State of Mich. v. City of Allen Park

739 F. Supp. 1102, 31 ERC (BNA) 1901, 1990 U.S. Dist. LEXIS 7245, 1990 WL 85107
CourtDistrict Court, E.D. Michigan
DecidedJune 8, 1990
DocketCiv. A. 79-74681, 79-74682
StatusPublished
Cited by4 cases

This text of 739 F. Supp. 1102 (State of Mich. v. City of Allen Park) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State of Mich. v. City of Allen Park, 739 F. Supp. 1102, 31 ERC (BNA) 1901, 1990 U.S. Dist. LEXIS 7245, 1990 WL 85107 (E.D. Mich. 1990).

Opinion

MEMORANDUM OPINION AND ORDER

FEIKENS, District Judge.

Defendants City of Allen Park (“Allen Park”) and Ecorse Creek Pollution Abatement Drain No. 1 (“Ecorse Abatement Drainage District”) bring this motion to compel the Michigan Department of Natural Resources (“MDNR”) and the United States Environmental Protection Agency (“EPA”) to fund its share of a Sewer System Evaluation Survey (“SSES”). Defendants argue that the motion to compel funding is premised on my power to enforce the final judgment and order in this case. Final Order and Judgment, June 30, 1980. See State of Michigan v. City of Allen Park, 501 F.Supp. 1007 (E.D.Mich. 1980). MDNR and EPA oppose the motion, claiming that no federal court has jurisdiction to compel funding, that my orders did not address funding of the SSES, and that *1104 defendants have failed to exhaust administrative remedies. Additionally, EPA argues that the Clean Water Act § 201(i )(1) precludes the award of federal funds for SSES work.

Additionally, EPA moves to terminate my compliance orders of June 30, 1980, February 15, 1983, and October 3, 1983, and to dismiss the actions, alleging that the SSES was not contemplated in the orders, and thus defendants have complied fully by performing all obligations that the orders require.

I held a hearing on these matters on February 6, 1990. For the reasons set forth below, I now GRANT defendants’ motion and DENY EPA’s motion.

I. BACKGROUND

Although two prior opinions describe the history of this case, I will highlight briefly the relevant chronology. 1 In May, 1969, the Michigan Water Resources Commission studied the water quality in Ecorse Creek and found that the discharge of combined sewer overflows into the creek was the principal cause of its poor water quality. In wet weather, rain and snow melt overtaxed the sewer system and caused overflows which dumped untreated sewage into the creek basin.

In November of 1970, MDNR ordered the communities in the Ecorse Creek basin to correct the pollution problem. To further that goal, Wayne County Drain Commissioner, Charles Youngblood, authorized a study of the sewer system, Facility Planning Study: Pollution Abatement of Ecorse Creek, Element 2 — Combined Sewer Areas, Final Plan (Wayne County Drain Commissioner, February 1977).

The study recommended construction of a new sewer system to separate domestic sanitary sewage from storm runoff. The proposed remedy was formally selected for implementation by the North Branch of Ecorse Creek Drain Improvement Board on January 27, 1977, following a public hearing. The plan received wide public support, including the support of Allen Park.

On June 14, 1977, Allen Park Council passed a resolution approving the financing of drain improvements. The Wayne County Drain Commissioner approved the petition submitted by the cities of Allen Park, Dearborn Heights, Lincoln Park and Taylor; County of Wayne; and State of Michigan on October 19, 1977, finding that the project was necessary for public health and should be constructed.

EPA and MDNR tendered grants under the Federal Water Pollution Control Act Amendments of 1972, 33 U.S.C. § 1251, for the construction of the new sewer, system. Under the arrangement, EPA provided seventy-five per cent of the funding and MDNR provided five percent of the funding. The remaining twenty percent was allocated among the four municipalities that had originally petitioned for the pollution abatement project.

In 1978, the Ecorse Abatement Drainage District approved a proposed apportionment of costs. Allen Park, however, balked at the completion schedule for the project because of the significant outlays it was required to make. On December 12, 1979, a suit was filed against Allen Park seeking to require the city to proceed with the project according to schedule. On June 30, 1980, after a prolonged trial, I ordered Allen Park to proceed with funding and construction of the project. See State of Michigan v. City of Allen Park, 501 F.Supp. 1007 (E.D.Mich.1980). I retained jurisdiction to implement the order. Final Order and Judgment, June 30, 1980, at 2-3.

In 1981, Allen Park challenged the apportionment, but I held that it was proper. City of Allen Park v. Ecorse Pollution Abatement Drain No. 2 Drainage District, 518 F.Supp. 1079 (E.D.Mich.1981), aff'd, 708 F.2d 722 (6th Cir.1982), cert. denied, 462 U.S. 1111, 103 S.Ct. 2464, 77 L.Ed.2d 1340 (1983). Allen Park continued to delay. As a result, on February 15, 1983, I entered a detailed schedule of compliance. Allen Park argued, based on the report of an engineering firm they had *1105 hired, that methods other than the separation project were more cost effective. EPA studied the proposed alternatives and suggested at a conference held on May 10, 1983, that although two alternatives might be preferable, it could not guarantee funding for them and would not agree to abandon the separation project.

Allen Park formally requested modification of the June 30, 1980 order to allow implementation of alternative methods. I denied the motion, in part, because “every additional moment of delay is an additional moment where a known health hazard is permitted to continue to impact upon the health and enjoyment of life of those who live in and around the Ecorse Creek Drainage Basin.” State of Michigan v. City of Allen Park, 573 F.Supp. 1481, 1486 (E.D.Mich.1983). I further reasoned:

A known health hazard has been permitted to exist for over 13 years while various administrative and judicial proceedings interminably ground along their way. Now we have at hand a solution to the problem which all parties agree will help alleviate the problem. We have state and federal funding for the project. We have all of the communities involved, with the exception of Allen Park, well on their way or completed with implementing their portions of the project.

Id. at 1486 (emphasis added). 2

On October 3,1983,1 ordered, inter alia, that any party named in, or in any way connected with, this lawsuit was enjoined from instituting any litigation or administrative proceedings

A. which will have the effect of preventing or delaying any of the parties or their officers, agents, attorneys or employees from fully carrying out and complying with this court’s June 30, 1980 Final Order and Judgment and this court’s February 15, 1983 compliance schedule as both presently exist; and
B. which seeks to or has the effect of withdrawing grants or grant contracts for the project which is the subject matter of this litigation, or which seeks to rearrange grant priorities....

Injunction, Mandamus and Order, October 3, 1983, at 3-4.

Since my order, Allen Park has substantially completed its separation project. All that remains is the SSES.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
739 F. Supp. 1102, 31 ERC (BNA) 1901, 1990 U.S. Dist. LEXIS 7245, 1990 WL 85107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-of-mich-v-city-of-allen-park-mied-1990.