State Ex Rel. Tucker County Solid Waste Authority v. West Virginia Division of Labor

668 S.E.2d 217, 222 W. Va. 588
CourtWest Virginia Supreme Court
DecidedJuly 17, 2008
Docket33809
StatusPublished
Cited by14 cases

This text of 668 S.E.2d 217 (State Ex Rel. Tucker County Solid Waste Authority v. West Virginia Division of Labor) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Tucker County Solid Waste Authority v. West Virginia Division of Labor, 668 S.E.2d 217, 222 W. Va. 588 (W. Va. 2008).

Opinions

DAVIS, Justice:

The petitioner herein, the Tucker County Solid Waste Authority (hereinafter “TCSWA”), requests this Court to issue a writ of prohibition against the respondent herein, the West Virginia Division of Labor (hereinafter “DOL”), to prevent the DOL from continuing administrative proceedings against it. Specifically, the TCSWA wishes to prohibit the enforcement of a DOL administrative order, entered June 29, 2007, which found the TCSWA did not pay certain temporary workers the prevailing wage and thus owes said workers additional wages and damages in the approximate amount of $199,760.30. In its petition to this Court, the TCSWA requests that we prohibit the enforcement of the hearing examiner’s order because, as alleged by the TCSWA, (1) the prevailing wage was improperly applied to employees of a public authority; (2) the prevailing wage was improperly applied to work that was never let to contract; and (3) the legislative history of the West Virginia Prevailing Wage Act (hereinafter “the Act”), W. [592]*592Va.Code § 21-5A-1, el seq., was not given deference. Upon a review of the parties’ arguments, the record presented for consideration, and the pertinent authorities, we find that the TCSWA was not required to pay the prevailing wage to the workers involved in this case and, accordingly, grant the requested writ of prohibition.

I

FACTUAL AND PROCEDURAL HISTORY

The facts underlying this original jurisdiction proceeding are as follows. In 2003, the Tucker County Solid Waste Authority (“TCSWA”) began preliminary work on an expansion of its landfill.1 To perform the excavation work for the new landfill cell, the TCSWA hired ten additional workers, from May until August, 2003. These employees performed the excavation work and transported the excavated dirt to existing areas of the landfill.2 While most of these workers were hired on a temporary basis, the TCSWA retained a few workers as permanent employees; the majority of those workers who did not become permanent employees were terminated between November, 2003, and January, 2004, although some of these workers were terminated earlier, between June and August, 2003. The above-described excavation work was not let to contract, and the workers hired to complete it were not paid prevailing wage because the TCSWA considered them to be temporary TCSWA employees.

On July 17, 2003, Delegate Mary M. Poling3 sent a letter to James R. Lewis,4 Commissioner of the West Virginia Division of Labor, alleging that “the Tucker County Solid Waste Authority may have violated the law when they hired temporary employees to do the construction on the landfill expansion,” and requesting an investigation of the matter. As a result of this correspondence, the West Virginia Division of Labor (“DOL”) began an investigation and issued a subpoena duces tecum to the TCSWA on September 17, 2003, for the payroll records of all employees who worked on the “Tucker County Landfill Expansion Project.” The TCSWA complied with this request. Thereafter, on or about March 30, 2004, the DOL corresponded with the TCSWA’s temporary employees who had worked on said expansion project and requested each of them to provide additional information to the DOL. In April, 2004, the DOL informed the TCSWA that it had concluded that nine of the TCSWA employees who had worked on the expansion project should have been paid prevailing wage. As a result, the DOL determined that the TCSWA owed these workers an additional $95,820.82 in addition to penalties in a like amount as provided by W. Va.Code § 21-5A-9(b) (1961) (Repl.Vol.2002), for a total due of $191,641.64.

Thereafter, the TCSWA requested and was granted an informal conference with the DOL to explain why it believed the West Virginia Prevailing Wage Act (“Act”) did not apply to its hiring of temporary workers to complete the excavation portion of the landfill expansion project. This meeting occurred on June 15, 2004, but no resolution was reached. Approximately nine months later, on March 8, 2005, the DOL determined that an additional TCSWA employee should have been paid the prevailing wage for his work on the landfill expansion project. Therefore, the DOL increased the total wages due and owing from the TCSWA to $99,880.15, or $199,760.30 with the addition of the like amount of damages for this sum.

[593]*593Ultimately, the DOL referred the matter to a hearing examiner, who issued “Preliminary Findings of Fact and Conclusions of Law and Order as to Further Proceedings,” on June 29, 2007. In an attempt to reconcile the various provisions of the Act, the hearing examiner concluded that “the Act was intended to apply to contracts of employment entered into by public authorities with persons for the specific purpose of such persons being engaged in the construction of public improvements, unless such work is for the specific purpose of making temporary or emergency repairs.” Insofar as the landfill expansion project was neither a temporary nor an emergency repair, the hearing examiner reasoned that the Act applied and that the temporary workers the TCSWA had hired to complete the excavation work thereon should have been paid the prevailing-wage. Additionally, the hearing examiner determined that further evidentiary proceedings would be necessary to finally resolve the dispute. Among the areas identified by the hearing examiner as requiring further factual development were the precise nature and type of the employment of the workers involved herein; whether the penalty provisions of W. Va.Code § 21-5A-9(b) applied to a direct employer scenario; and whether, if the penalty provisions did apply, the “honest mistake” exception of W. Va.Code § 21-5A-9(b) would relieve the TCSWA of liability for the prevailing wages not paid.

Following these rulings, the TCSWA filed a petition for writ of prohibition with this Court seeking to prohibit the further eviden-tiary proceedings recommended by the hearing examiner. By order entered January 10, 2008, this Court issued a rule to show cause. Thereafter, the West Virginia State Building and Construction Trades Council, AFL-CIO (hereinafter “Trades Council”), moved to intervene as a party respondent in this proceeding and was granted intervenor status by order entered February 13, 2008. In addition, the Kanawha Valley Builders Association (hereinafter “Association”) moved for leave to appear in the case as Amicus Curiae; this Court granted the Association’s motion by order entered February 13, 2008.5

II.

STANDARD FOR ISSUANCE OF WRIT

This ease is before the Court upon a petition for a writ of prohibition. When considering whether a prohibitory writ should issue in a particular ease, we employ the following standard:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mendoza v. Fonseca McElroy Grinding Co., Inc.
492 P.3d 993 (California Supreme Court, 2021)
SER Betty J. Almond v. Hon. Rudolph Murensky, Judge, and Pfizer, Inc.
794 S.E.2d 10 (West Virginia Supreme Court, 2016)
Gregory Grim v. Eastern Electric
West Virginia Supreme Court, 2014
Grim v. Eastern Electric, LLC
767 S.E.2d 267 (West Virginia Supreme Court, 2014)
State of West Virginia v. John J. Moffit
741 S.E.2d 860 (West Virginia Supreme Court, 2013)
In Re Chevie V.
700 S.E.2d 815 (West Virginia Supreme Court, 2010)
In the Interest of F. F.
695 S.E.2d 723 (Court of Appeals of Georgia, 2010)
STATE EX REL. MATIN v. Bloom
674 S.E.2d 240 (West Virginia Supreme Court, 2009)
River Riders, Inc. v. Steptoe
672 S.E.2d 376 (West Virginia Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
668 S.E.2d 217, 222 W. Va. 588, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-tucker-county-solid-waste-authority-v-west-virginia-division-wva-2008.