State v. Fiorenzo

671 N.E.2d 287, 108 Ohio App. 3d 500
CourtOhio Court of Appeals
DecidedJanuary 2, 1996
DocketNo. 94-T-5172.
StatusPublished
Cited by8 cases

This text of 671 N.E.2d 287 (State v. Fiorenzo) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Fiorenzo, 671 N.E.2d 287, 108 Ohio App. 3d 500 (Ohio Ct. App. 1996).

Opinion

Joseph E. Mahoney, Presiding Judge.

The following appeal arises from a bench trial before the Trumbull County Court of Common Pleas finding appellant, James Fiorenzo, guilty of theft in office, complicity to theft in office, and four counts of forgery. For the reasons stated below, we affirm.

In January 1993, appellant began his term as the Trumbull County Engineer, having been newly elected to the position in November 1992. Soon after taking office, appellant began seeking information about the process that he needed to follow in order to remodel the Trumbull County Engineer’s Office.

During appellant’s second week in office, he was informed by Roselyn Ferris, Clerk for the Trumbull County Commissioners, that any plans he had for remodeling would require, pursuant to R.C. 307.86, a competitive bidding process if the aggregate cost of the planned renovations exceeded $10,000. 1 During the week prior to this conversation with Ferris, appellant had encountered the bidding requirements of R.C. 307.86 when the county required him to return a vehicle he had attempted to lease, which had a total cost in excess of $10,000.

Despite the advice of Ferris and his previous encounter with the bidding requirements of R.C. 307.86, appellant spoke with Edward Bush, then the Trumbull County Auditor, regarding appellant’s remodeling plans. Bush testified that appellant told him that he, appellant, had just spoken with the commissioners’ clerk regarding certain procedures of the building laws and that appellant felt that Ferris was “making him jump through hoops.” Bush confirmed for appellant the information Ferris had supplied and, on two occasions during the month of January, sent the engineer’s office written information about the bidding process. Furthermore, when appellant stated his intention to keep *503 the cost of the office remodeling under $10,000 by using several different contractors, Bush informed appellant that the remodeling would be considered one job. The project, Bush told appellant, could not be split between several contractors in an effort to spread the cost and thereby avoid the competitive bidding process.

Starting in mid-February 1993, appellant began his remodeling project at the Trumbull County Engineer’s Office. A total of four rooms were remodeled. On the first floor of the building, the offices used by the engineer and the engineer’s secretary were updated, while the conference room was converted into additional office space. Additionally, an old lunchroom on the second floor was converted into a new conference room.

Much of the work done throughout the remodeling project was completed by Trumbull County Engineer employees, working on county time. Appellant was still working in the building throughout the project, and county laborers testified to conversations they had with appellant regarding the quality of work that they had completed and additional work that still needed to be finished. Several county workers testified about their role in the project, which included the following: pulling up and discarding of old carpeting and padding, creation of a permanent wall between the secretary’s office and the new office space, electrical work in the new office space, painting of walls, and installation of new shelving in the engineer’s office. Other work was contracted out, including laying of new carpeting, wallpapering, installation of new blinds, and renovation of a bathroom connected to the engineer’s office.

Beginning in March 1993, the county began receiving billing statements from three separate contractors for work supposedly completed at the Trumbull County Engineer’s Office. A statement from Donald E. Walters of “Don Walter’s Construction” totaling $6,820.20 was submitted for work done to the first-floor conference room, which had been converted into offices. M.B. Construction, owned by Michael Baka, submitted a statement totaling $7,886.54 for work on the office of the engineer’s secretary. Richard L. Warzala, of Warzala Construction, submitted two statements for payment: $8,975 for work on the engineer’s office and $1,502 for converting the second-floor lunchroom into the new conference room. All statements, totaling $25,183.74, were approved by appellant and sent to the proper county officials for payment. Although none of the statements provided a complete list of the work done by the contractors, each statement did seek payment for work that had either not been done by that particular contractor or had been actually performed by county employees.

In a letter dated April 7,1993, Bush informed appellant that the auditor’s office had received a number of requests for payment that exceeded the $10,000 limitation imposed by R.C. 307.86. Bush informed appellant that payment would *504 be delayed, pending a meeting with the county commissioners and other county officials. This meeting was held on May 14,1993. Although it was acknowledged that appellant failed to comply with the required bidding procedures, the consensus reached at the meeting was that the contractors should be paid, provided that appellant supplied detailed information as to the nature of the remodeling, the materials used, the dates of the work performed, and the names of those individuals who performed the work.

In response to this request, on May 24, 1993, appellant submitted a cost breakdown of the materials and labor used in the remodeling of each office as provided by the three contractors. This cost breakdown was submitted on appellant’s stationery and signed by him. On June 8,1993, after a request by the county commissioners for more information, appellant provided contracts signed by each contractor showing the materials and labor they allegedly provided. As with the earlier billing statements, these cost breakdowns listed items that were either not done by the contractors or actually performed by county employees.

While the county initially withheld paying the submitted statements only because appellant had failed to comply with the bidding procedures, when they received the cost breakdowns, county officials began to question the validity of some of the items listed in those statements. For instance, Bush, apparently referring to the media attention this case had received, testified about the “infamous toilet seat” for which the county was billed $110.60. On June 26,1993, in an interview with Janet Rogers, a reporter for television station WFMJ, appellant stated that he thought the remodeling of the Trumbull County Engineer’s Office would cost over $25,000 and that he had hired three contractors in an effort to comply with the state’s bidding procedures.

Following an investigation by the Trumbull County Sheriffs Department, it was revealed that neither Donald Walters, owner of Don Walters Paving Co., nor Michael Baka, owner of M.B. Construction, had participated in the remodeling job at the Trumbull County Engineer’s Office. Walters and Baka each testified at trial that sometime in February or March 1993, Richard Warzala, of Warzala Construction, was given a blank bill from each of their businesses. Each man affixed his signature to the bill after it had been filled out. Walters and Baka each testified that he met with Warzala and had no contact with appellant. However, Baka testified to some remodeling work he and Warzala performed on appellant’s home in May 1993.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hanamura-Valashinas v. Transitions by Firenza, L.L.C.
2020 Ohio 4888 (Ohio Court of Appeals, 2020)
State v. Trammell
2013 Ohio 4615 (Ohio Court of Appeals, 2013)
Pollock v. Associated Public, 06ca8 (4-9-2007)
2007 Ohio 1726 (Ohio Court of Appeals, 2007)
Wright v. Suzuki Motor, Unpublished Decision (6-27-2005)
2005 Ohio 3494 (Ohio Court of Appeals, 2005)
State v. Echols
752 N.E.2d 314 (Ohio Court of Appeals, 2001)
State v. Moore
675 N.E.2d 13 (Ohio Court of Appeals, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
671 N.E.2d 287, 108 Ohio App. 3d 500, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-fiorenzo-ohioctapp-1996.