Moore Excavating, Inc. v. Consolidated Supply Co.

63 P.3d 592, 186 Or. App. 324, 2003 Ore. App. LEXIS 159
CourtCourt of Appeals of Oregon
DecidedFebruary 12, 2003
Docket9906-05896; A112636
StatusPublished
Cited by18 cases

This text of 63 P.3d 592 (Moore Excavating, Inc. v. Consolidated Supply Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moore Excavating, Inc. v. Consolidated Supply Co., 63 P.3d 592, 186 Or. App. 324, 2003 Ore. App. LEXIS 159 (Or. Ct. App. 2003).

Opinion

*326 LINDER, J.

Plaintiff Moore Excavating, Inc., brought this action seeking common-law indemnity and damages for negligence from defendant Consolidated Supply Co. The trial court granted defendant’s motion for summary judgment on both claims and entered judgment for defendant. Plaintiffs appeal requires us to resolve two unrelated issues. The first is whether the discharge element of the claim for common-law indemnity can be satisfied based on plaintiffs settlement of a claim with a third party on which defendant is also liable when the settlement did not legally extinguish defendant’s liability on the claim. The second issue is whether the terms of the contract between plaintiff and defendant create the kind of special relationship that can be a basis for a duty on defendant’s part to further plaintiffs economic interests. For the following reasons, we agree with the trial court’s resolution of both issues and affirm.

On review of a grant of summary judgment, we view the facts and all reasonable inferences that may be drawn from them in the light most favorable to the nonmoving party — in this case, plaintiff. ORCP 47 C; Robinson v. Lamb’s Wilsonville Thriftway, 332 Or 453, 455, 31 P3d 421 (2001). Because it had the burden of proving all the elements of its claims at trial, plaintiff was required to produce evidence to establish a material issue of fact to avoid summary judgment. ORCP 47 C.

Plaintiff entered into an agreement with Aspen Meadows, LLC, (Aspen) to install a domestic water system in a manufactured home development. Plaintiff purchased the pipe and glue for that project from defendant. According to what plaintiff characterizes as “the standard of practice of contractors and suppliers in the industry and the area,” plaintiff relied on defendant to select the appropriate glue for the system “based upon the pipe specifications, the time of year for installation and other factors.” Plaintiff also relied on defendant’s expertise in carrying out that selection.

Plaintiff installed the water system, using the pipes and glue that it received from defendant. After the installation, Aspen discovered that the water system was leaking *327 and, based on that discovery, asserted claims against plaintiff. Plaintiff and Aspen entered into a settlement agreement pursuant to which plaintiff paid Aspen $37,000 and installed a new water system. Also pursuant to that settlement agreement, Aspen released all claims that it had against plaintiff. Plaintiff, for its part, reserved all of its claims against defendant. The settlement agreement did not release Aspen’s claims against defendant.

Defendant moved for summary judgment on plaintiffs indemnity claim on the ground that plaintiff could not prove that it had discharged defendant’s liability to Aspen. Plaintiff responded by producing its settlement agreement with Aspen as well as the affidavit of plaintiffs president, Roy Moore. That affidavit simply stated that Aspen asserted claims against/plaintiff resulting from leaks in the water system and that Moore incurred costs and expenses in defending against and satisfying those claims.

In reply, defendant argued that, because plaintiffs settlement agreement with Aspen did not demonstrate that Aspen released its claims against defendant, plaintiff could not prove that it had discharged defendant’s liability to Aspen. Shortly after defendant filed its reply, plaintiff submitted the affidavit of Jeffrey Payne, Aspen’s managing member, which indicatéd through the following averments that Aspen had no intention of pursuing any claims against defendant:

“5. Neither Aspen nor I have ever pursued or contemplated pursuing any claim against Consolidated Supply Co. arising out of the leaks in the water lines at the Project, or any other issues related to the Project.
“6. Neither Aspen nor I have any intention of pursuing any claim against Consolidated Supply Co. now or at any time in the future related to the water line leaks at the Project.
“7. As a result of the performance by Moore pursuant to the Mutual Release and Settlement Agreement between Aspen and Moore, Aspen is satisfied that it has received adequate compensation for all damages resulting from the *328 leaks in the domestic water line system at the Project discussed above and the domestic water line system at the Project has been replaced.”

In ruling on defendant’s motion for summary judgment on the indemnity claim, the trial court concluded that, because the settlement agreement did not expressly release Aspen’s claims against defendant, and notwithstanding the averments in the Payne affidavit, those claims survived. The trial court therefore determined that plaintiff produced no evidence to create a material issue of fact as to whether plaintiff had discharged defendant’s liability to Aspen. Thus, as a matter of law, plaintiff was not entitled to indemnity.

Plaintiffs primary argument on appeal is that the trial court erred in concluding that it was required to obtain a release of Aspen’s claims against defendant. 1 Specifically, plaintiff argues that the Supreme Court’s decision in Savelich Logging v. Preston Mill Co., 265 Or 456, 509 P2d 1179 (1973), does not require a release, that the trial court erred in relying on the law of contribution to support its reasoning, and that this court’s decisions require only proof that an indemnity plaintiff incurred reasonable costs in defending or satisfying a claim. Plaintiff also argues that the evidence it submitted in opposition to defendant’s motion is sufficient to create a triable issue of fact about whether it discharged defendant’s liability. Defendant responds that, regardless of whether the trial court was correct about the necessity of a release, the central issue is whether plaintiff was able to “prove that it discharged a liability owed jointly by plaintiff and defendant to Aspen.” According to defendant, plaintiff did not produce sufficient evidence to create a jury question on that element of its claim.

In an action for indemnity, a plaintiff must plead and prove that (1) it has discharged a legal obligation owed to a third party; (2) the defendant was also liable to the third party; and (3) as between the plaintiff and the defendant, the *329 obligation ought to be discharged by the defendant. Fulton Ins. v. White Motor Corp., 261 Or 206, 210, 493 P2d 138 (1972), overruled in part on other grounds by Waddill v. Anchor Hocking, Inc., 330 Or 376, 8 P3d 200 (2000). As stated above, the issue here is whether plaintiff has discharged a legal obligation owed to a third party. To prove that element, plaintiff must show that it discharged the obligation owed to Aspen “so as to extinguish both its own and defendants’ liability.” Savelich Logging, 265 Or at 460. Thus, the question we must answer is not whether, as a factual matter, Aspen is content with plaintiffs performance under their settlement. Rather, consistently with Savelich Logging, the question is whether plaintiff has extinguished defendant’s liability to Aspen.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

COHEN v. SUBARU CORPORATION
D. New Jersey, 2022
Benson Tower Condominium Owners Ass'n v. Victaulic Co.
22 F. Supp. 3d 1126 (D. Oregon, 2014)
Marton v. Ater Construction Co.
302 P.3d 1198 (Court of Appeals of Oregon, 2013)
Bixby v. KBR, Inc.
893 F. Supp. 2d 1067 (D. Oregon, 2012)
Cain v. BOVIS LEND LEASE, INC.
817 F. Supp. 2d 1251 (D. Oregon, 2011)
ARCH CHEMICALS, INC. v. Radiator Specialty Co.
727 F. Supp. 2d 997 (D. Oregon, 2010)
Budget Rent-A-Car Systems v. Bridgestone
203 P.3d 154 (New Mexico Court of Appeals, 2008)
Budget Rent-a-Car Sys., Inc. v. Bridgestone Firestone N. Am. Tire
2009 NMCA 13 (New Mexico Court of Appeals, 2008)
MT BUILDERS, LLC v. Fisher Roofing Inc.
197 P.3d 758 (Court of Appeals of Arizona, 2008)
United States Brass Corp. v. Dormont Manufacturing Co.
242 F. App'x 575 (Tenth Circuit, 2007)
Boyer v. Barney
162 P.3d 1016 (Court of Appeals of Oregon, 2007)
VTech Communications, Inc. v. Robert Half, Inc.
77 P.3d 1154 (Court of Appeals of Oregon, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
63 P.3d 592, 186 Or. App. 324, 2003 Ore. App. LEXIS 159, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moore-excavating-inc-v-consolidated-supply-co-orctapp-2003.