State of Minnesota, by Its Attorney General, and Minnesota Public Utilities Commission v. Federal Energy Regulatory Commission and the United States of America, and Northern States Power Company (Minnesota) Northern States Power Company (Wisconsin) Lake Superior District Power Company Public Service Commission of Wisconsin, Intervenors. State of Minnesota, by Its Attorney General, and Minnesota Public Utilities Commission v. Federal Energy Regulatory Commission and United States of America, and Northern States Power Company (Minnesota) and (Wisconsin) and Lake Superior District Power, Intervenors

734 F.2d 1286, 1984 U.S. App. LEXIS 22459
CourtCourt of Appeals for the Eighth Circuit
DecidedMay 15, 1984
Docket83-1745
StatusPublished
Cited by1 cases

This text of 734 F.2d 1286 (State of Minnesota, by Its Attorney General, and Minnesota Public Utilities Commission v. Federal Energy Regulatory Commission and the United States of America, and Northern States Power Company (Minnesota) Northern States Power Company (Wisconsin) Lake Superior District Power Company Public Service Commission of Wisconsin, Intervenors. State of Minnesota, by Its Attorney General, and Minnesota Public Utilities Commission v. Federal Energy Regulatory Commission and United States of America, and Northern States Power Company (Minnesota) and (Wisconsin) and Lake Superior District Power, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State of Minnesota, by Its Attorney General, and Minnesota Public Utilities Commission v. Federal Energy Regulatory Commission and the United States of America, and Northern States Power Company (Minnesota) Northern States Power Company (Wisconsin) Lake Superior District Power Company Public Service Commission of Wisconsin, Intervenors. State of Minnesota, by Its Attorney General, and Minnesota Public Utilities Commission v. Federal Energy Regulatory Commission and United States of America, and Northern States Power Company (Minnesota) and (Wisconsin) and Lake Superior District Power, Intervenors, 734 F.2d 1286, 1984 U.S. App. LEXIS 22459 (8th Cir. 1984).

Opinion

734 F.2d 1286

STATE OF MINNESOTA, By its ATTORNEY GENERAL, and Minnesota
Public Utilities Commission, Petitioners,
v.
FEDERAL ENERGY REGULATORY COMMISSION and the United States
of America, Respondents,
and
Northern States Power Company (Minnesota); Northern States
Power Company (Wisconsin); Lake Superior District
Power Company; Public Service
Commission of Wisconsin, Intervenors.
STATE OF MINNESOTA, By its ATTORNEY GENERAL, and Minnesota
Public Utilities Commission, Petitioners,
v.
FEDERAL ENERGY REGULATORY COMMISSION and United States of
America, Respondents,
and
Northern States Power Company (Minnesota) and (Wisconsin)
and Lake Superior District Power, Intervenors.

Nos. 83-1745, 83-2271.

United States Court of Appeals,
Eighth Circuit.

Submitted Feb. 15, 1984.
Decided May 15, 1984.

George F. Bruder, Bruder & Gentile, Washington, D.C., David A. Lawrence, Law Dept., Northern States Power Company, Minneapolis, Minn., for intervenors Northern States Power Company (Minnesota), Northern States Power Company (Wisconsin), Lake Superior District Power Company.

Hubert H. Humphrey, III, Atty. Gen., State of Minn., Karl W. Sonneman, Sp. Asst. Atty. Gen., St. Paul, Minn., for Minnesota Public Utilities Commission.

Stephen R. Melton, Acting General Counsel, Jerome M. Feit, Sol., Robert F. Shapiro, Washington, D.C., for respondent Federal Energy Regulatory Commission.

Before BRIGHT, ARNOLD and FAGG, Circuit Judges.

BRIGHT, Circuit Judge.

The State of Minnesota and the Minnesota Public Utilities Commission (collectively referred to as the MPUC) petition for review of orders1 of the Federal Energy Regulatory Commission (the Commission) approving a proposed amendment to the Coordinating Agreement among the Northern States Power Companies (NSP Companies). The MPUC contends that the Commission lacked jurisdiction to review the proposed amendment because the Coordinating Agreement does not establish a wholesale rate for the resale of electricity. We deny the petition and affirm the orders of the Commission.

I. Background.

The NSP Companies are three affiliated public utilities providing wholesale and retail electric service to customers in the Upper Midwest. NSP-Minnesota, the parent company, serves Minnesota, North Dakota, and South Dakota. NSP-Wisconsin and the Lake Superior District Power Company, subsidiaries of NSP-Minnesota, serve Wisconsin and the Upper Peninsula of Michigan. To achieve economies of scale, the NSP Companies develop and operate their respective generation and transmission facilities on an interconnected and integrated basis. The Companies accomplish this objective through their participation in a Coordinating Agreement, which establishes, among other things, procedures for sharing the costs of the entire system.2

On November 1, 1982, the NSP Companies filed with the Commission an amendment to the Coordinating Agreement. The amendment proposed a methodology for determining the rate of return on investment (or capital) as a component of the fixed costs shared by the Companies under the Coordinating Agreement. The proposed amendment included a fifteen percent rate of return on equity. The MPUC intervened and challenged the Commission's jurisdiction to review the proposed amendment. According to its brief, the MPUC challenges the Commission's jurisdiction in order to protect its interest in regulating retail electric rates and to avoid being bound by a federal determination as to rate of return on investment which will affect retail rates. The MPUC argues that the Commission exceeded its authority under the Federal Power Act and intruded upon retail ratemaking functions by accepting a filing that sets a rate of return on capital as part of a cost allocation agreement between affiliated power companies.

II. Discussion.

The issue in this case is whether, as the MPUC claims, the Commission exceeded its jurisdiction and usurped the retail ratemaking authority of the MPUC by accepting an amendment to the Coordinating Agreement which establishes a rate of return on capital. Under the Federal Power Act, the Commission is vested with exclusive authority to regulate wholesale rates for the resale of electric power in interstate commerce. See 16 U.S.C. Sec. 824(b) (1976 & Supp. V 1981);3 New England Power Co. v. New Hampshire, 455 U.S. 331, 340, 102 S.Ct. 1096, 1101, 71 L.Ed.2d 188 (1982); FPC v. Southern California Edison Co., 376 U.S. 205, 215-16, 84 S.Ct. 644, 651-52, 11 L.Ed.2d 638 (1964). In determining that it possessed jurisdiction to review the proposed amendment, the Commission found that the Coordinating Agreement among the NSP Companies established a wholesale rate for the resale of electric power in interstate commerce. The Commission's jurisdiction to review the proposed amendment, therefore, turns on the nature of the transactions provided for under the Coordinating Agreement.

The MPUC's challenge to the Commission's jurisdiction rests on its contention that the Coordinating Agreement serves simply as a mechanism for allocating costs among the NSP Companies and does not establish a wholesale rate for the resale of electricity. A wholesale rate, the MPUC points out, requires that there be a "sale of electric energy * * * for resale." 16 U.S.C. Sec. 824(d). The MPUC argues that the Coordinating Agreement does not provide for sales of electric energy between the NSP Companies and, therefore, cannot establish a wholesale rate. To demonstrate that the NSP Companies do not sell power to each other, the MPUC observes that NSP-Minnesota, which has the greatest generating capacity of the NSP Companies, does not purchase electric energy from its affiliates on a "steady, reliable basis." It also contends that the NSP Companies' failure to specify a price for a kilowatt or kilowatt hour further demonstrates that no sales transactions take place.

In evaluating the MPUC's claim that the Commission erroneously found the existence of a wholesale rate under the Coordinating Agreement, we note that our review of the Commission's orders is limited in scope. First, we are required to accept as conclusive the "findings of the Commission as to facts, if supported by substantial evidence." 16 U.S.C. Sec. 825l (b) (1976); see Otter Tail Power Co. v. FERC, 583 F.2d 399, 407 (8th Cir.1978), cert. denied, 440 U.S. 950, 99 S.Ct. 1431, 59 L.Ed.2d 639 (1979). In addition, we must defer to the Commission's judgment in making determinations within its area of administrative expertise. See E.I. du Pont de Nemours & Co. v. Collins, 432 U.S. 46, 54-57, 97 S.Ct. 2229, 2234-2235, 53 L.Ed.2d 100 (1977); FPC v. Florida Power & Light Co., 404 U.S. 453, 463, 92 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
734 F.2d 1286, 1984 U.S. App. LEXIS 22459, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-of-minnesota-by-its-attorney-general-and-minnesota-public-utilities-ca8-1984.