the

clay tile roof of the residence was severely damaged in a wind storm. Thereafter,

McCulloch made a claim for the damage to the roof with Westfield Insurance Company,

his homeowner’s insurance carrier.

Westfield estimated that the costs of repairs amounted to approximately $95,000.

Thereafter, McCulloch contracted with Steinrock to repair the tile roof. The contract

amount was for $95,367.13, which required 2% interest per month for late payments, plus

the filing fee and reasonable attorney’s fees.

Steinrock commenced work in May 2009, and completed it in August 2009.

Pursuant to the contract, McCulloch made two payments totaling $75,270.60. However,

McCulloch withheld $15,000 from the second check in light of concerns that he had

regarding various deficiencies in the roof. Those deficiencies included leaking, falling,

cracked, and warped tiles, and other tiles that were improperly installed. As a result of

McCulloch’s failure to pay the last draw under the contract, Steinrock filed a mechanic’s

lien against McCulloch.

Thereafter, Steinrock filed suit against McCulloch, seeking an unpaid balance on

the contract in the amount of $29,096.53. McCulloch denied owing this amount and filed

3 a counterclaim, asserting that Steinrock had installed the roof in a negligent and un-

workmanlike manner.

McCulloch hired Gilbert Arnold, a roofing expert from Louisville, Kentucky, to

consult about the damages. At a bench trial that commenced on December 2, 2009,

Arnold testified many of the field tiles were not attached properly to the wood deck, and

many of the hip and ridge tiles were not embedded properly in the mortar and were loose.

Mortar was missing in other tiles that resulted in open joints. Arnold further testified that

field tiles were spaced too close together in many areas, and some of them appeared to be

cupped, broken, and cracked. Arnold was of the opinion that the roof could only be

restored by removing all of the tiles and replacing the underlayment and clay tile roofing.

In sum, the entire roof needed to be removed and reinstalled.

During the pendency of the action, a second expert that both parties chose

inspected the roof. The expert, Richard Spalding, of the Merrick-Kemper Company in

Louisville, testified in a videotaped deposition. Spalding’s findings coincided with those

of Arnold. Spalding’s primary concern was that the hip and ridge tiles were not properly

installed, and he noted that they were poorly embedded in their mortar beds and their

fasteners were insufficient. Spalding easily removed the screw holding in one of the hip

joints with his fingers because it had failed to engage the wood to a depth of 3/4 inches

per the manufacturer’s recommendation. Rather, the hip and tile screws that Steinrock

installed penetrated only 3/8 inch.

4 Spalding testified that he actually removed a hip tile, examined the underlayment,

and determined that the tiles were not correctly installed. Spalding stated that two pieces

of the underlayment met at a “point” at the hip and ridge, and commented that such was

not the proper way to install the underlayment. Tr. p. 168. Spalding also testified that

the tile spacing was not correctly laid out, in that there was some overlap and they were

laid too tightly or too far apart from each other. Spalding was also of the opinion that the

flashing at the chimney was not installed correctly and required replacement.

In sum, Spalding testified that while he did not believe that the entire roof needed

to be replaced, many repairs had to be undertaken so the roof would last within its

seventy-year life expectancy. Spalding estimated the repair costs at $75,059.00.

At a bench trial that commenced on March 1, 2011, McCulloch introduced

photographic evidence that a rather large leak was coming from below the hip tiles.

McCulloch testified to the many deficiencies including tiles that were cracked, chipped,

warped, or cupped. Mortar was falling out of the hip and ridge joints and fasteners were

sticking out of the top pieces of tile. Tile fasteners were being driven into empty joint

spaces between the planks on his roof. McCulloch testified that he withheld the last

payment because of these deficiencies.

It was also established at trial that during the pendency of the proceedings,

McCulloch had heard that Steinrock had gone out of business and telephoned the

company to ascertain its status. The phone call was received by a Ms. Tara Hunter who

testified at trial. Hunter was the receptionist at Electric Blue, which is a blueprint

5 company that rents office space from Steinrock. Hunter testified that she received a brief

phone call from McCulloch, inquiring as to whether Steinrock was still in business.

Hunter further testified she assured McCulloch that the business was still in

operation and began to search for Steinrock’s phone number.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Van Bibber v. Norris
419 N.E.2d 115 (Indiana Supreme Court, 1981)
Strack and Van Til, Inc. v. Carter
803 N.E.2d 666 (Indiana Court of Appeals, 2004)
Indiana-American Water Co. v. Town of Seelyville
698 N.E.2d 1255 (Indiana Court of Appeals, 1998)
Schrader v. Eli Lilly and Co.
639 N.E.2d 258 (Indiana Supreme Court, 1994)
Richey v. Chappell
594 N.E.2d 443 (Indiana Supreme Court, 1992)
Snellenbarger v. Kunz
798 N.E.2d 523 (Indiana Court of Appeals, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Steinrock Roofing & Sheet Metal Inc. v. James S. McCulloch, PNC Bank, N.A., Counsel Stack Legal Research, https://law.counselstack.com/opinion/steinrock-roofing-sheet-metal-inc-v-james-s-mccull-indctapp-2012.