STATE THROUGH DEPT. OF TRANSP. v. Scott

650 P.2d 158, 59 Or. App. 25, 1982 Ore. App. LEXIS 3172
CourtCourt of Appeals of Oregon
DecidedSeptember 1, 1982
DocketA7711-16420, CA 19390
StatusPublished
Cited by10 cases

This text of 650 P.2d 158 (STATE THROUGH DEPT. OF TRANSP. v. Scott) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
STATE THROUGH DEPT. OF TRANSP. v. Scott, 650 P.2d 158, 59 Or. App. 25, 1982 Ore. App. LEXIS 3172 (Or. Ct. App. 1982).

Opinion

*27 WARDEN, J.

On January 31, 1977, defendant Scott, doing business as Waconda West Construction (Scott) entered into a contract as prime contractor with the Oregon State Highway Division to perform cleaning and painting and to install safety devices on the Columbia River (Astoria) bridge for $328,978. Defendant United States Fidelity and Guaranty Company, (USF&G) provided the performance bond for Scott on the project. On February 8, 1977, Scott subcontracted with B & E Painting, Inc., for B & E to perform sand blasting and painting work for $212,000. 1 On May 11, 1977, defendants Edward and Bernice Columbus, owners of B & E, executed a personal guarantee of all obligations of B & E to Scott.

During the course of the project, a dispute arose between Scott and B & E, and on August 17, 1977, B & E stopped working on the bridge. LaGrande Industrial Supply Co., the relator, was a supplier to B & E. LaGrande was unpaid and filed this action against B & E, the Columbuses and Scott, and against the USF&G on the bond. LaGrande’s claim was settled by a payment by Scott, and LaGrande is not involved in this appeal.

In May, 1978, Scott filed a cross-claim against B & E and the Columbuses, alleging that they had breached their agreement by stopping work on the bridge. In June, B & E filed its answer to the cross-claim and, in February, 1979, filed its supplemental cross-claim against Scott and USF&G, alleging that Scott had breached the agreement by failing to make progress payments, by failing to pay B & E workers directly and by failing to pay for extra work performed. The cross-claims were tried before a jury, which returned a verdict in favor of B & E but awarded no damages. Judgment was entered, and Scott appeals.

Scott’s first six assignments of error are that the trial court erred in denying his motions for directed verdicts on a variety of issues. When determining the propriety of a motion for a directed verdict, we view the evidence *28 in the light most favorable to the party against whom it is sought. Scott v. Mercer Steel/Edwards Realty, 263 Or 464, 466-67, 503 P2d 1242 (1972). In order to prevail on a motion for directed verdict, it must be shown that reasonable persons could draw but one inference from the evidence and that the inference supports the conclusion urged by the moving party. James v. Carnation Co., 278 Or 65, 69, 562 P2d 1192 (1977).

Scott first contends that the evidence is undisputed that B & E breached its contract and that, therefore, he was entitled to a directed verdict on his claim for costs incurred in completing the project after B & E refused to perform further. A party to a contract who complains that the other party has breached the terms of a contract must prove performance of the contract on his own part. Huszar v. Certified Realty Co., 266 Or 614, 620, 512 P2d 982 (1973). In the present case, Scott presented evidence that the subcontract was for $212,000, that he had paid to B & E or to others on its behalf, excluding charges for paint, approximately $157,000 (or 74 percent of the total subcontract price), that payments were to be made on a monthly basis in proportion to the percentage of work completed by B & E and that only 50 percent of the work had been completed. That evidence is undisputed in the record as presented to this court. 2 Scott does not, however, direct us to any evidence in the record to show that he complied with his additional contractual duty to pay B & E workers directly. 3 Nonperformance by Scott of this duty, if so material as to justify á refusal by B & E to perform its part of the contract, would have discharged B & E’s duty to perform. Wasserburger v. Amer. Sci. Chem., 267 Or 77, 82, 514 P2d 1097 (1973). Whether a breach is so material as to have such a result is ordinarily a question of fact. In this case the jury could have found that B & E was justified in stopping work on the project and, therefore, was discharged *29 from performing its contract with Scott. The motion for directed verdict on Scott’s claim for damages for completing B & E’s work was properly denied.

Scott next contends that he was entitled to a directed verdict on three claims for indemnification for payment of obligations incurred by B & E. The first claim is for $23,000, which Scott paid to LaGrande in settlement of the lawsuit that precipitated this case. The second is for $6,500, which Scott paid to Andrews & Andrews Equipment Company, and the third is for $1,442 for miscellaneous payments made by Scott to other creditors of B & E.

In an action for indemnity, the plaintiff must plead and prove that 1) a third party made a claim against him; 2) he reasonably incurred costs in defending or satisfying the claim; and 3) as between the plaintiff and the defendant, the costs incurred ought to be borne by the latter. PGE v. Const. Consult. Assoc., 57 Or App 116, 643 P2d 1334 (1982). In the present case, counsel for B & E conceded at trial that B & E owed the amounts in question and that the amounts were reasonable and necessary. It is undisputed that Scott paid the debts in the amount claimed, and it is also undisputed that, according to the contract, B & E was to “furnish all labor, material, equipment, scaffolds, etc. * * From the foregoing evidence, it is clear that as between Scott and B & E, B & E ought to be liable for the debts, and Scott is therefore entitled to indemnification. Scott’s motions for directed verdicts on the three claims for indemnification should have been granted.

Scott next contends that he was entitled to a directed verdict on his claims against Edward and Bernice Columbus on their agreement to personally guarantee the subcontract obligations of B & E. Because the guarantee agreement could only come into play if B & E was obligated to Scott and because the jury found it was not, this issue is not properly before us on this appeal and we need not consider it. 4

*30 Next, Scott contends that he was entitled to a directed verdict on each of the cross-claims of B & E. The first claim 5 is for $5,300, which B & E contended was the difference between what B & E expended on the project and what it claims it received from Scott. This figure was apparently derived by subtracting $66,000 6 that Scott paid B & E from approximately $71,300 that B & E expended. However, it is undisputed that Scott paid an additional $10,000 to Mr. Columbus for work as superintendent on the project and that the $10,000 was meant to be included as part of the total subcontract price. B & E, therefore, actually received $76,000, or $4,700 more than it expended. The trial court should have granted Scott’s motion for a directed verdict on this claim.

B & E’s second claim is for lost profits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ARCH CHEMICALS, INC. v. Radiator Specialty Co.
727 F. Supp. 2d 997 (D. Oregon, 2010)
Moore Excavating, Inc. v. Consolidated Supply Co.
63 P.3d 592 (Court of Appeals of Oregon, 2003)
Portland General Electric Co. v. Jungwirth Logging, Inc.
951 P.2d 1101 (Court of Appeals of Oregon, 1997)
Smith v. Urich
947 P.2d 1125 (Court of Appeals of Oregon, 1997)
City of Portland v. Paulson
779 P.2d 188 (Court of Appeals of Oregon, 1989)
State v. Sweet
763 P.2d 739 (Court of Appeals of Oregon, 1988)
Martin v. Cahill
752 P.2d 857 (Court of Appeals of Oregon, 1988)
Paprock v. Defenbaugh
693 P.2d 654 (Court of Appeals of Oregon, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
650 P.2d 158, 59 Or. App. 25, 1982 Ore. App. LEXIS 3172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-through-dept-of-transp-v-scott-orctapp-1982.