State Highway Commission v. DeLong Corp.

539 P.2d 1100, 22 Or. App. 436, 1975 Ore. App. LEXIS 1724
Court of Appeals of Oregon·Decided September 10, 1975·No. No. 59-323·Published

Opinion

FORT, J.

This is a declaratory judgment action. The principal questions between the parties were disposed of by this court in an opinion appearing at 9 Or App 550, 495 P2d 1215, Sup Ct review denied (1972), cert de[438] nied 411 US 965, rehearing denied 412 US 944 (1973), in which we affirmed the judgment of the trial court in favor of the plaintiff. Following the conclusion of that matter, defendant’s surety, Travelers Indemnity Company, paid on or about June 11, 1973, the sum of $4,036,540.80 in claimed satisfaction of that judgment. On that date plaintiff filed its Satisfaction of Judgment Pro Tanto “for the sum of $2,923,815.28 with certain additional interest, costs and disbursements * * * and of plaintiff’s attorney’s lien herein.” Thereafter, on May 1, 1974, defendants moved for an order “that the judgment entered herein on May 23,1969, has been fully satisfied.” After hearing arguments thereon the trial court in September 1974, entered its order granting the defendants’ motion. Plaintiff appeals.

This matter involves the construction of one provision of the judgment in relation to the narrow problem of interest after judgment upon prejudgment interest included in the decree, and the application, if any, to that judgment of ORS 82.010(1) (b).

Paragraph 3 of the judgment provides:

“Plaintiff shall be and hereby is granted judgment against the defendants and each of them in the amount of $1,719,864.19, bearing interest at the rate of 6% per annum on the respective portions thereof from the respective dates set forth below:
Bearing Interest AMOUNT From:
$ 278,554.38 June 22,1965
602,720.42 July 19,1965
242,647.01 Aug. 27,1965
21,062.83 Oct. 26,1965
19,719.74 Nov. 18,1965
69,412.50 Nov. 24,1965
9,356.05 Dec. 16,1965
[439]*4398,283.31 Feb. 7,1966
3,691.50 Feb. 15,1966
6,346.20 Mar. 14,1966
3,266.00 Apr. 14,1966
117,114.86 Aug. 29,1966
7,807.76 Sept. 14,1966
4,151.23 Sept. 16,1966
78,615.55 Oct. 22,1966
73,172.59 Nov. 22,1966
9,720.54 Dee. 22,1966
2,800.37 Feb. 15,1967
156,534.88 Mar. 16,1967
4,886.47 Apr. 5,1967
1,719,864.19”

It is agreed by the parties that the sole question is whether interest at the six per cent statutory rate runs on that prejudgment interest after the date of the judgment or whether it terminates on that date and no postjudgment interest accrues thereafter.

In their brief, defendants summarize their argument on this narrow issue as follows:

“The language of paragraph 3 of the declaratory judgment of May 23, 1969, is clear. It awards plaintiff judgment against the defendants <# * * in the amount of $1,719,864.19, bearing interest * * * on the respective portions thereof from the respective dates set forth below * * *\ "When this judgment is construed in light of the provisions of OES 82.010(1) (b), which provide that judgments for the payment of money will bear interest i# * * from the date of the entry thereof wiless some other date is specified therein * * (Emphasis supplied.) It is clear that plaintiff is not entitled to receive post-judgment interest on a sum representing the total of all interest accruing to the date of judgment.”

In essence, then, defendants assert that while plaintiff is entitled to interest prior to judgment on the [440] above 20 items as set forth in the judgment, supra, from the dates specified therein, it is not entitled to interest on that interest after the date of the judgment, but only to postjudgment interest on the aggregate principal of those 20 items, which together make up the figure of $1,719,864.19.

Plaintiff commission contends that under the judgment the prejudgment interest on the 20 items merges into the judgment and that postjudgment interest runs on the entire amount until payment. The amount of interest which had accrued on the 20 items computed as required under paragraph 3 as of the date of judgment of May 23,1969, was $355,724, according to plaintiff’s brief. This prejudgment interest was included in the amount paid by defendants into court on June 11, 1973. No postjudgment interest on that sum has been paid.

In construing the judgment we find it helpful by way of background to consider the letter opinion of the trial judge of January 31, 1969, which according to its terms constituted his findings of fact. In the course of that letter the court said:

ÉÉ# * * * *
“The Columbia River is one of the nation’s large rivers and the bridge was to be constructed across its estuary. The building of the substructure was subject to the problems of transversing several miles underwater, in a swift current, and complicated further by the ebb and flow of the tide. This project required vision and vigor on the part of all participants.
[441] ■ “In April, 1964, Plaintiff terminated Defendant’s contract basically for the failure of Defendant to remove and replace the bad concrete seal at Pier 169 and to prosecute with vigor the balance of the work at hand, the Court hereby finds that said cancellation was valid and proper.
“The Plaintiff re-advertised and re-let the contract and the substructure work was subsequently completed by another contractor, to the Plaintiff’s damage in the amount of $12,464,810.77, in the principal amount. This to draw interest from the respective dates expended by the Plaintiff, as per Exhibit ‘E’ attached to the Fifth Amended Complaint.
*
“However, the Plaintiff is entitled to an additional amount other than stated above, in the form of liquidated damages, occasioned by the delay caused by the Defendant, for a period of 476 days at $2,000.00 per day, or the amount of $952,000.00.
“Plaintiff notified the Defendant that they elected to take possession of certain materials and equipment on the job site at the time of the termination. This, Plaintiff had a right to do, under the terms of the contract, in order for the Plaintiff to turn over said materials and equipment to a subsequent contractor, and in computing the damages above Defendant was given credit for value of said materials and equipment.

Free access — add to your briefcase to read the full text and ask questions with AI

State Highway Commission v. DeLong Corp., 539 P.2d 1100, 22 Or. App. 436, 1975 Ore. App. LEXIS 1724 (Or. Ct. App. 1975).

539 P.2d 1100 (State Highway Commission v. DeLong Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Oregon, State Highway Com'n v. DeLong Corp.
495 P.2d 1215 (Court of Appeals of Oregon, 1972)
Gow v. Multnomah Hotel, Inc.
228 P.2d 791 (Oregon Supreme Court, 1951)
Brauer v. City of Portland
58 P. 861 (Oregon Supreme Court, 1899)
Rhodes v. Belchee
59 P. 117 (Oregon Supreme Court, 1899)
Graham v. Merchant
72 P. 1088 (Oregon Supreme Court, 1903)