Oregon Shores Conservation Coalition v. Board of County Commissioners

258 P.3d 1269, 243 Or. App. 298, 2011 Ore. App. LEXIS 709
CourtCourt of Appeals of Oregon
DecidedJune 1, 2011
Docket082633; A143688
StatusPublished
Cited by2 cases

This text of 258 P.3d 1269 (Oregon Shores Conservation Coalition v. Board of County Commissioners) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oregon Shores Conservation Coalition v. Board of County Commissioners, 258 P.3d 1269, 243 Or. App. 298, 2011 Ore. App. LEXIS 709 (Or. Ct. App. 2011).

Opinion

*300 HASELTON, P. J.

Petitioner Oregon Shores Conservation Coalition (OSCC) appeals the circuit court’s judgment in a writ of review proceeding that affirmed respondent Clatsop County’s 1 determination that respondents Gary and Beverly Aspmo (the Aspmos) have a vested right to complete development of a 30-lot residential subdivision in compliance with county and state waivers issued pursuant to Ballot Measure 37 (2004). 2 On appeal, OSCC contends that the reviewing court misconstrued the applicable law in sustaining the county’s determination that the Aspmos had a vested right to complete that development because (1) the Aspmos “had no final plat approval or building permits and had not initiated the use” — viz., the construction of residences; (2) a significant portion of the Aspmos’ development expenditures were not made in good faith; and (3) there was not adequate consideration of the expenditure ratio — that is, a comparison of the relevant expenditures to the “total project cost.” Further, OSCC contends that the reviewing court erred in upholding the county’s finding that the Aspmos’ expenditures could not be adapted to an alternative lawful use because that finding was not supported by substantial evidence. Consistently with our decision in Friends of Yamhill County v. Board of Commissioners, 237 Or App 149, 165-68, 176, 178, 238 P3d 1016 (2010), rev allowed, 349 Or 602 (2011), we reject OSCC’s legal contentions concerning good faith and the initiation of construction and lack of permits without further discussion but conclude that the court should have remanded the decision to the county to determine the total project cost and to give proper weight to the expenditure ratio in the circumstances of this case. Further, for the reasons that we will *301 explain, we conclude that OSCC’s contentions concerning the adaptability of expenditures are unreviewable. Accordingly, we reverse and remand the reviewing court’s judgment.

The material facts are uncontroverted. In 1995, the Aspmos obtained state and county waivers that allowed for the development of a 30-lot residential subdivision. The Aspmos subsequently obtained preliminary subdivision approval and claimed to have expended over $200,000 to develop the property before Measure 49 became effective on December 6, 2007. 3

Thereafter, the Aspmos applied to the county’s Director of Transportation and Development Services for a determination that they had a vested right to complete and continue the use described in the Measure 37 waivers, and OSCC submitted comments in response to the application. The director determined that “the Aspmos have demonstrated a vested right to continue and complete phase one of their development as a residential subdivision, and to construct dwellings on each of the five lots in phase one,” but that they “have not demonstrated a vested right to complete and continue development of the remainder of the property.”

*302 Significantly, unlike in other cases that we have considered, 4 the director determined that, in calculating the vested right expenditure ratio, the cost of residences must be included in the denominator. The director noted that, even though the “Aspmos did not include the cost of constructing homes on each lot in the subdivision,” he could rely on a “rough estimate,” which “assumfed] the current average price per square foot of $120, for homes between 1,500 and 2,500 square feet.” In light of that estimate, the director determined that “the Aspmos ha[d] spent between 2% and 3% of the total cost to develop the property” and, thus, that the expenditure ratio “factor weighted] against a vested right.”

The director also determined that the adaptability factor — that is, whether the expenditures could apply to other uses of the property — “weighted] against a vested right.” Specifically, the director reasoned that, even though the expenditures “are contrary to the property’s use for forest operations,” most of those expenditures “could have been used for the 1-10 lots that would have been permitted by Measure 49[.]” 5

Pursuant to a local procedure, the Aspmos appealed the director’s decision to the board of commissioners, and, again, OSCC submitted comments. With regard to the expenditure ratio, the board agreed with the director that “the cost of constructing homes is properly included in the total project cost * * In determining the total project cost in this case, the board determined that it could properly consider “a range of the potential total cost” of development. Specifically, the board explained:

*303 “There is conflicting evidence in the record as to the total costs associated with constructing homes in the Subdivision. Opponent 1000 Friends of Oregon submitted evidence estimating that the total project cost is approximately $10,024,880. The Director roughly estimated that homes would cost $120 a square foot to construct and that homes would range from 1,500 to 2,500 square feet in size. At this rate, the Director calculated a total project cost ranging from $5,000,000 to $9,000,000. The Aspmos countered this testimony with evidence that homes could be constructed on the Property for substantially less than the Director estimates, particularly if they implemented prefabricated or modular construction techniques. In such case, the cost of constructing the homes could be as low as $31 a square foot. If the homes cost only $31 a square foot and were 1,812 square feet in size, the Aspmos could construct all 30 homes for approximately $1,680,000, bringing the total project cost to $2,840,000.
“The Board finds that it is reasonable to consider these estimates as a range of the potential total cost for developing the Subdivision with a dwelling on each lot. This range extends from $2,840,000 to $10,024,880. The Aspmos have incurred eligible expenses totaling $244,772.89. These expenses represent between 2.4% and 8.6% of the total project cost. Although the Board finds that the Aspmos’ expenditures are substantial in nature, the Board finds that there is insufficient evidence to support a determination that the expenditure ratio weighs in favor of finding a vested right to complete and continue development of the Subdivision with a dwelling on each lot.”

Further, the board reasoned that, even though it did not weigh in favor of a determination of vesting, the ratio factor “should have lesser importance in the overall analysis of the Application.” According to the board, that was so because “the over $7,000,000 range in cost estimates and the current volatility of the credit and housing markets renders these figures inherently unreliable” such that “the resulting expenditure ratio is not informative in this context.”

With regard to the issue of the adaptability of expenditures, the board determined that the director’s determination that the Aspmos’ expenditures could apply to other uses was not supported by the evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Or. Shores Conservation Coal. v. Bd. of Commissioners of Clatsop Cnty.
441 P.3d 647 (Court of Appeals of Oregon, 2019)
Oregon Shores Conservation v. Bd. of County
277 P.3d 639 (Court of Appeals of Oregon, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
258 P.3d 1269, 243 Or. App. 298, 2011 Ore. App. LEXIS 709, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oregon-shores-conservation-coalition-v-board-of-county-commissioners-orctapp-2011.