State Ex Rel. Mobil Corp. v. Gaughan

563 S.E.2d 419, 211 W. Va. 106, 2002 W. Va. LEXIS 35
CourtWest Virginia Supreme Court
DecidedApril 25, 2002
Docket30314
StatusPublished
Cited by13 cases

This text of 563 S.E.2d 419 (State Ex Rel. Mobil Corp. v. Gaughan) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Mobil Corp. v. Gaughan, 563 S.E.2d 419, 211 W. Va. 106, 2002 W. Va. LEXIS 35 (W. Va. 2002).

Opinion

*108 PER CURIAM.

Petitioner Mobil Corporation 1 seeks extraordinary relief from a February 26, 2002, Trial Scheduling Order 2 entered by the Circuit Court of Kanawha County in connection with certain asbestos-based personal injury cases that have been amassed under West Virginia Trial Court Rule (“TCR”) 26.01. Mobil argues that the procedures contemplated by the lower court in connection with bringing the asbestos eases to trial will, as a matter of certainty, result in a denial of its Due Process rights if trials ensue under the outlined, but as yet unfinalized, trial procedures. Upon our full review of this matter, we do not find that Mobil has met the requirements for entitlement to either a writ of prohibition or a writ of mandamus. Accordingly, the requested writs for extraordinary relief are hereby denied; however, due to the inherent complexities involved with the management of these asbestos cases, we proceed to set forth certain observations and cautionary concerns for the trial court’s consideration and use.

I. Procedural Background

This matter arises in connection with the grouping of presumably several thousands 3 of asbestos personal injury claims under the provisions of TCR 26.01. In addition to addressing the propriety of these cases proceeding under TCR 26.01 in State ex rel. Allman v. MacQueen, 209 W.Va. 726, 661 S.E.2d 369 (2001), we outlined a fourteen-point directive for the trial court in connection with the management of these cases. See id. at 732-36, 551 S.E.2d at 375-378. However, before those directives could be fully implemented, Mobil sought relief from this Court 4 in connection with the trial court’s intent to use a mass trial format, the prospective application of various tidal groupings, and the use of certain measures for calculating damages. Much of the relief sought by Mobil was previously considered and rejected in the Allman decision. For example, Mobil previously raised the argument, which we rejected, that both Rule 42 of the West Virginia Rules of Civil Procedure and the cases construing that rule were controlling. See Allman, 209 W.Va. at 731, 551 5.E.2d at 374 (noting that “[bjecause the provisions of TCR 26.01 control the underlying civil action, we do not view this matter as one affected by case law interpreting various rules of civil procedure, including Rules 20, 23, or 42, which respectively address issues of joinder, class action, and consolidation”).

At the time Mobil filed its petition for relief in late December 2001, the only ruling that had been issued by Judge Gaughan was a “Report,” which was entered on September 6, 2001. As an initial matter, Judge Gaughan concluded that “because of the very complicated intertwining of plaintiffs’ attorneys, multiple defendants and their defense attorneys, varying exposures to asbestos and different theories of liability, it is futile to continue to pursue small all-issues trials over a long period of time as contemplated by the current trial schedule.” 5 After discussing the use of mediation to resolve these cases and indicating that mediation would be addressed through a separate order 6 and *109 would be scheduled to occur between October 1, 2001, and March 4, 2002, 7 Judge Gaughan provided for a June 24, 2002, mass trial date. Under the trial plan described in the Report, three judges and three juries would be convened for the purpose of resolving “issues that are common to all or almost all of the parties.” Following this initial phase of trying common issues, the trial court contemplated at the time of the September 6, 2001, Report that “additional juries wfould] be picked to try the issues of exposure/causation and damages.” Based on the history of previous mass trials, Judge Gaughan anticipated that “through the elimination of parties during the mediation and the jury trial process ..., the number of litigants would be drastically reduced within two months of the initial verdict on liability.” At such time, the trial court speculated that it might attempt to use a damage matrix for purposes of the unresolved cases. 8 Appreciative of both the potential unworkability of or the need to completely discard the matrix concept, Judge Gaughan stated that “it is the intention of the Court to continue to try cases to jury verdict until there are no unresolved trials.” After discussing the use of a unified numbering system for documents and a method for dealing with previously-ruled upon motions, Judge Gaughan ended the Report by observing that “the trial plan has not been solidified.” 9

In late December 2001, Mobil sought relief from this Court based on the approach outlined by Judge Gaughan in the September 6, 2001, Report. Mobil asked this Court to vacate the September 6, 2001, ruling on the grounds that the trial court’s decision to “consolidate] thousands of unrelated individual asbestos personal injury claims into a single trial was arbitrary and capricious” and that such decision denied Mobil its right to Due Process and Equal Protection. Mobil challenged the trial court’s refusal to conduct evidentiary hearings on the issue of whether these claims could be grouped together and still provide a fair determination of the issues presented, as well as the contemplated use of a punitive damage matrix. Mobil further alleged that the trial court was thwarting its “efforts to secure review” by “failing to set forth specifically the procedures to be used in the consolidated trial.”

In response to Mobil’s request for relief and the rule to show cause, Judge Gaughan issued the February 26, 2002, Trial Scheduling Order. In that order, the trial court further developed some of the ideas outlined in the September 6, 2001, Report. To illustrate, the trial court provided additional details regarding the format to be used at the September 23, 2002, trial. 10 Three simultaneous trial groupings are to proceed simultaneously, with the object of determining issues solely related to the fault of the various defendants. The trial groupings represent, in generalized fashion, the various causes of action alleged by the plaintiffs: (1) product liability claims; (2) premises liability claims; and (3) deliberate intent causes of action asserted under West Virginia Code § 23-4-2 (1994) (Repl.Vol.1998). The scheduling order indicates that interrogatories will be submitted to the three juries to permit individualized findings of liability for each defendant. *110 After the liability trials have been completed, new juries will be selected for mini-trials that will be convened to resolve issues of causation and damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SER J.C., a minor v. Hon. James P. Mazzone, Judge
772 S.E.2d 336 (West Virginia Supreme Court, 2015)
State Ex Rel. Nationwide Mutual Insurance v. Kaufman
658 S.E.2d 728 (West Virginia Supreme Court, 2008)
In Re Tobacco Litigation
624 S.E.2d 738 (West Virginia Supreme Court, 2005)
State Ex Rel. Termnet Merchant Services, Inc. v. Jordan
619 S.E.2d 209 (West Virginia Supreme Court, 2005)
Norfolk Southern Railway Co. v. McGraw
71 F. App'x 967 (Fourth Circuit, 2003)
State ex rel. McCaffery v. Hutchison
585 S.E.2d 52 (West Virginia Supreme Court, 2003)
In Re West Virginia Rezulin Litigation
585 S.E.2d 52 (West Virginia Supreme Court, 2003)
Mobil Corp. v. Adkins
537 U.S. 944 (Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
563 S.E.2d 419, 211 W. Va. 106, 2002 W. Va. LEXIS 35, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-mobil-corp-v-gaughan-wva-2002.