State Hwy. Dept. v. Milton Const. Co.

586 So. 2d 872, 1991 WL 183971
CourtSupreme Court of Alabama
DecidedAugust 23, 1991
Docket1900596, 1900731
StatusPublished
Cited by40 cases

This text of 586 So. 2d 872 (State Hwy. Dept. v. Milton Const. Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Hwy. Dept. v. Milton Const. Co., 586 So. 2d 872, 1991 WL 183971 (Ala. 1991).

Opinion

This case arises out of a contract dispute between Milton Construction Company, Inc., and the State of Alabama Highway Department. In Milton Construction Co. v. State Highway Dep't,568 So.2d 784 (Ala. 1990) ("Milton I"), we held that the clause in the contract between these parties, which authorized the Highway Department to withhold money as disincentive payments for projects not completed by the deadline, was void and unenforceable as a penalty.1 In that case we reversed the judgment of the trial court and remanded the case for further proceedings consistent with our opinion.

On remand, Milton Construction filed a motion for summary judgment based upon this Court's opinion in Milton I. The Highway Department then filed an amended counterclaim, seeking damages for the "road user costs"2 caused by Milton Construction's alleged breach of the contract and a motion in opposition to Milton Construction's motion for summary judgment. Milton Construction then filed a motion to dismiss the amended counterclaim. The trial court entered a judgment holding that the disincentive clause in the contract was void and that the Highway Department must reimburse Milton Construction the $534,000 withheld from payment under the disincentive clause in the contract, and the trial court dismissed the Highway Department's amended counterclaim. The trial court denied Milton Construction's motion for prejudgment interest. The court dismissed the Highway Department's amended counterclaim.

The Highway Department appealed on the grounds that the trial court erred in not allowing it to amend its counterclaim to seek actual damages under the contract and that the doctrine of sovereign immunity prohibits the Highway Department from reimbursing Milton Construction for the money it had withheld under the disincentive clause of the contract. Milton Construction filed a cross-appeal on the grounds that the trial court had erred in not granting its motion for the award of prejudgment interest. We affirm in part; reverse in part; and remand. *Page 874

I. User Costs
The Highway Department argues that the trial court erred because it dismissed the amended counterclaim, which sought a recovery of user costs allegedly caused by Milton Construction's breach of the contract. The Highway Department says that even though this Court held that the disincentive provision of the contract was void, the language of that provision still allows the Highway Department to prove and recover user costs caused by Milton's delay. The disincentive clause states as follows:

"The contractor's attention is directed to the fact that it is in the public's best interest to complete the project at the earliest possible date taking into account the traffic control plan and sequence of construction specified in the plans. The final completion of the entire project and final acceptance by the department must be accomplished within 330 calendar days [in the I-65 project; 210 in the I-59 project]."

Milton I, 568 So.2d at 786.

The Highway Department relies in large part on the decision in Cook v. Brown, 408 So.2d 143 (Ala.Civ.App. 1981). In Cook, the Court of Civil Appeals held that a "liquidated damages" provision contained in a contract between the parties was void as a penalty. The court reversed the trial court's judgment and remanded the case with instructions. In its opinion, the court stated that its finding that the liquidated damages provision was void did not prevent Cook from recovering actual damages caused by Brown's breach of the contract. The Highway Department urges this Court to apply Cook to this case and hold that although the disincentive clause was void, the Highway Department may amend its counterclaim to seek user costs caused by Milton Construction's delay in completing the contract. We hold, however, that Cook is distinguishable from this case.

In Milton I we held that the disincentive clause of the contract between Milton Construction and the Highway Department was void as a penalty and that it was not intended to provide "compensation for any delay caused to the Highway Department orto the public." Milton I, 568 So.2d at 791 (emphasis added). Unlike the contract in Cook, the instant contract contained a liquidated damages clause and the invalid disincentive clause. When the court in Cook invalidated the liquidated damages clause as a penalty, the parties were left to recover actual damages. Here, the Highway Department has already recovered under the default and liquidated damages clauses of the instant contract. Milton I, 568 So.2d at 786-87, 791. Now the Highway Department seeks to recover user costs in addition, on the ground that the contract provided that both the disincentive clause and the liquidated damages clause applied in case of deadline overruns.

We have already held the following:

"The recovery of 'all costs' by the Highway Department upon Milton's default in either the I-65 Project or the I-59 Project, along with the additional recovery of liquidated damages for delay, would certainly justly compensate the Highway Department for any injury; any further compensation would pass the limit of reasonableness."

Id. That is, the Highway Department's recovery under the contract's default provisions and liquidated damages provisions provide it with full compensation. Whether the additional damages are characterized as disincentives or as user costs, they would pass the "limit of reasonableness."

The Highway Department's recovery of such damages was specifically foreclosed by our decision in Milton I, wherein this Court held that the disincentive clause was a penalty and not a means of recovering damages for the travelling public. The same analysis applies to the claim for recovery of user costs, and the Highway Department is equally foreclosed. Although the Highway Department can not recover user costs in this case, we do not foreclose the possibility that the Highway Department may recover such costs caused by contract delays in highway construction contracts where the contract allows for such damages and those damages do not constitute a penalty. Therefore, we hold *Page 875 that the trial court did not err in dismissing the Highway Department's amended counterclaim seeking an award of user costs.

II. Sovereign Immunity
The Highway Department next argues that, because of the doctrine of sovereign immunity, it can not be made to pay the $534,000 that it withheld from Milton under the void disincentive provision of the contract. The Highway Department argues that any action that seeks to compel the state, or a state agency (e.g., the Highway Department), to perform any contract or to pay any debt is barred under Ala. Const., art. I, § 14. We disagree.

It is true that § 14 of the Constitution prevents a suit against the state as well as suits against its agencies. SeePhillips v. Thomas, 555 So.2d 81 (Ala. 1989); Rutledge v.Baldwin County Comm'n, 495 So.2d 49 (Ala. 1986). However, this Court has also recognized that there are certain established exceptions to the protection afforded the state or its agencies by sovereign immunity. See Ex parte Carter, 395 So.2d 65, 68 (Ala. 1981).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Corley v. Richardson
243 So. 3d 812 (Supreme Court of Alabama, 2017)
Woodfin v. Bender
238 So. 3d 24 (Supreme Court of Alabama, 2017)
Alabama State University v. Danley
212 So. 3d 112 (Supreme Court of Alabama, 2016)
State v. Hall
184 So. 3d 1029 (Court of Civil Appeals of Alabama, 2015)
Ex parte Jackson County Board of Education.
164 So. 3d 532 (Supreme Court of Alabama, 2014)
D.C. Pruett Contracting Co. v. Jackson County Board of Education
164 So. 3d 532 (Supreme Court of Alabama, 2014)
Health Care Authority for Baptist Health v. Davis
158 So. 3d 397 (Supreme Court of Alabama, 2013)
Alabama Department of Corrections v. Merritt
74 So. 3d 1 (Court of Civil Appeals of Alabama, 2010)
ALB. COMMONS PARTNERSHIP v. City Council
212 P.3d 1122 (New Mexico Court of Appeals, 2009)
Albuquerque Commons Partnership v. City Council of Albuquerque
2009 NMCA 65 (New Mexico Court of Appeals, 2009)
Ex Parte Alabama Dept. of Human Resources
999 So. 2d 891 (Supreme Court of Alabama, 2008)
Alabama Dept. of Transp. v. Harbert Intern., Inc.
990 So. 2d 831 (Supreme Court of Alabama, 2008)
Marous Bros. Construction, L.L.C. v. Alabama State University
533 F. Supp. 2d 1199 (M.D. Alabama, 2008)
S & M Equipment Co. v. Alabama Department of Transportation
978 So. 2d 718 (Supreme Court of Alabama, 2007)
Ex Parte Alabama Dept. of Transp.
978 So. 2d 718 (Supreme Court of Alabama, 2007)
Good Hope Contracting Co. v. Alabama Department of Transportation
978 So. 2d 17 (Supreme Court of Alabama, 2007)
ALA. DEPT. OF HUMAN RES. v. Ideal Truck Serv., Inc.
999 So. 2d 888 (Court of Civil Appeals of Alabama, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
586 So. 2d 872, 1991 WL 183971, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-hwy-dept-v-milton-const-co-ala-1991.