State v. Sherrill

534 P.2d 598, 13 Wash. App. 250, 1975 Wash. App. LEXIS 1338
CourtCourt of Appeals of Washington
DecidedApril 21, 1975
Docket2318-1
StatusPublished
Cited by25 cases

This text of 534 P.2d 598 (State v. Sherrill) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Sherrill, 534 P.2d 598, 13 Wash. App. 250, 1975 Wash. App. LEXIS 1338 (Wash. Ct. App. 1975).

Opinion

Swanson, J.

In this eminent domain proceeding commenced in March 1972, the State seeks to acquire 4.63 acres of property owned by respondents (hereinafter generally referred to as “the owner”) in order to construct a so-called “diamond” interchange in Skagit County about 1 mile south of the city of Mount Vernon where Interstate 5 is intersected by Anderson Road. The jury returned a verdict awarding the property owner $46,300 as just compensation. The State appeals.

The trial of this action presented a complicated fact pattern involving an earlier acquisition by the State from a prior owner of part of the same tract of land here in question. This acquisition was necessary because of a 1955 state highway improvement plan (“1955 plan”) which stood partially completed and abandoned at the time of the trial in the present action.

In general terms, the State’s assignments of error focus upon rulings by the trial court which affected the “before” taking valuation basis of the subject property. First, at a pretrial hearing, the trial court ruled, in effect, that in determining the fair market value of the property before the acquisition, the jury should assume that the never-completed construction under the 1955 plan was completed; second, the trial court ruled as a matter of law that the “commercial” zoning classification of the subject property which existed at the time of trial should be considered to be part of the “before” situation and thereby, the State contends, foreclosed consideration of any other zoning classification *252 despite evidence that prior rezones from “residential” to “commercial” were granted because of the project for which the property was being taken; third, the court refused the State’s proposed instruction on zoning. The State contends these rulings were erroneous, prejudicing its presentation of evidence and requiring a new trial.

The Trial Court’s Ruling On Valuation

At the pretrail hearing agreed upon by the parties to obtain a ruling from the trial judge as to the effect of the unfinished construction under the 1955 plan upon the valuation of the subject property in the “before” situation and, specifically, to determine whether the jury ought to consider the subject property as it existed in fact on the date of trial or whether they should assume all features of the 1955 plan to have been completed, the following undisputed factual chronology was presented: In the earlier condemnation proceeding, by a stipulated judgment and decree of appropriation entered November 19, 1956, the State acquired from the owner’s predecessors, J. M. Sherrill and Nina Sherrill, 1.01 acres and all access rights of the abutting property to the right-of-way being taken except, as the judgment provided, “that the right of reasonable access shall be granted to that certain frontage service road to be constructed along the Easterly side of said highway . . .” This 1956 acquisition was necessary because of the 1955 plan which called for construction of a 4-lane limited access highway, designated Primary State Highway 1, and now known as Interstate 5, through Skagit County to bypass the city of Mount Vernon. The 1955 plan also directed construction of entrance and exit ramps on both sides of the highway at or near the Anderson Road intersection, but with no provision by overpass or otherwise for cross-traffic at Anderson Road. In addition, the 1955 plan included a frontage road on the east side of the highway to serve the abutting property which is the subject of the present action.

The State constructed the four lanes of highway, but after the passage of the federal Interstate Highways Act in *253 1956, Primary State Highway 1 was redesignated S.R. 5 (Interstate 5), and further implementation of the 1955 plan was abandoned in the sense that there was no further construction. Consequently, the exit and entrance ramps and frontage road at the Anderson Road intersection described in the 1955 plan were never built; however, unrestricted access to Interstate 5 at grade was available to the abutting property owners and traffic was permitted to cross Interstate 5 at grade at the Anderson Road intersection. On August 17, 1970, the Washington State Highway Commission adopted a plan to construct a diamond interchange at the Anderson Road intersection which required the acquisition of the subject property of 4.63 acres located in the southeast quadrant of the intersection, and thereby left the owner with 9.14 acres.

The State argued to the trial court that the valuation of the subject property in the “before” situation should be determined by consideration of the actual condition of the property on the date of trial, not what its condition would have been if the State had completed construction according to the 1955 plan. This contention was stated to the court as follows:

The state’s position is that we should consider the 1955 plan. We should know about its existence and we should know how it effects market value today and the value that should be considered. But we shouldn’t consider something to be there that is not there and assuming it were built which it is not. There is a remedy for respondents if they are damaged and that issue is not before us.

The owner contended that the 1956 judgment and decree of appropriation agreed to by his predecessor gave him vested access rights to the highway and, because the 1956 judgment was predicated on the 1955 plan, the State was bound by all features of the plan and could not deviate from it. The owner persuaded the trial court that in appraising the subject property in the “before” situation, it must be assumed that the improvements provided for in the 1955 plan are complete, arguing that only if such an assumption is *254 made can the owner not only recover its alleged damages for the State’s failure to complete the 1955 plan, but also receive just compensation for the subject property. The owner’s counsel stated, “We assume it is built right today according to the 1955 plan which the state is bound by regardless of whether it is constructed or not. They are bound to do it.” The trial court accepted the owner’s argument and ruled that the State was bound by the 1955 plan. This pretrial ruling established the basis for appraising respondent’s property before the acquisition and, in practical terms, it was interpreted to mean that the appraisers had to regard all features of the 1955 plan, including off and on ramps, frontage road, etc., as having been completed and in existence at the time of trial.

The Proper Standard Of Valuation

On appeal, the State contends that the basis thus adopted by the trial court to appraise the subject property erroneously combines a statutory condemnation action with a claim for damages. The State argues that it was greatly prejudiced by the trial court’s ruling which, in effect, made mandatory, in the appraisal of the fair market value of the subject property “before” taking, the assumption that all construction features of the 1955 plan were in fact complete —an assumption which all parties recognized to be a fiction. We agree.

The trial court erred in combining a claim for damages, based on the State’s deviation or failure to complete the 1955 plan, with the determination of just compensation for the taking of the subject property in this statutory condemnation proceeding.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mark and Lynn Stephens v. Town of Steilacoom
Court of Appeals of Washington, 2025
Thomas Center Owners Assoc. v. Robert E. Thomas Trust
Court of Appeals of Washington, 2020
Overlake Farms B.l.k. Iii Llc, App. v. Bellevue-overlake Farm, Llc, Resp.
196 Wash. App. 929 (Court of Appeals of Washington, 2016)
Kenneth Hauge v. City Of Lacey And Thurston County
Court of Appeals of Washington, 2014
Snohomish County v. Kay Kohler
Court of Appeals of Washington, 2013
State v. Paul Bunyan Rifle & Sportsman's Club, Inc.
130 P.3d 414 (Court of Appeals of Washington, 2006)
Western Farmers Electric Cooperative v. Enis
1999 OK CIV APP 111 (Court of Civil Appeals of Oklahoma, 1999)
Sintra, Inc. v. City of Seattle
131 Wash. 2d 640 (Washington Supreme Court, 1997)
Hoover v. Pierce County
903 P.2d 464 (Court of Appeals of Washington, 1995)
Town of Paradise Valley v. Young Financial Services, Inc.
868 P.2d 971 (Court of Appeals of Arizona, 1993)
City of Bellevue v. Kravik
850 P.2d 559 (Court of Appeals of Washington, 1993)
Carson v. Willstadter
830 P.2d 676 (Court of Appeals of Washington, 1992)
State v. Templeman
693 P.2d 125 (Court of Appeals of Washington, 1984)
Kansas City Power & Light Co. v. Jenkins
648 S.W.2d 555 (Missouri Court of Appeals, 1983)
State v. McDonald
656 P.2d 1043 (Washington Supreme Court, 1983)
State v. Evans
634 P.2d 845 (Washington Supreme Court, 1982)
State v. Evans
612 P.2d 442 (Court of Appeals of Washington, 1980)
State v. Coleman
576 P.2d 925 (Court of Appeals of Washington, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
534 P.2d 598, 13 Wash. App. 250, 1975 Wash. App. LEXIS 1338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-sherrill-washctapp-1975.