State ex rel. Eureka Cedar Lumber & Shingle Co. v. Superior Court

182 P. 607, 107 Wash. 620, 1919 Wash. LEXIS 801
CourtWashington Supreme Court
DecidedJuly 22, 1919
DocketNo. 15436
StatusPublished

This text of 182 P. 607 (State ex rel. Eureka Cedar Lumber & Shingle Co. v. Superior Court) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State ex rel. Eureka Cedar Lumber & Shingle Co. v. Superior Court, 182 P. 607, 107 Wash. 620, 1919 Wash. LEXIS 801 (Wash. 1919).

Opinion

Fullerton, J.

This is an application made originally in this court for a writ of prohibition against the superior court of Pierce county requiring it to desist and refrain from certain described acts in a receivership proceeding. An alternative writ was issued upon the filing’ of the application, to which the trial court has made return. The cause is before us [621]*621on the question whether the alternative writ shall be made peremptory.

The record in this court is in many respects incomplete and unsatisfactory, making the pertinent facts somewhat difficult to gather. The facts are, however, as we understand them, in substance, these: The defendant Martinolich Ship Building Company, a corporation organized under the laws of this state, contracted to build for the Dockton Motorship Company, a corporation organized in another state, a steam schooner. The vessel was partially completed by the Martinolich Company at its own yards in Pierce county, after which it was moved to the yards of the Foundation Company, in the same county, where work thereon was continued by the Dockton Motorship Company; the Martinolich Company in the meantime having become insolvent. During the time the Martinolich Company had possession of the vessel it incurred large obligations to divers persons for materials used in the vessel’s construction, which it did not meet, among which was an obligation to the applicant herein, the Eureka Cedar Lumber and Shingle Company. The Eureka Company claims the balance due on the account to be $7,604.12, although the amount is disputed by the owner of the vessel. On May 3, 1919, the applicant, claiming a lien upon the vessel under the provisions of § 1182 of the code (Remington’s), began an action in the superior court of Pierce county to recover the sum named and to foreclose the lien. ' It made parties defendant the Martinolich Company, one Egil Naesheim, and the Dockton Motorship Company. In its complaint it alleged facts showing the obligation of the Martinolich Company to it, its right of lien on the vessel, the insolvency of the Martinolich Company, and further alleged that the vessel was then exposed to the weather and was deteriorating on account [622]*622thereof, and that such deterioration would amount, during the summer season of 1919, to forty per cent of the actual value of the vessel; that the vessel was only partially completed; that there was no adequate fire protection for the vessel and that its security was subject to serious loss, risk and hazard. It alleged that there were numerous other materialmen having unpaid claims for materials furnished and which were used in the construction of the vessel; that work had ceased on the vessel and that there was no likelihood of such work being resumed. It further alleged that an emergency existed for the appointment of a receiver.

At the time of the filing of the complaint, there was also filed by the attorney representing the plaintiff the answer of the Martinolich Company, which answer admitted all of the allegations of the complaint and joined in the prayer for the appointment of a receiver. On the showing made, the trial court appointed a receiver, fixing his bond in the sum of $5,000, and directing that he forthwith take possession of the vessel. It was further ordered that the defendants appear before the court on June 4, 1919, and there show cause, if any they had, why the appointment of the receiver should not be confirmed and his appointment continued in force until the final hearing of the cause.

The receiver qualified by giving the bond directed and immediately took possession of the vessel, appointing a keeper therefor whom he contracted to pay at the rate of five dollars per day. On June 28, 1919, the receiver made a report to the court to the effect that he found representatives of the owner of the vessel in its possession doing work thereon looking to its completion, and “having no desire to inconvenience the owner, has permitted the representatives of said owner to continue said work of completing said vessel, [623]*623but subject, however, at all times, to the possession and control by your receiver,” estimating that the time required for the completion of the vessel would be about three weeks. The receiver further reported that there were valid liens and claims against the vessel in the neighborhood of $40,000; that he believed that such claims would be adjusted and paid by the owners before any great length of time, but believed it unsafe to allow the vessel to go uninsured, and therefore prayed that he be authorized to insure it as the representative of the creditors, in the sum of $50,000. On the filing of the report, the court made an order confirming the receiver’s acts, and directing that he insure the vessel in the sum named. This order was made without notice to the owner of the vessel or to the owner’s representatives found in its possession. On June 4,1919, the owner appeared in the proceeding, at which time, by agreement of the parties, the hearing on the question whether the temporary appointment of the receiver should be made permanent was continued until June 19, 1919.

Between the time of the commencement of the action and June 19,1919, a number of persons obtained leave of court and intervened in the action, claiming obligations due them from the Martinolich Company for materials and labor furnished and used in the construction of the vessel, the several amounts of which they asked to have decreed to be a lien upon the vessel and that the vessel be sold in satisfaction thereof. These claims' aggregated $18,859.33.

On June 19, 1919, a hearing was had on the show cause order of the court, at which time the Dockton Motorship Company moved to quash the order appointing the receiver on the ground that it was made upon a “fraudulent and collusive showing.” The court did not rule upon the motion directly. It found [624]*624from the evidence given at the hearing that certain of the claims had been paid, leaving a balance of $18,094.34; that of this sum the claim of George Broom for $4,000 was not due because he had not completed the contract on which the same was payable, and that the owner ivas willing to deposit the sum in court to be paid to Broom when the same should be earned; that the remaining claims were disputed by the owner, and that the owner offered in open court to give a bond in such sum as the court might fix, with sureties to be approved by the court, conditioned to pay to the claimants such sums as the court might adjudge to be due thereon, together with their proper costs and charges. In addition to the foregoing recitals, it appeared that the owners had expended in excess of the sum of $360,000 in constructing the vessel; that it was nearing completion and was, or could be, chartered for ocean-going freight, and that to tie up the vessel pending the determination of the plaintiff’s and interveners’ actions would cause the owners great and irreparable losses. The court thereupon made and signed the following order:

“ (1) That the clerk of this court be, and he hereby is, instructed and directed to cause to be certified and retain the said check payable to George Broom, in the said sum of four thousand ($4,000) dollars, until further order of this court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Washington Iron Works Co. v. Jensen
28 P. 1019 (Washington Supreme Court, 1892)
Thompson v. Allen
106 P. 173 (Washington Supreme Court, 1910)
Kalb-Glibert Lumber Co. v. Cram
107 P. 381 (Washington Supreme Court, 1910)
Kalb-Glibert Lumber Co. v. Cram
111 P. 1050 (Washington Supreme Court, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
182 P. 607, 107 Wash. 620, 1919 Wash. LEXIS 801, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-eureka-cedar-lumber-shingle-co-v-superior-court-wash-1919.