State Ex Rel. Drabik v. Martz

451 N.W.2d 893, 1990 Minn. App. LEXIS 211, 1990 WL 16601
CourtCourt of Appeals of Minnesota
DecidedFebruary 27, 1990
DocketC6-89-1620
StatusPublished
Cited by6 cases

This text of 451 N.W.2d 893 (State Ex Rel. Drabik v. Martz) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Drabik v. Martz, 451 N.W.2d 893, 1990 Minn. App. LEXIS 211, 1990 WL 16601 (Mich. Ct. App. 1990).

Opinion

OPINION

HUSPENI, Judge.

Appellant Timothy D. Martz (“Martz”) seeks review of the trial court’s preliminary injunction prohibiting construction of a 600+ foot radio tower near the boundary waters canoe area (“BWCA”) pending trial on the merits of an action pursuant to the Minnesota Environmental Rights Act (“MERA”), Minn.Stat. ch. 116B (1988). We affirm.

FACTS

In 1986, Martz began searching for a site in northern Minnesota from which to broadcast 100,000 watts of FM radio signal. Martz states an interest in serving Cook County and Grand Marais, Minnesota. The criteria established by him, however, evidence a focus on the Thunder Bay, Ontario, radio market also.

Martz sought to lease a site owned by the Department of Natural Resources (“DNR”), which opposed the tower and refused to lease space to Martz. Martz then *895 purchased a 40-acre tract on a nearby summit, one of the highest in the state. Over 95% of Cook County land is owned by government entities and Martz’ site is virtually surrounded by the BWCA, Judge C.R. Magney State Park and other parkland areas with outdoor recreational and wilderness uses. The primary economic activities in Cook County are timber-related industries and tourism.

Martz’ proposed tower would be approximately 2600 feet above sea level, or about 1000 feet higher than the average elevation of the surrounding terrain. Because of the tower’s height, a conditional use permit from Cook County was required.

The minutes of the public hearing before the Cook County Planning Commission on June 8, 1988, indicate substantial public opposition. The powerful radio station would broadcast not only to northeastern Minnesota, but to parts of Ontario, Michigan and Wisconsin. The primary benefit to Cook County residents would be the payroll and capital investment made by Martz. The tower site is closer to Ontario than it is to Grand Marais. Despite opposition, the Cook County Board of Commissioners granted the permit with one condition, that the proposed 2000 gallon diesel fuel storage tank (to run the generators which would power the station) be buried underground.

Harry F. Drabik (“Drabik”), a north shore resident, obtained counsel and in July of 1989, after other attempts to block construction had failed, served the summons and complaint to initiate this suit under MERA. On August 10, 1989, the parties appeared for a hearing on a temporary injunction sought by Drabik. The trial court read memoranda, heard short arguments, recessed very briefly and issued from the bench its decision that an injunction should be granted pending trial on the merits. The trial court also granted Martz’ request for an expedited trial, eventually scheduled for less than two months after the injunction hearing. Martz appealed the grant of temporary injunction. Trial on the merits has not occurred.

ISSUES

1. Did the trial court make findings adequate to permit review?

2. Did the trial court err in granting this temporary injunction?

3. Did the trial court err in requiring a $1,000 bond?

ANALYSIS

Although Martz argues the merits of his entire case, we are limited in our review to determining whether the preliminary injunction and bond were proper.

I.

In granting interlocutory injunctions, the trial court shall set forth findings of fact and conclusions of law. Minn.R.Civ.P. 52.-01 (Supp.1989). The findings and conclusions may be stated orally rather than written and findings shall not be set aside unless clearly erroneous. Id. Martz asserts that the trial court did not make findings. We disagree.

Five factors must be considered by the trial court to determine whether to grant a temporary injunction. They are:

(1) The nature * * * of the relationship between the parties * * *.
(2) The harm to be suffered by [appellant] if the temporary restraint is denied as compared to that inflicted on [respondent] if the injunction issues pending trial.
(3) The likelihood that one party or the other will prevail on the merits * * *.
(4) The aspects of the fact situation, if any, which permit or require consideration of public policy expressed in statutes
(5) The administrative burdens involved in judicial supervision and enforcement of the temporary decree.

Dahlberg Brothers, Inc. v. Ford Motor Co., 272 Minn. 264, 274-75, 137 N.W.2d 314, 321-22 (1965).

The transcript discloses that the trial court found the proposed tower would present the potential for significant visual impact which would impair the wilderness *896 setting and cause a potential risk to plant and animal life. The trial court held that Drabik had presented a prima facie case showing the need for an injunction. The trial court further held that Martz’ affidavits did not rebut Drabik’s prima facie case. The trial court found that other feasible locations may exist, that construction could lead to irreparable harm and that environmental considerations outweigh the risks and costs of delay to Martz.

If the record were incapable of meaningful review, we would remand for further findings. See, e.g., Oxford Development, Inc. v. Ramsey County, 417 N.W.2d 319, 321 (Minn.Ct.App.1988). However, the record shows that the trial court adequately applied the appropriate legal factors to the facts. Sunny Fresh Foods v. Microfresh Foods, 424 N.W.2d 309, 310-11 (Minn.Ct.App.1988). We will not engage in de novo review of a temporary injunction. Id.

Here, the trial court’s statements clearly demonstrate that it considered the risks to the environment, the plaintiff’s likelihood of success on the merits, and any alternatives to the action proposed, and that it then balanced the likelihood of irreparable harm to each of the parties. The trial court then determined that the risk of harm to Martz was not sufficient to justify disturbing the status quo pending resolution of the issues at a trial on the merits. The record before this court is adequate and meaningful review is possible.

II.

A temporary injunction may be granted to preserve the status quo pending trial on the merits. Miller v. Foley, 317 N.W.2d 710, 712 (Minn.1982). The trial court’s ruling on the temporary injunction is an exercise of discretion which shall not be disturbed unless clearly abused. Eakman v. Brutger, 285 N.W.2d 95, 97 (Minn. 1979). On review the facts will be viewed favorably to the party who prevailed below. Krueger v. Washington Federal Savings Bank,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jeffrey A. August, Relator v. Chisago County Board of Commissioners
868 N.W.2d 741 (Court of Appeals of Minnesota, 2015)
Michels v. Kozitza
610 N.W.2d 368 (Court of Appeals of Minnesota, 2000)
Williams Pipeline Co. v. Soo Line Railroad
597 N.W.2d 340 (Court of Appeals of Minnesota, 1999)
State Ex. Rel. Wacouta Township v. Brunkow Hardwood Corp.
510 N.W.2d 27 (Court of Appeals of Minnesota, 1993)
Central Baptist Theological Seminary v. City of New Brighton
487 N.W.2d 528 (Court of Appeals of Minnesota, 1992)
Krmpotich v. City of Duluth
474 N.W.2d 392 (Court of Appeals of Minnesota, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
451 N.W.2d 893, 1990 Minn. App. LEXIS 211, 1990 WL 16601, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-drabik-v-martz-minnctapp-1990.