Steel Dynamics Columbus, LLC v. Altech Environment USA Corp.

273 F. Supp. 3d 627
CourtDistrict Court, N.D. Mississippi
DecidedMarch 31, 2017
DocketNO. 1:14-CV-124-DMB-DAS
StatusPublished
Cited by2 cases

This text of 273 F. Supp. 3d 627 (Steel Dynamics Columbus, LLC v. Altech Environment USA Corp.) is published on Counsel Stack Legal Research, covering District Court, N.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steel Dynamics Columbus, LLC v. Altech Environment USA Corp., 273 F. Supp. 3d 627 (N.D. Miss. 2017).

Opinion

MEMORANDUM OPINION

Debra M. Brown, UNITED STATES DISTRICT JUDGE

In August 2010, Steel Dynamics Columbus, LLC (under its former name, Severs-tal Columbus, LLC),1 contracted with Al-tech Environment USA Corp. to purchase two continuous emissions monitoring units (“CEMS”) for its steel plant in Columbus, Mississippi. The CEMS, installed at Steel’s plant in 2011, were required by the Mississippi Department of Environmental Quality (“MDEQ”) under the Title V permit issued to Steel. After experiencing multiple operating issues with the CEMS over the course of three years, Steel commenced this action against Altech, alleging the CEMS were defective. Steel seeks to recover from Altech damages for (1) the cost of the CEMS; (2) the costs incurred in trying to make the CEMS work; (3) a fine imposed by MDEQ; and (4) attorney’s fees.

The Court held a three-day bench trial on Steel’s claims for negligence, breach of contract, breach of warranties, and contractual indemnification. At the bench trial, after Steel’s case in chief, the Court granted Altech’s motion for a judgment on partial findings as to Steel’s contractual indemnity claim only. After the presentation of all evidence at trial, the Court took under advisement Altech’s renewed motion for a judgment on Steel’s remaining claims. Upon consideration of the trial evidence and the applicable law, the Court issues this memorandum opinion as its ultimate findings of fact and conclusions of law.

I

Procedural History

On June 30, 2014, Steel filed this action against Altech in the Circuit Court of Lowndes County, Mississippi. Doc. # 2. On August 4, 2014, Altech removed the case to this Court based on 28 U.S.C. § 1332.2 [633]*633Doc. # 1 at ¶ 5. On October 14, 2014, Steel filed an amended complaint, asserting claims for breach of contract, breach of implied warranties, breach of express warranty, negligence, and contractual indemnification.3 Doc. # 13 at ¶¶ 22-25, 36-89.

On November 6, 2015, Alteeh filed a “Motion for Partial Summary Judgment on the Issue of Contractual Limitation of Remedies.” Doc. # 49. Though denying liability, Alteeh limited its motion to “how ... provisions [in the parties’ purchase contract] limit recoverable damages.” Doc. # 50 at 2. The Court denied Altech’s motion without prejudice, concluding that ruling on only the issue of damages before a trial in which liability would be contested would be inefficient. Doc. # 85 at 2 n.5, 3. The Court further stated that it preferred to consider the issue of damages in view of all facts to be presented at the bench trial4 rather than just on the motion record. Id.

The Court held a bench trial from June 20, 2016, to June 23, 2016. At the close of Steel’s case in chief, Alteeh moved for a judgment on partial findings on all of Steel’s claims, which the Court granted only as to Steel’s contractual indemnity claim.5 At the close of Altech’s case, Steel declined to present a rebuttal case, and Alteeh re-urged its motion for judgment as to Steel’s remaining claims. The Court took Altech’s re-urged motion under advisement and ordered that the record be left open for seven days following trial. After the close of the record, Steel and Alteeh filed proposed findings of fact and conclusions of law on October 21, 2016. Doc. # 96; Doc. # 97.

II

Factual Findings

Steel operates a steel plant in Columbus, Mississippi, that melts scrap metal in an electric arc furnace. Tr. at 45, 90, 93.6 The process releases pollutants regulated by Title V of the Clean Air Act. Id. at 94.

MDEQ issued Steel a Title V permit which, among other things, required Steel to install two CEMS. CEMS provide continuous data on the level of monitored pollutants in industrial emissions. Steel’s Title V permit required the installation of the CEMS to monitor levels of four regulated pollutants—Nitrogen Oxides (NO*), Carbon Monoxide (CO), Volatile Organic Compounds (VOCs), and Sulfur Dioxide (S02). Ex. P-1 at §§ 3.B.12-B.19.

A, Alteeh Proposal

In May 2010, Steel, which had no experience with CEMS, solicited bids to pur[634]*634chase the CEMS required by MDEQ. Tr. at 96, 307-08. Altech, an Illinois provider of environmental monitoring ■ systems, responded with a written proposal dated August 10, 2010. Ex. P-2,

Altech’s proposal specified that Altech would supply CEMS that would monitor the pollutants regulated under Steel’s Title V permit. Id, at 28-30, 40.7 The proposal included a “DAS” computer, which would be pre-loaded with software to operate CEMS and would be necessary to receive usable information from the CEMS.8 Id. at 29. The concentration ranges within which the CEMS would measure the regulated pollutants were to be set “as required.” Id, at 28. As proposed, Altech represented that its CEMS would be “very well suited to monitoring emissions on arc furnaces.” Id. at 23.

Under Altech’s proposal, Altech would begin a “7-Day Drift Test” on the CEMS within five to seven days after “Equipment Startup” and, within a year after that, a more extensive “Relative Accuracy Test Audit” (“RATA”) required by Steel’s Title V- permit. Id. at 41, 45, 49; Tr. at 526. The proposal included a one year maintenance contract, which included quarterly maintenance, as well as support services for startup, RATA testing, and “regulatory approval.” Ex. P-2 at 29-30, 46.

The proposal also specified installation and maintenance requirements to be met by Steel and Altech. Regarding installation, the CEMS were to be mounted on a wall in a temperature-controlled room provided by Steel. Id, at 26, 41. Regarding maintenance, the proposal specified quarterly, semi-annually, and yearly maintenance, with the first year of maintenance to be performed by Altech under a proposed quarterly maintenance contract. Id. at 45. Every quarter, the CEMS were to' undergo a performance test known as a “Calibration Gas Audit” and preventative maintenance, including servicing filters in the probe assembly.9 Every year, the CEMS were to undergo a RATA. Id.

B. CEMS Purchase

On August 17, 2010, Steel issued a purchase order to Altech in the amount of $447,610.20 for two CEMS. Ex. P-3. The purchase order, which referred to Altech’s proposal both by its identifying number and by specific numbered items, included a one year quarterly maintenance contract, a DAS computer with CEMLink5™ software from Contec, and a quality assurance plan for regulatory approval. Id.; Ex. P-2 at 28-30.' When Steel ordered the two CEMS, “[Altech] understood that [Steel] intended to use the CEMS units to monitor emissions [from its steel plant] in compliance 'with the Title V Permit that MDEQ issued to [Steel].” Doc. #86 at § 9.a.(5), (6). . .

The undated “Goods and Services: Terms and Conditions of Purchase” (“Terms”) include two sections relating to liability.10 One section provides for an express warranty, and the other disclaims all implied warranties. Ex. P-4 at § 14, As [635]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
273 F. Supp. 3d 627, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steel-dynamics-columbus-llc-v-altech-environment-usa-corp-msnd-2017.