State v. Crook County

256 P.3d 178, 242 Or. App. 580, 2011 Ore. App. LEXIS 666
CourtCourt of Appeals of Oregon
DecidedMay 11, 2011
Docket08CV0045; A142004
StatusPublished
Cited by10 cases

This text of 256 P.3d 178 (State v. Crook County) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Crook County, 256 P.3d 178, 242 Or. App. 580, 2011 Ore. App. LEXIS 666 (Or. Ct. App. 2011).

Opinion

*582 HASELTON, P. J.

Petitioner, State of Oregon through the Department of Land Conservation and Development (DLCD), appeals the circuit court’s judgment in a writ of review proceeding that affirmed respondent Crook County’s 1 determination that respondent Shelley Hudspeth (Hudspeth) has a vested right to complete development of a 59-lot residential subdivision in compliance with county and state waivers issued pursuant to Ballot Measure 37 (2004). 2 On appeal, DLCD contends, inter alia, that the circuit court misconstrued applicable law in sustaining the county’s determination that Hudspeth has a vested right to complete that development because there was inadequate consideration of the expenditure ratio factor (viz., the ratio of expenditures to total project costs). In response, Hudspeth contends that, as to the merits, the circuit court properly determined that, under the circumstances of this case, she had a vested right but that, as a preliminary matter, the appeal must be dismissed because DLCD lacks standing to pursue it. For the reasons explained below, we conclude that (1) DLCD has standing to appeal; and (2) consistently with our decision in Friends of Yamhill County v. Board of Commissioners, 237 Or App 149, 238 P3d 1016 (2010), rev allowed, 349 Or 602 (2011), the circuit court should have remanded the decision to the county to determine the total project cost and to give proper weight to the *583 expenditure ratio in the circumstances of this case. Accordingly, we deny the motion to dismiss and remand the circuit court’s judgment.

For purposes of appeal, the following facts are undisputed. Measure 37 waivers from the county and the state allowed for the development of a 59-lot subdivision on Hudspeth’s property. Hudspeth obtained tentative approval from the county for a subdivision 3 and expended hundreds of thousands of dollars to develop the property before Measure 49 became effective on December 6, 2007.

Thereafter, Hudspeth applied for a determination from the county that she had a vested right to complete and continue the use described in the Measure 37 waivers. 4 Hudspeth’s application indicated that the total project budget was $5,081,946. That figure, however, did not include the cost of residences that would ultimately be constructed in the subdivision. DLCD submitted written comments in response to Hudspeth’s application that consisted of “guidelines for applying vested right common law in the context of Measure 49” that were developed by DLCD and the Department *584 of Justice. According to DLCD, it offered the guidelines “for the county to consider in reviewing this application and requested] that it be included in the record.”

The county’s planning director concluded that Hudspeth had a vested right to complete and continue the use described in the waivers. As pertinent to the issues on appeal, in considering the expenditure ratio factor, the county’s planning director determined that Hudspeth “ha[d] spent over $500,000 in ‘allowed expenditures’ * * *.” 5 Further, the planning director determined that “the cost of individual residences shall not be included in the total project costs for completion for the subdivision and that those costs are relative to future land use approvals for site plan review and building permits.” Accordingly, the director calculated the ratio of allowed expenditures (i.e., $502,300) to total project cost (i.e., $5,081,946) to be 9.88 percent.

Pursuant to a county procedure, DLCD appealed the planning director’s determination to the Crook County Court. As pertinent here, and as identified in its notice of appeal to the county court, DLCD’s primary contention was that “[t]he director should have included the cost of individual residences in total project costs for the use that applicant seeks to vest.”

In response, Hudspeth noted that “[t]he ratio test is one factor of many to be considered in the vesting determination” and that “the case law does not require that the total *585 cost of building the homes be considered in the ratio test,” particularly where, as here, she “[did] not intend to build homes, but rather intend[ed] to sell buildable lots.” Alternatively, Hudspeth contends that, if the cost of the residences is included in the denominator of the expenditure ratio, any determination of that cost would be purely speculative. Nevertheless, Hudspeth asserts that “[t]he cost of homes could be as low as $100,000 (double wide manufactured homes)” and that, even assuming that the cost to complete each of the 59 residences was as much as $200,000, the resulting expenditure ratio demonstrated that “this development [had] vested.”

The county court affirmed the planning director’s decision. Although the county court generally incorporated the planning director’s findings and conclusions into its order, it specifically stated that

“[tjhe total cost of the project need not include the costs of the homes which is determined by this Court to be too speculative and there is no direct authority on point requiring this Court to include the costs of the homes for this project; however, the Court also finds that even with the cost of homes included in the calculation, with a minimum cost of $100,000 per dwelling, there is a sufficient substantial investment directly related to the establishment of the residential subdivision, which was made in good faith, to vest this development!.]”

DLCD sought review of the county court’s order in the circuit court. 6 As pertinent to the dispositive issue in this appeal, the circuit court issued a letter opinion in which it concluded that “a specific determination of the denominator in the ratio of investment to total cost of development is not required in every case.” Further, the court reasoned that, “[e]ven if a specific ratio is required by Oregon law, which I believe it is not, the county alternatively found that, if the cost of homes is included in the calculation at $100,000 per dwelling[ 7 ] there was sufficient and substantial investment to vest the development.”

*586 Consistently with its letter opinion, the court entered a judgment, sustaining the local government’s determination that Hudspeth had a vested right to complete the development of her property and dismissing DLCD’s writ of review. DLCD appeals.

Thereafter, Hudspeth filed a motion to dismiss, contending that “DLCD does not have statutory authority to appeal the Circuit Court’s decision.” In response, DLCD noted that the issue concerning its authority had not been raised below and appeared to question whether that issue was the proper subject of a motion to dismiss.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Clatsop County
281 P.3d 613 (Court of Appeals of Oregon, 2012)
STATE EX REL. DEPT. OF LAND CONSERVATION & DEVT. v. Crook County
274 P.3d 260 (Court of Appeals of Oregon, 2012)
State v. Mullen
263 P.3d 1146 (Court of Appeals of Oregon, 2011)
Oregon Shores Conservation Coalition v. Board of County Commissioners
258 P.3d 1269 (Court of Appeals of Oregon, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
256 P.3d 178, 242 Or. App. 580, 2011 Ore. App. LEXIS 666, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-crook-county-orctapp-2011.