State of Georgia Department of Corrections v. Developers Surety and Indemnity Company

CourtCourt of Appeals of Georgia
DecidedOctober 28, 2013
DocketA13A0969
StatusPublished

This text of State of Georgia Department of Corrections v. Developers Surety and Indemnity Company (State of Georgia Department of Corrections v. Developers Surety and Indemnity Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State of Georgia Department of Corrections v. Developers Surety and Indemnity Company, (Ga. Ct. App. 2013).

Opinion

SECOND DIVISION BARNES, P. J., MILLER and RAY, JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. http://www.gaappeals.us/rules/

October 28, 2013

In the Court of Appeals of Georgia A13A0969. STATE OF GEORGIA DEPARTMENT OF CORRECTIONS v. DEVELOPERS SURETY AND INDEMNITY COMPANY.

RAY, Judge.

This case stems from a construction contract entered between the Georgia

Department of Corrections (“GDOC”) and Lewis Walker Roofing (“Walker

Roofing”) for the purpose of re-roofing certain buildings at the Valdosta State Prison.

After a nearly two-year long delay in completing the project, GDOC declared the

contract in default, and the payment and performance bonds issued by Developers

Surety and Indemnity Company (“Developers Surety”) for the benefit of GDOC as

obligee were invoked. Developers Surety then filed the present suit against GDOC,

alleging that GDOC breached the construction contract it entered into with Walker

Roofing. Developers Surety also sought a declaratory judgment that, as a result of GDOC’s breach of the construction contract, it had no obligation to perform its

obligations under the payment and performance bond it issued to Walker Roofing on

behalf of GDOC. GDOC filed a counterclaim for breach of contract. Both parties

filed cross-motions for summary judgment. In its motion for summary judgment,

GDOC argued that the doctrine of sovereign immunity barred Developers Surety’s

claims against it. GDOC appeals from the trial court’s order granting Developers

Surety’s summary judgment motion and denying GDOC’s summary judgment motion.

Finding no error, we affirm.

On appeal from the grant or denial of a motion for summary judgment, “this

Court conducts a de novo review of the evidence to determine whether there is a

genuine issue of material fact and whether the undisputed facts, viewed in the light

most favorable to the nonmoving party, warrant judgment as a matter of law.”

(Citation omitted.) Shekhawat v. Jones, __ Ga. __ (746 SE2d 89) (2013).

So viewed, the relevant evidence shows as follows. On April 25, 2008, GDOC

posted an “Invitation to Bid” for a construction project that involved replacing the

roofs on several buildings located at the Valdosta State Prison. On June 12, 2008,

GDOC awarded the project to Walker Roofing. The construction contract between

GDOC and Walker Roofing included two “no assignment” clauses prohibiting

2 Walker Roofing from assigning its performance or right to payment under the

contract.

As a prerequisite to contracting with GDOC, Walker Roofing was required to

obtain payment and performance bonds that would assure its performance under the

contract. Developers Surety issued payment and performance bonds to Walker

Roofing. Walker Roofing and Developers Surety had previously signed a general

agreement of indemnity in favor of Developers Surety that included a provision in

which Walker Roofing assigned to Developers Surety the company’s right to payment

under bonded contracts as security against any losses that Developers Surety might

suffer under a bond. GDOC is not a party to the indemnity agreement. The bonds

required Developers Surety, upon default of Walker Roofing, to “promptly remedy

the default or defaults or to promptly perform the [c]ontract in accordance with its

terms and conditions.” It also required Developers Surety to give GDOC notice

“within twenty-five (25) days after receipt of a declaration of default of the surety’s

election either to remedy the default or defaults promptly or to perform the contract

promptly.”

Walker Roofing began work at the Valdosta State Prison on December 1, 2008.

Pursuant to its construction contract, Walker Roofing was required to complete its

3 work within 150 consecutive calendar days; however, the work was not completed

as of September 23, 2010, when GDOC declared Walker Roofing in default. The

contract between Walker Roofing and GDOC states that Walker Roofing shall have

access to work areas on weekdays between 7:30 a.m. and 5:00 p.m. However, Walker

Roofing’s daily start time was delayed by at least thirty minutes and up to two-and-a-

half hours because the workers experienced difficulties gaining access to the prison

grounds. GDOC additionally required Walker Roofing to have their equipment

properly secured and the roofers off the project site by 4:30 p.m., not 5:00 p.m. as per

the contract. To exit the project site and secure their equipment by 4:30 p.m.,

however, the roofing crew had to stop work at 3:30 p.m. Work was further delayed

because Walker Roofing was prohibited from accessing more than one roof at a time,

GDOC assigned only one prison guard to monitor the roofing crew, and work was not

permitted when the assigned guard was unavailable due to sickness or vacation time.

On September 23, 2010, GDOC issued a formal notice of default with respect

to the performance of Walker Roofing, thus triggering Developers Surety’s

obligations under the performance bond. Developers Surety did not notify GDOC

within 25 days of receipt of GDOC’s notice of default regarding whether it would

remedy the default or perform the contract. However, on January 12, 2011,

4 approximately three months after the declaration of default, Developers Surety

offered to GDOC that it “could enter into a contract with Skyline for the completion

of the work on the Project (this process being sometime known as a ‘tender of

completion contractors’).” GDOC then contracted with Skyline to complete the

project. Prior to Walker Roofing’s default, Developers Surety had provided financial

assistance to Walker Roofing under the payment and performance bonds in the

amount of $577,118.60, and it additionally incurred $160,161.39 in costs and attorney

fees arising from its investigation of its liability, if any, under the default.

On July 12, 2011, Developers Suretys filed the present complaint against

GDOC for breach of contract and for a declaratory judgment that it had no obligation

under the payment and performance bond it issued to Walker Roofing on behalf of

GDOC. The parties filed cross-motions for summary judgment. After a hearing, the

trial court found that Developers Surety’s claims were not barred by sovereign

immunity and that GDOC had breached the construction contract as a matter of law.

Thus, it granted Developers Surety’s motion for summary judgment and denied

GDOC’s motion for summary judgment. In the same order, the trial court entered a

5 judgment in favor of Developers Surety in the amount of $577,118.60.1 GDOC

appeals from that order.

1. GDOC contends that the trial court’s denial of its summary judgment motion

was in error because Developers Surety was not a party to the construction contract

between GDOC and Walker Roofing and, thus, that the State’s waiver of sovereign

immunity for breach of contract did not apply to Developers Surety. We disagree.

“[S]overeign immunity is a threshold issue that the trial court [is] required to

address before reaching the merits of any other argument.” (Footnote omitted.)

Albertson v. City of Jesup, 312 Ga. App. 246, 248 (1) (718 SE2d 4) (2011). It is

axiomatic that “[t]he party seeking to benefit from the waiver of sovereign immunity

bears the burden of proving such waiver.” (Citations omitted.) Bd.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kennedy v. Georgia Department of Human Resources Child Support Enforcement
648 S.E.2d 727 (Court of Appeals of Georgia, 2007)
McWhirter Material Handling Co. v. Georgia Paper Stock Co.
164 S.E.2d 852 (Court of Appeals of Georgia, 1968)
Turner v. Mize
633 S.E.2d 641 (Court of Appeals of Georgia, 2006)
Argonaut Insurance v. C & S Bank of Tifton
232 S.E.2d 135 (Court of Appeals of Georgia, 1976)
Cotton States Mutual Insurance v. Citizens & Southern National Bank
308 S.E.2d 199 (Court of Appeals of Georgia, 1983)
Robinson v. GLOBAL RESOURCES, INC.
684 S.E.2d 104 (Court of Appeals of Georgia, 2009)
Board of Regents of University System of Georgia v. Tyson
404 S.E.2d 557 (Supreme Court of Georgia, 1991)
Crown Ford, Inc. v. Crawford
473 S.E.2d 554 (Court of Appeals of Georgia, 1996)
Board of Regents of the University System v. Doe
630 S.E.2d 85 (Court of Appeals of Georgia, 2006)
Albertson v. City of Jesup
718 S.E.2d 4 (Court of Appeals of Georgia, 2011)
Shekhawat v. Jones
746 S.E.2d 89 (Supreme Court of Georgia, 2013)
Nova Casualty Co. v. United States
69 Fed. Cl. 284 (Federal Claims, 2006)
DeKalb County School District v. Gold
734 S.E.2d 466 (Court of Appeals of Georgia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
State of Georgia Department of Corrections v. Developers Surety and Indemnity Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-of-georgia-department-of-corrections-v-developers-surety-and-gactapp-2013.